type: "Promise Ledger"
title: "ACME Solar Holdings Ltd: what management promised, and what happened"
description: "28 statements by ACME Solar Holdings Ltd's management, each checked against the company's later filings: 4 kept, 2 slipped, 16 pending, 6 unverifiable."
resource: "https://eqdoc.com/stock/ACMESOLAR"
tags: ["promise ledger","management guidance","india","acmesolar"]
sources: [{"resource":"https://eqdoc.com/pdf/ann/7451477.pdf"},{"resource":"https://eqdoc.com/pdf/ann/7095273.pdf"},{"resource":"https://nsearchives.nseindia.com/corporate/ACMECS_29072026204105_InvestorPresentation.pdf"},{"resource":"https://nsearchives.nseindia.com/corporate/ACME122002_04022026202011_Intimation-Transcript-04022026.pdf"},{"resource":"https://nsearchives.nseindia.com/corporate/ACME122002_10112025120439_Intimation.pdf"},{"resource":"https://nsearchives.nseindia.com/corporate/ACME122002_01082025192716_Intimation.pdf"},{"resource":"https://nsearchives.nseindia.com/corporate/ACMESOLAR_29112024164833_Intimation.pdf"}]
generated: {"by":"process:eqdoc-promise-audit","at":"2026-10-07"}
stale_after: "2027-01-15"
x-eqdoc-symbol: "ACMESOLAR"
x-eqdoc-counts: {"kept":4,"slipped":2,"missed":0,"pending":16,"unverifiable":6}
---

# How to read this

Each entry is something management said it would do, when it said it, and whether the company's later filings show it happened.
- **Kept**: a later filing shows it done. **Slipped**: done late or in part. **Missed**: the deadline passed without it.
- **Pending**: the deadline has not come, or no later filing yet speaks to it. **Unverifiable**: no filing could settle it.
- Evidence is either a sentence built from figures the company filed, or a quote from a later company document, as marked.

# Promises

## 2026-10-28 · Increase the share of central offtakers to 84% from 67%.: Unverifiable

- Said: Share of Central Offtakers to increase to 84% from present 67%, which is expected to further reduce DSO days
- By: Company presentation, Investor presentation, 28 Oct 2026
- Verdict: Unverifiable
- Evidence: We could not match this promise to a figure, and no later call settles it.
- Filing: <https://eqdoc.com/pdf/ann/7451477.pdf> (page 17)

## 2026-10-28 · Secure INR 1,500+ Cr revenue lock-in for partial sale of FY28 BESS capacity.: Pending

- Said: INR 1,500+ Cr revenue lock-in for partial sale of FY28 BESS capacity till date and balance to be tied up through future bids
- By: Company presentation, Investor presentation, 28 Oct 2026
- Due: FY28
- Verdict: Pending
- Evidence: Not due until 31 Mar 2028, after the latest results; later ones will show.
- Filing: <https://eqdoc.com/pdf/ann/7451477.pdf> (page 5)

## 2026-10-28 · Target a portfolio of 20 GW generation capacity and 70 GWh BESS capacity by 2032.: Pending

- Said: Target to have a portfolio of 20 GW generation capacity and 70 GWh BESS capacity by 2032
- By: Company presentation, Investor presentation, 28 Oct 2026
- Due: 2032
- Verdict: Pending
- Evidence: Not due until 31 Dec 2032, after the latest results; later ones will show.
- Filing: <https://eqdoc.com/pdf/ann/7451477.pdf> (page 23)

## 2026-10-28 · Target to maintain Net Debt to Run-Rate EBITDA under approximately 5.5x on an operational portfolio basis.: Unverifiable

- Said: Net Debt/Run-Rate EBITDA targeted to be under ~5.5x on operational portfolio basis
- By: Company presentation, Investor presentation, 28 Oct 2026
- Verdict: Unverifiable
- Evidence: We could not match this promise to a figure, and no later call settles it.
- Filing: <https://eqdoc.com/pdf/ann/7451477.pdf> (page 16)

## 2026-07-29 · Achieve cumulative BESS commissioning of 10,959 MWh across quarters through Q4 FY27.: Pending

- Said: Cumulative Commissioning (MWh) 3,109 5,009 9,459 10,959
- By: Company presentation, Investor presentation, 29 Jul 2026
- Due: Q4E FY27
- Verdict: Pending
- Evidence: Not due until 31 Mar 2027, after the latest results; later ones will show.
- Filing: <https://eqdoc.com/pdf/ann/7095273.pdf> (page 20)

## 2026-07-29 · Commission cumulative 10+ GWh BESS capacity by FY27.: Pending

- Said: Revised upward guidance to commission cumulative 10+ GWh BESS capacity by FY27
- By: Company presentation, Investor presentation, 29 Jul 2026
- Due: by FY27
- Verdict: Pending
- Evidence: Not due until 31 Mar 2027, after the latest results; later ones will show.
- Filing: <https://eqdoc.com/pdf/ann/7095273.pdf> (page 7)

