title: "Adani Green Energy Ltd: what management promised, and what happened"
description: "25 statements by Adani Green Energy Ltd's management, each checked against the company's later filings: 1 slipped, 19 pending, 5 unverifiable."
resource: "https://eqdoc.com/stock/ADANIGREEN"
tags: ["promise ledger","management guidance","india","adanigreen"]
sources: [{"resource":"https://eqdoc.com/pdf/ann/7438793.pdf"},{"resource":"https://nsearchives.nseindia.com/corporate/ADANIGREEN_28042026181730_Letter_Equity.pdf"},{"resource":"https://nsearchives.nseindia.com/corporate/ADANIGREEN_04112025112620_Letter.pdf"},{"resource":"https://nsearchives.nseindia.com/corporate/ADANIGREEN_01082025183425_Letter.pdf"}]
generated: {"by":"process:eqdoc-promise-audit"}
x-eqdoc-symbol: "ADANIGREEN"
x-eqdoc-counts: {"kept":0,"slipped":1,"missed":0,"pending":19,"unverifiable":5}
---

# How to read this

Each entry is something management said it would do, when it said it, and whether the company's later filings show it happened.
- **Kept**: a later filing shows it done. **Slipped**: done late or in part. **Missed**: the deadline passed without it.
- **Pending**: the deadline has not come, or no later filing yet speaks to it. **Unverifiable**: no filing could settle it.
- Evidence is either a sentence built from figures the company filed, or a quote from a later company document, as marked.

# Promises

## 2026-10-26 · Commission maiden 500 MW Chitravathi pumped storage project by year-end.: Pending

- Said: While our maiden 500-megawatt pump storage project at Chitravathi is also progressing towards completion by year-end.
- By: Ashish Khanna, Q2 FY27 earnings call
- Due: by year-end
- Verdict: Pending
- Evidence: Not due yet, so it can't be checked.
- Filing: <https://eqdoc.com/pdf/ann/7438793.pdf> (page 4)

## 2026-10-26 · Exceed 10 gigawatt hours of installed battery storage capacity during the year.: Pending

- Said: We remain firmly on track to exceed 10 gigawatt hour during the year.
- By: Ashish Khanna, Q2 FY27 earnings call
- Due: during the year
- Verdict: Pending
- Evidence: Not due yet, so it can't be checked.
- Filing: <https://eqdoc.com/pdf/ann/7438793.pdf> (page 4)

## 2026-07-22 · The company aims to include 5 GW of Pump Storage in its 50+ GW target by 2030.: Pending

- Said: achieve 50+ GW target including 5 GW (30 GWh) of Pump Storage (PSP) and 50 GWh of BESS capacity by 2030
- By: Company presentation, Investor presentation, 22 Jul 2026
- Due: 2030-12-31
- Verdict: Pending
- Evidence: Not due until 31 Dec 2030, after the latest results; later ones will show.

## 2026-07-22 · The company aims to reach 50 GW of renewable energy capacity by 2030.: Pending

- Said: Secured growth path to 50 GW by 2030
- By: Company presentation, Investor presentation, 22 Jul 2026
- Due: 2030-12-31
- Verdict: Pending
- Evidence: Not due until 31 Dec 2030, after the latest results; later ones will show.

## 2026-07-22 · The company commits to achieving no net loss of biodiversity by FY30.: Pending

- Said: No Net Loss of biodiversity in alignment with IBBI 100% by FY30
- By: Company presentation, Investor presentation, 22 Jul 2026
- Due: 2030-03-31
- Verdict: Pending
- Evidence: Not due until 31 Mar 2030, after the latest results; later ones will show.

## 2026-07-22 · The company plans to install 10+ GWhr of Front-of-the-Meter BESS capacity by FY27.: Pending

- Said: 10+ GWhr of Front-of-the-Meter (FTM) BESS capacity by FY27
- By: Company presentation, Investor presentation, 22 Jul 2026
- Due: 2027-03-31
- Verdict: Pending
- Evidence: Not due until 31 Mar 2027, after the latest results; later ones will show.

## 2026-07-22 · The company targets 10+ GWh of BESS capacity by FY27E.: Pending

- Said: BESS Capacity (as of June 30, 2026) FY27E 3.5 GWh ►► 10+ GWh
- By: Company presentation, Investor presentation, 22 Jul 2026
- Due: 2027-03-31
- Verdict: Pending
- Evidence: Not due until 31 Mar 2027, after the latest results; later ones will show.

