type: "Promise Ledger"
title: "Adani Power Ltd: what management promised, and what happened"
description: "23 statements by Adani Power Ltd's management, each checked against the company's later filings: 2 slipped, 15 pending, 6 unverifiable."
resource: "https://eqdoc.com/stock/ADANIPOWER"
tags: ["promise ledger","management guidance","india","adanipower"]
sources: [{"resource":"https://eqdoc.com/pdf/ann/7437609.pdf"},{"resource":"https://eqdoc.com/pdf/ann/7252401.pdf"},{"resource":"https://nsearchives.nseindia.com/corporate/ADANIPOWER_07092026172301_APLInvestorPresentationpublicationINR07092026.pdf"},{"resource":"https://eqdoc.com/pdf/ann/7108772.pdf"},{"resource":"https://nsearchives.nseindia.com/corporate/ADANIPOWER_29072026214437_APLearningscalltranscript29072026.pdf"},{"resource":"https://eqdoc.com/pdf/ann/6699947.pdf"},{"resource":"https://nsearchives.nseindia.com/corporate/ADANIPOWER_04022026171645_APLtranscript04022026.pdf"},{"resource":"https://nsearchives.nseindia.com/corporate/ADANIPOWER_05112025183934_APLtranscriptofconcall05112025.pdf"},{"resource":"https://nsearchives.nseindia.com/corporate/ADANIPOWER_08082025105715_APLTranscript08082025.pdf"}]
generated: {"by":"process:eqdoc-promise-audit"}
x-eqdoc-symbol: "ADANIPOWER"
x-eqdoc-counts: {"kept":0,"slipped":2,"missed":0,"pending":15,"unverifiable":6}
---

# How to read this

Each entry is something management said it would do, when it said it, and whether the company's later filings show it happened.
- **Kept**: a later filing shows it done. **Slipped**: done late or in part. **Missed**: the deadline passed without it.
- **Pending**: the deadline has not come, or no later filing yet speaks to it. **Unverifiable**: no filing could settle it.
- Evidence is either a sentence built from figures the company filed, or a quote from a later company document, as marked.

# Promises

## 2026-10-25 · Develop 10 GW of nuclear power capacity by 2035 with sites identified for location.: Pending

- Said: Targeting capacity of 10 GW by 2035; sites identified for project location
- By: Company presentation, Investor presentation, 25 Oct 2026
- Due: 2035
- Verdict: Pending
- Evidence: Not due until 31 Dec 2035, after the latest results; later ones will show.
- Filing: <https://eqdoc.com/pdf/ann/7437609.pdf> (page 17)

## 2026-10-25 · Execute thermal power capacity expansion of 23.7 GW with an estimated capex of ₹2 trillion by FY 2031-32.: Pending

- Said: Ongoing capacity expansion of 23.7 GW thermal power plants with estimated capex of ₹ 2 Trillion and targeted completion by FY 2031-32
- By: Company presentation, Investor presentation, 25 Oct 2026
- Due: FY 2031-32
- Verdict: Pending
- Evidence: Not due until 31 Mar 2032, after the latest results; later ones will show.
- Filing: <https://eqdoc.com/pdf/ann/7437609.pdf> (page 17)

## 2026-10-25 · Expand base load power capacity to 45 GW by FY 2031-32.: Pending

- Said: Base Load Power Capacity Expansion to 45 GW by FY 2031-32
- By: Company presentation, Investor presentation, 25 Oct 2026
- Due: FY 2031-32
- Verdict: Pending
- Evidence: Not due until 31 Mar 2032, after the latest results; later ones will show.
- Filing: <https://eqdoc.com/pdf/ann/7437609.pdf> (page 17)

## 2026-10-25 · Reduce greenhouse gas emission intensity to 0.84 tCO2e/MWh by FY27.: Pending

- Said: Reduction in GHG emission intensity to 0.84 tCO2e/MWh by FY27
- By: Company presentation, Investor presentation, 25 Oct 2026
- Due: FY27
- Verdict: Pending
- Evidence: Not due until 31 Mar 2027, after the latest results; later ones will show.
- Filing: <https://eqdoc.com/pdf/ann/7437609.pdf> (page 30)

## 2026-09-07 · Deploy over $20 billion in capital investments by FY32.: Pending

- Said: $20 Bn+ Investment Plan by FY32
- By: Company presentation, Investor presentation, 7 Sep 2026
- Due: by FY32
- Verdict: Pending
- Evidence: Not due until 31 Mar 2032, after the latest results; later ones will show.
- Filing: <https://eqdoc.com/pdf/ann/7252401.pdf> (page 6)