## 2026-07-29 · Target to build a portfolio of 10 GW generation capacity by 2030.: Pending

- Said: Target to have a portfolio of 10 GW generation capacity and 25 GWh BESS capacity by 2030
- By: Company presentation, Investor presentation, 29 Jul 2026
- Due: by 2030
- Verdict: Pending
- Evidence: Not due until 31 Dec 2030, after the latest results; later ones will show.
- Filing: <https://eqdoc.com/pdf/ann/7095273.pdf> (page 21)

## 2026-07-29 · Target to commission approximately 1.5 GW renewable energy capacity comprising FDRE and Hybrid projects in FY27.: Pending

- Said: Target to commission: • ~1.5 GW renewable energy capacity comprising FDRE and Hybrid projects
- By: Company presentation, Investor presentation, 29 Jul 2026
- Due: FY27
- Verdict: Pending
- Evidence: Not due until 31 Mar 2027, after the latest results; later ones will show.
- Filing: <https://nsearchives.nseindia.com/corporate/ACMECS_29072026204105_InvestorPresentation.pdf> (page 19)

## 2026-07-29 · Net Debt to EBITDA Target: Pending

- Said: Net Debt/Run-Rate EBITDA targeted to be under ~5.5x on operational portfolio basis
- Verdict: Pending
- Filing: <https://nsearchives.nseindia.com/corporate/ACMECS_29072026204105_InvestorPresentation.pdf>

## 2026-01-30 · BESS commissioning guidance is targeted at 10 GWh by CY2027.: Pending

- Said: As a strategy, we are fast tracking BESS installment of 10 gigawatt of our FDRE projects by calendar year 2027, to unlock value early.
- By: Rajat Kumar Singh, Q3 FY26 earnings call
- Verdict: Pending
- Evidence: Not due until 31 Dec 2027, after the latest results; later ones will show.
- Filing: <https://nsearchives.nseindia.com/corporate/ACME122002_04022026202011_Intimation-Transcript-04022026.pdf> (page 6)

## 2025-11-10 · BESS capacity installation: Kept

- Said: total BESS orders to 5.1 gigawatt hour till date, which is expected to get installed in a phased manner starting in Q4 FY‘26.
- Due: Q4 FY26
- Verdict: Kept
- Later filing says (2026-05-08): ~2.3 GWh BESS operationalized in phases from Feb’26 till May’26 under 3 project sites, has begun generating revenue under merchant/short term peak power contracts
- Filing: <https://nsearchives.nseindia.com/corporate/ACME122002_10112025120439_Intimation.pdf>

## 2025-11-10 · Debt interest rate reduction: Kept

- Said: In this project where we have reached 8.4%, it is shortly likely to be reduced to 8%.
- Verdict: Kept
- Later filing says (2026-01-29): Latest refinancing at a rate of 8.0% p.a. for 300 MW Operational projects
- Filing: <https://nsearchives.nseindia.com/corporate/ACME122002_10112025120439_Intimation.pdf>

## 2025-11-10 · Renewable capacity commissioning: Pending

- Said: We have commissioned 378 megawatts capacity till date, and balance 72 megawatts is under advanced stages of construction. We will most likely be done by early part of January with that.
- Due: 2026-01
- Verdict: Pending
- Filing: <https://nsearchives.nseindia.com/corporate/ACME122002_10112025120439_Intimation.pdf>

## 2025-11-10 · Renewable plant commissioning: Pending

- Said: like the plants which are getting commissioned in June, you will see that modules start coming in January to February there. So, modules for, you can say, around 1-gigawatt - 1.5-gigawatt which is targeted around June.
- Due: 2026-06
- Verdict: Pending
- Filing: <https://nsearchives.nseindia.com/corporate/ACME122002_10112025120439_Intimation.pdf>

## 2025-11-10 · Transmission line operationalization: Kept

- Said: Having said that, the connectivity line is anticipated to be operational by December as per repeated assessments by CTU and of course confirmation at the highest possible level
- Due: 2025-12
- Verdict: Kept
- Later filing says (2026-02-04): Importantly, now with commissioning of Narela Khetri line with effect from 14 th December 2025, ACME Sikar is operating at full capacity without any curtailment.
- Filing: <https://nsearchives.nseindia.com/corporate/ACME122002_10112025120439_Intimation.pdf>

## 2025-07-28 · Contracted renewable capacity of 2.2 GW is scheduled to be commissioned by FY27.: Pending

- Said: So you're right, Mohit. That 2.2 gigawatt will be done by FY '27. And it is staggered across FY '26 and FY '27, the connectivity.
- By: Nikhil Dhingra, Q1 FY26 earnings call
- Due: by FY27
- Verdict: Pending
- Evidence: Not due until 31 Mar 2027, after the latest results; later ones will show.
- Filing: <https://nsearchives.nseindia.com/corporate/ACME122002_01082025192716_Intimation.pdf> (page 17)

## 2025-05-20 · The 570 MW SJVN projects are scheduled for completion by May 2026.: Unverifiable

- Said: and 250 megawatt, that's around 5701 megawatts of SJVN, that's also the timeline is May 2026 as per the PPA.
- By: Nikhil Dhingra, Q4 FY25 earnings call
- Due: by May 2026
- Verdict: Unverifiable
- Evidence: We could not match this promise to a figure, and no later call settles it.