## 2026-07-22 · The company targets 30 GW of operational capacity at the Khavda site by 2029.: Pending

- Said: 30 GW by 2029
- By: Company presentation, Investor presentation, 22 Jul 2026
- Due: 2029-12-31
- Verdict: Pending
- Evidence: Not due until 31 Dec 2029, after the latest results; later ones will show.

## 2026-07-22 · The company targets 65% deployment of electric vehicles by FY30.: Pending

- Said: Electric Vehicles deployment 65% by FY30
- By: Company presentation, Investor presentation, 22 Jul 2026
- Due: 2030-03-31
- Verdict: Pending
- Evidence: Not due until 31 Mar 2030, after the latest results; later ones will show.

## 2026-06-30 · The company projects a capital expenditure of INR 42,000 crore for FY 2027.: Pending

- Said: the FY '27 guidance is about INR42,000 crores of Capex to be done for FY '27
- By: management, Q4 FY26 earnings call
- Due: for FY 2027
- Verdict: Pending
- Evidence: Not due until 31 Mar 2027, after the latest results; later ones will show.

## 2026-04-28 · Achieve 50 gigawatt capacity target by 2030.: Pending

- Said: and that's put us very firmly on course to achieve 50 gigawatts by 2030.
- By: Sagar Adani, Q4 FY26 earnings call
- Due: by 2030
- Verdict: Pending
- Evidence: Not due until 31 Dec 2030, after the latest results; later ones will show.
- Filing: <https://nsearchives.nseindia.com/corporate/ADANIGREEN_28042026181730_Letter_Equity.pdf> (page 4)

## 2026-04-28 · Add an additional 7 gigawatts of evacuation capacity in Khavda by December 2026.: Pending

- Said: So, we expect an additional 7 gigawatts of evacuation that is opening up in Khavda by December of 2026.
- By: Sagar Adani, Q4 FY26 earnings call
- Due: by December of 2026
- Verdict: Pending
- Evidence: Not due until 31 Dec 2026, after the latest results; later ones will show.
- Filing: <https://nsearchives.nseindia.com/corporate/ADANIGREEN_28042026181730_Letter_Equity.pdf> (page 13)

## 2026-04-28 · Commission maiden 500 MW pumped storage project at Chitravathi in the coming year.: Pending

- Said: we aim to complete our maiden 500-megawatt project at Chitravathi in Andhra Pradesh in this coming year.
- By: Sagar Adani, Q4 FY26 earnings call
- Due: in this coming year
- Verdict: Pending
- Evidence: Not due yet, so it can't be checked.
- Filing: <https://nsearchives.nseindia.com/corporate/ADANIGREEN_28042026181730_Letter_Equity.pdf> (page 4)

## 2026-04-28 · Commission north of 10 gigawatt hours of battery storage in the coming year.: Pending

- Said: We expect to commission north of 10,000 megawatt hours or 10 gigawatt hours in this coming year.
- By: Sagar Adani, Q4 FY26 earnings call
- Due: in this coming year
- Verdict: Pending
- Evidence: Not due yet, so it can't be checked.
- Filing: <https://nsearchives.nseindia.com/corporate/ADANIGREEN_28042026181730_Letter_Equity.pdf> (page 7)

## 2026-04-28 · Convert 5.3 gigawatts of infirm power into active PPAs incrementally by December 2026, with the rest by March 2027.: Pending

- Said: All of this will incrementally happen by December of 2026. Some of it might remain, which will get done by March 2027.
- By: Sagar Adani, Q4 FY26 earnings call
- Due: by March 2027
- Verdict: Pending
- Evidence: Not due until 31 Dec 2026, after the latest results; later ones will show.
- Filing: <https://nsearchives.nseindia.com/corporate/ADANIGREEN_28042026181730_Letter_Equity.pdf> (page 17)

## 2026-04-28 · Ensure all 4.5 to 5 gigawatts of capacity added in FY27 is under 100% PPA.: Pending

- Said: Even in FY27, the 4.5 to 5 gigawatts that we're adding in terms of capacity is 100% PPA.
- By: Sagar Adani, Q4 FY26 earnings call
- Due: in FY27
- Verdict: Pending
- Evidence: Not due until 31 Mar 2027, after the latest results; later ones will show.
- Filing: <https://nsearchives.nseindia.com/corporate/ADANIGREEN_28042026181730_Letter_Equity.pdf> (page 17)

## 2026-04-24 · The company plans to add between 4.5 and 5 gigawatts of capacity in the coming year.: Pending

- Said: We will be looking at an addition in the coming year of somewhere between 4.5 to 5 GW.
- By: Sagar Adani, Q4 FY26 earnings call
- Verdict: Pending
- Evidence: Not due yet, so it can't be checked.