## 2026-09-07 · Expand Mahan Energen capacity to 4,400 MW by 2030.: Pending

- Said: Target capacity 4,400 MW by 2030
- By: Company presentation, Investor presentation, 7 Sep 2026
- Due: by 2030
- Verdict: Pending
- Evidence: Not due until 31 Dec 2030, after the latest results; later ones will show.
- Filing: <https://eqdoc.com/pdf/ann/7252401.pdf> (page 14)

## 2026-09-07 · Expand Raigarh plant capacity to 3,800 MW by 2031.: Pending

- Said: Target capacity 3,800 MW by 2031
- By: Company presentation, Investor presentation, 7 Sep 2026
- Due: by 2031
- Verdict: Pending
- Evidence: Not due until 31 Dec 2031, after the latest results; later ones will show.
- Filing: <https://eqdoc.com/pdf/ann/7252401.pdf> (page 14)

## 2026-09-07 · Expand Raipur plant capacity to 2,970 MW by 2030.: Pending

- Said: Target capacity 2,970 MW by 2030
- By: Company presentation, Investor presentation, 7 Sep 2026
- Due: by 2030
- Verdict: Pending
- Evidence: Not due until 31 Dec 2030, after the latest results; later ones will show.
- Filing: <https://eqdoc.com/pdf/ann/7252401.pdf> (page 14)

## 2026-09-07 · Fund approximately ₹180,000 crores of capex over the next 7 years using FFO from the existing fleet.: Pending

- Said: Considering repayment of ₹ 40k crores, FFO from the existing fleet would allow APL to fund large portion of capex of ~ ₹ 180k crores over the next 7 years
- By: Company presentation, Investor presentation, 7 Sep 2026
- Due: over the next 7 years
- Verdict: Pending
- Evidence: Not due until 7 Sep 2033, after the latest results; later ones will show.
- Filing: <https://nsearchives.nseindia.com/corporate/ADANIPOWER_07092026172301_APLInvestorPresentationpublicationINR07092026.pdf> (page 23)

## 2026-08-01 · Construct the first 570 MW Bhutan hydro project under Wangchhu Hydroelectric Power Ltd. at an estimated project cost of: Pending

- Said: First project of 570 MW to be set up under SPV Wangchhu Hydroelectric Power Ltd. with 49:51 stake of APL and DGPC; estimated project cost of ₹ 60 Billion
- By: Company presentation, Investor presentation, 1 Aug 2026
- Verdict: Pending
- Evidence: Not due yet, so it can't be checked.
- Filing: <https://eqdoc.com/pdf/ann/7108772.pdf> (page 16)

## 2026-07-23 · Korba Phase-II is expected to come online before the end of December of the current year.: Slipped

- Said: We expect that Korba Phase-II will come before December end this year. That is the broader expectation.
- By: S B Khyalia, Q1 FY27 earnings call
- Due: before December end this year
- Verdict: Slipped
- Evidence: The Q2 FY27 call, 26 Oct 2026 settles it: “At Korba Phase-II, the first 660 MW unit has been achieved grid synchronization. Commercial commissioning is expected shortly. The second unit is planned for quarter 4 of '27.”
- Filing: <https://nsearchives.nseindia.com/corporate/ADANIPOWER_29072026214437_APLearningscalltranscript29072026.pdf> (page 13)

## 2026-04-30 · Korba Phase-II is expected to be commissioned during the course of the current year.: Pending

- Said: We expect to commission Korba Phase-II during the course of the current year.
- By: S. B. Khyalia, Q4 FY26 earnings call
- Due: during the course of the current year
- Verdict: Pending
- Evidence: Not due yet, so it can't be checked.
- Filing: <https://eqdoc.com/pdf/ann/6699947.pdf> (page 4)

## 2026-04-30 · The company conservatively projects reaching an EBITDA of INR 50,000 crore by FY31.: Pending

- Said: So, Bharat Bhai, we should be in a position to achieve INR50,000 crore conservatively by FY 2031.
- By: S. B. Khyalia, Q4 FY26 earnings call
- Due: by FY 2031
- Verdict: Pending
- Evidence: Not due until 31 Mar 2031, after the latest results; later ones will show.
- Filing: <https://eqdoc.com/pdf/ann/6699947.pdf> (page 15)

## 2026-04-30 · The company expects to sign the Maharashtra PPA within the next 3 months.: Unverifiable

- Said: So, we expect that in the next 3 months, we should be in a position to get the PPA signed. Then we will need 48 months.
- By: S. B. Khyalia, Q4 FY26 earnings call
- Due: next 3 months
- Verdict: Unverifiable
- Evidence: We could not match this promise to a figure, and no later call settles it.
- Filing: <https://eqdoc.com/pdf/ann/6699947.pdf> (page 10)