## 2025-05-20 · The company expects to add 450 MW AC capacity in FY26.: Unverifiable

- Said: 450 megawatt is what we are adding in this year. And that's the AC basis. On a DC basis, it could be, you can say 600 megawatt peak around that number.
- By: Nikhil Dhingra, Q4 FY25 earnings call
- Due: in FY26
- Verdict: Unverifiable
- Evidence: We could not match this promise to a figure, and no later call settles it.

## 2025-05-20 · The scheduled COD of the 190 MW FDRE project is June of next year.: Unverifiable

- Said: So, the scheduled COD of that project is June of next year. 2 years' time you get to execute.
- By: Nikhil Dhingra, Q4 FY25 earnings call
- Verdict: Unverifiable
- Evidence: We could not match this promise to a figure, and no later call settles it.

## 2025-01-29 · The company aims to commission 100 MW of wind capacity between June and September quarter.: Slipped

- Said: And the 100 MW wind, again, we'll try in best case to do it by let's say between June to September quarter.
- By: Nikhil Dhingra, Q3 FY25 earnings call
- Verdict: Slipped
- Evidence: The Q3 FY26 call, 30 Jan 2026 settles it: “So, wind project is expected to be completed in February, early part of February.”

## 2025-01-29 · The company expects to operate 6,970 MW of capacity in the base case by FY27-28.: Pending

- Said: in the base case we have 6,970 MW of capacity which we will be operating by FY'27-28.
- By: Nikhil Dhingra, Q3 FY25 earnings call
- Due: by FY27-28
- Verdict: Pending
- Evidence: Not due until 31 Mar 2027, after the latest results; later ones will show.

## 2025-01-29 · The company targets reaching a 10 GW capacity portfolio towards the 2028 to 2030 timeframe.: Pending

- Said: And our focus will remain that any future pipeline or whatever we create, we create towards '28 to '30 timelines, so we achieve a 10 GW, our target.
- By: Manoj K Upadhyay, Q3 FY25 earnings call
- Verdict: Pending
- Evidence: Not due until 31 Dec 2028, after the latest results; later ones will show.

## 2024-11-29 · Capacity additions next financial year: Pending

- Said: You can say around 900 megawatt-odd is coming online in the next financial year.
- Due: FY26
- Verdict: Pending
- Filing: <https://nsearchives.nseindia.com/corporate/ACMESOLAR_29112024164833_Intimation.pdf>

## 2024-11-29 · Debt retirement via IPO proceeds: Kept

- Said: with the IPO proceeds that we have received, we plan to retire some of the debt to the tune of roughly INR1,800 to INR2,000 odd crores
- Verdict: Kept
- Later filing says (2025-02-03): debt has been reduced by around INR 2,070 crores, which has resulted in a steep reduction in the net debt.
- Filing: <https://nsearchives.nseindia.com/corporate/ACMESOLAR_29112024164833_Intimation.pdf>

## 2024-11-29 · ISTS 1200MW plant final commissioning: Slipped

- Said: in terms of the commissioning, this is expected in the next 10 days or so.
- Due: 2024-12-05
- Verdict: Slipped
- Later filing says (2025-11-03): Acme Raisar Solar Energy Private Limited | Rajasthan | Solar | 300 | SECI | 2.44 | Phase I (272 MW): December 2024 Phase II (28 MW): January 2025
- Filing: <https://nsearchives.nseindia.com/corporate/ACMESOLAR_29112024164833_Intimation.pdf>

## 2024-11-29 · Quarterly capacity addition: Pending

- Said: Another 450 megawatts is getting added in the quarter, right, quarter one of this.
- Due: Q1 FY26
- Verdict: Pending
- Filing: <https://nsearchives.nseindia.com/corporate/ACMESOLAR_29112024164833_Intimation.pdf>

## 2024-11-29 · Under-construction capacity commissioning target: Pending

- Said: So, our whole of this 4.2 gigawatt is expected to be charged before around 2027.
- Due: FY27
- Verdict: Pending
- Filing: <https://nsearchives.nseindia.com/corporate/ACMESOLAR_29112024164833_Intimation.pdf>

## 2024-11-25 · The company's first wind plant is slated to come online in approximately one month.: Unverifiable

- Said: And of course, our first wind plant is also coming up in a month or so.
- By: Nikhil Dhingra, Q2 FY25 earnings call
- Verdict: Unverifiable (a second reading found it slipped)
- Evidence: We could not match this promise to a figure, and no later call settles it.

Live record: https://eqdoc.com/stock/ACMESOLAR. Not investment advice.