## 2025-11-04 · Targeting 50 gigawatts of total capacity by 2030.: Pending

- Said: We remain firmly on track to achieve our targeted 50 gigawatt capacity by 2030.
- By: Ashish Khanna, Q2 FY26 earnings call
- Due: by 2030
- Verdict: Pending
- Evidence: Not due until 31 Dec 2030, after the latest results; later ones will show.
- Filing: <https://nsearchives.nseindia.com/corporate/ADANIGREEN_04112025112620_Letter.pdf> (page 3)

## 2025-10-29 · The company projects annual capital expenditure between INR 30,000 crores and INR 35,000 crores for the next two years.: Pending

- Said: From a perspective of next two years, the range would be in that same INR30,000 crores to INR35,000 crores of capex to be done each year.
- By: Saurabh Shah, Q2 FY26 earnings call
- Verdict: Pending
- Evidence: Not due yet, so it can't be checked.
- Filing: <https://nsearchives.nseindia.com/corporate/ADANIGREEN_04112025112620_Letter.pdf> (page 8)

## 2025-08-01 · Full-year FY26 consolidated sales were implied by run-rate guidance, with annual capex guiding up to ₹35,000-40,000 cror: Unverifiable

- Said: With a comprehensive capital management framework, we ensure that our growth is fully funded for our 50-gigawatt target by 2030 while upholding strict credit discipline.
- By: Ashish Khanna, Q1 FY26 earnings call
- Due: by 2030
- Verdict: Unverifiable
- Evidence: We could not match this promise to a figure, and no later call settles it.
- Filing: <https://nsearchives.nseindia.com/corporate/ADANIGREEN_01082025183425_Letter.pdf> (page 4)

## 2025-04-29 · The company expects to commission the 600 megawatt hybrid project within the current year.: Unverifiable

- Said: We expect to have that commissioned sometime this year.
- By: Raj Kumar Jain, Q4 FY25 earnings call
- Verdict: Unverifiable
- Evidence: We could not match this promise to a figure, and no later call settles it.

## 2025-04-29 · The company plans to commission 5 gigawatts of capacity in FY '26.: Unverifiable

- Said: in FY '26, as he said, there is a 5 gigawatt of capacity that we are looking to commission
- By: Saurabh Shah, Q4 FY25 earnings call
- Due: in FY '26
- Verdict: Unverifiable
- Evidence: We could not match this promise to a figure, and no later call settles it.

## 2025-01-24 · The company expects to add 5 gigawatts of new capacity in the current fiscal year (FY25).: Unverifiable

- Said: we feel very strongly that we should be able to deliver approximately 5 gigawatt of new capacity this year.
- By: Amit Singh, Q3 FY25 earnings call
- Due: FY25
- Verdict: Unverifiable
- Evidence: We could not match this promise to a figure, and no later call settles it.

## 2024-10-23 · The company plans to add approximately 6 gigawatts of renewable capacity in FY25.: Slipped

- Said: Now, turning our attention towards FY25, we have made a comprehensive construction plan to deliver neighborhood of 6-gigawatt scale of renewable capacity.
- By: Amit Singh, Q2 FY25 earnings call
- Due: in FY25
- Verdict: Slipped
- Evidence: The Q3 FY25 call, 24 Jan 2025 settles it: “we feel very strongly that we should be able to deliver approximately 5 gigawatt of new capacity this year.”

## 2024-10-23 · The company projects an attributable EBITDA run rate of approximately INR 10,800 crores for the current year.: Unverifiable

- Said: So from an attributable EBITDA perspective, for this year we are looking at a run rate range of about INR10,800 crores.
- By: Saurabh Shah, Q2 FY25 earnings call
- Verdict: Unverifiable
- Evidence: We could not match this promise to a figure, and no later call settles it.

Live record: https://eqdoc.com/stock/ADANIGREEN. Not investment advice.