## 2026-01-29 · Power supply under the Uttarakhand PPA will commence from next month onwards.: Unverifiable

- Said: The Uttarakhand PPA will start supplying it from next month onwards.
- By: Nishit Dave, Q3 FY26 earnings call
- Due: next month onwards
- Verdict: Unverifiable
- Evidence: We could not match this promise to a figure, and no later call settles it.
- Filing: <https://nsearchives.nseindia.com/corporate/ADANIPOWER_04022026171645_APLtranscript04022026.pdf> (page 15)

## 2025-10-30 · Adani Power aims to expand generation capacity from 18 GW to 42 GW by 2032.: Pending

- Said: Now, we are set firmly on our path to raise our generation capacity from 18 GW to 42 GW by 2032, with an even faster growth in earnings and cash flows.
- By: S. B. Khyalia, Q2 FY26 earnings call
- Due: by 2032
- Verdict: Pending
- Evidence: Not due until 31 Dec 2032, after the latest results; later ones will show.
- Filing: <https://nsearchives.nseindia.com/corporate/ADANIPOWER_05112025183934_APLtranscriptofconcall05112025.pdf> (page 4)

## 2025-10-30 · Godda Power Plant is expected to be connected to the Indian grid by December 2025.: Unverifiable

- Said: We are expecting that it will get connected by December 2025.
- By: S. B. Khyalia, Q2 FY26 earnings call
- Due: by December 2025
- Verdict: Unverifiable
- Evidence: We could not match this promise to a figure, and no later call settles it.
- Filing: <https://nsearchives.nseindia.com/corporate/ADANIPOWER_05112025183934_APLtranscriptofconcall05112025.pdf> (page 11)

## 2025-10-30 · The company targets commissioning around 3 GW next year, followed by 2.4 GW and 3.2 GW in successive years.: Pending

- Said: We are going to commission around 3 GW in next year. Thereafter, we are going to commission 2.4 GW. In next to that year, 3.2 GW.
- By: S. B. Khyalia, Q2 FY26 earnings call
- Due: next year
- Verdict: Pending
- Evidence: Not due yet, so it can't be checked.
- Filing: <https://nsearchives.nseindia.com/corporate/ADANIPOWER_05112025183934_APLtranscriptofconcall05112025.pdf> (page 11)

## 2025-08-01 · Dhirauli coal mine production is projected to commence around September or October 2025.: Slipped

- Said: The production should start by September or October, somewhere. So, we are on time as per the plan which we gave earlier.
- By: S.b. Khyalia, Q1 FY26 earnings call
- Due: by September or October
- Verdict: Slipped
- Evidence: The Q2 FY26 call, 30 Oct 2025 settles it: “For Dhirauli mine, we are expecting that by end of this year only, the box cutting will be done by end of the year, and from next year, we will have coal production”
- Filing: <https://nsearchives.nseindia.com/corporate/ADANIPOWER_08082025105715_APLTranscript08082025.pdf> (page 12)

## 2025-08-01 · EBITDA margins are expected to remain similar to the previous year until new capacity expansions are realized.: Unverifiable

- Said: So, till the time our capacity expansion takes place, you can expect similar EBITDA margins as we have recorded in the last year.
- By: Nishit Dave, Q1 FY26 earnings call
- Due: till the time our capacity expansion takes place
- Verdict: Unverifiable
- Evidence: We could not match this promise to a figure, and no later call settles it.
- Filing: <https://nsearchives.nseindia.com/corporate/ADANIPOWER_08082025105715_APLTranscript08082025.pdf> (page 10)

## 2025-05-01 · Adani Power plans an expansion capex of INR 13,307 crores for FY26.: Unverifiable

- Said: and we have planned of INR13,307 crores towards expansion capex for FY26.
- By: Dilip Jha, Q4 FY25 earnings call
- Due: for FY26
- Verdict: Unverifiable
- Evidence: We could not match this promise to a figure, and no later call settles it.

## 2025-05-01 · Dhirauli coal mine will commence coal production this year.: Unverifiable

- Said: One of the mines in MP, which is in the Dhirauli block in Singrauli, will start production of coal this year.
- By: S B Khyalia, Q4 FY25 earnings call
- Verdict: Unverifiable
- Evidence: We could not match this promise to a figure, and no later call settles it.

## 2024-10-28 · Under-construction capacity at Lanco is expected to be ready within two years.: Pending

- Said: We are expecting that in the next two years, it will be ready.
- By: Dilip Jha, Q2 FY25 earnings call
- Verdict: Pending
- Evidence: Not due yet, so it can't be checked.

Live record: https://eqdoc.com/stock/ADANIPOWER. Not investment advice.