type: "Promise Ledger"
title: "Aegis Vopak Terminals Ltd: what management promised, and what happened"
description: "28 statements by Aegis Vopak Terminals Ltd's management, each checked against the company's later filings: 1 kept, 4 slipped, 2 missed, 18 pending, 3 unverifiable."
resource: "https://eqdoc.com/stock/AEGISVOPAK"
tags: ["promise ledger","management guidance","india","aegisvopak"]
sources: [{"resource":"https://nsearchives.nseindia.com/corporate/AVTL_07082026164455_AVTL_InvestorPresentation_Q1FY27_sIGNED.pdf"},{"resource":"https://nsearchives.nseindia.com/corporate/AVTL_05022026115705_AVTL_CV_Transcript_Merged.pdf"},{"resource":"https://nsearchives.nseindia.com/corporate/AVTL_13082025140354_AVTL_TranscriptQ1FY26_Signed.pdf"}]
generated: {"by":"process:eqdoc-promise-audit","at":"2026-10-07"}
stale_after: "2027-01-15"
x-eqdoc-symbol: "AEGISVOPAK"
x-eqdoc-counts: {"kept":1,"slipped":4,"missed":2,"pending":18,"unverifiable":3}
---

# How to read this

Each entry is something management said it would do, when it said it, and whether the company's later filings show it happened.
- **Kept**: a later filing shows it done. **Slipped**: done late or in part. **Missed**: the deadline passed without it.
- **Pending**: the deadline has not come, or no later filing yet speaks to it. **Unverifiable**: no filing could settle it.
- Evidence is either a sentence built from figures the company filed, or a quote from a later company document, as marked.

# Promises

## 2026-08-14 · The company aims to grow volumes by at least 25% year-on-year every year.: Pending

- Said: We like to at least grow in our volumes 25% year-on-year every year.
- By: Murad Moledina, Q1 FY27 earnings call
- Verdict: Pending
- Evidence: Not due yet, so it can't be checked.

## 2026-08-07 · The Kandla-Gorakhpur pipeline will have the capacity to transport over 25% of India's total LPG demand.: Pending

- Said: Pipeline will be capable to transport 25%+ of India’s total LPG demand (8.25 MMTPA)
- By: Company presentation, Investor presentation, 7 Aug 2026
- Verdict: Pending
- Evidence: Not due yet, so it can't be checked.

## 2026-08-07 · The company intends to pursue inorganic growth through acquisitions to expand its footprint.: Pending

- Said: Will evaluate acquisition opportunities which offers expansion potential at existing locations and entry into newer locations
- By: Company presentation, Investor presentation, 7 Aug 2026
- Verdict: Pending
- Evidence: Not due yet, so it can't be checked.

## 2026-08-07 · The company is planning to add 49,577 cbm of liquid storage capacity in Kochi by Q1 FY27.: Unverifiable

- Said: Upcoming 49,577 cbm capacity of liquid storage tank in Kochi
- By: Company presentation, Investor presentation, 7 Aug 2026
- Due: by Q1 FY27
- Verdict: Unverifiable (a second reading found it pending)
- Evidence: We could not match this promise to a figure, and no later call settles it.

## 2026-08-07 · The company is planning to add 51,998 MT of refrigerated LPG storage capacity in JNPA by Q1 FY27.: Unverifiable

- Said: Upcoming 51,998 MT capacity of refrigerated double steel LPG storage tank in JNPA
- By: Company presentation, Investor presentation, 7 Aug 2026
- Due: by Q1 FY27
- Verdict: Unverifiable (a second reading found it pending)
- Evidence: We could not match this promise to a figure, and no later call settles it.

## 2026-08-07 · Capex Target 2027 and 2031: Pending

- Said: To reach capex of 1.2 billion dollars by next year and we expect to reach 5 billion dollars aggregate capex by 2030-31
- Due: FY31
- Verdict: Pending
- Filing: <https://nsearchives.nseindia.com/corporate/AVTL_07082026164455_AVTL_InvestorPresentation_Q1FY27_sIGNED.pdf>

## 2026-08-06 · The company aims to reach a capital expenditure of 1.2 billion dollars by next year.: Pending

- Said: To reach capex of 1.2 billion dollars by next year
- By: Company presentation, Investor presentation, 6 Aug 2026
- Verdict: Pending
- Evidence: Not due yet, so it can't be checked.

## 2026-08-06 · The company expects to reach an aggregate capital expenditure of 5 billion dollars by 2030-31.: Pending

- Said: we expect to reach 5 billion dollars aggregate capex by 2030-31
- By: Company presentation, Investor presentation, 6 Aug 2026
- Due: by 2030-31
- Verdict: Pending
- Evidence: Not due until 31 Dec 2030, after the latest results; later ones will show.

## 2026-08-06 · The company plans to connect its JNPA facility to the northern hinterland via the Western Dedicated Freight Corridor.: Pending

- Said: JNPA will be connected to northern hinterland via Western DFC with its full commissioning.
- By: Company presentation, Investor presentation, 6 Aug 2026
- Verdict: Pending
- Evidence: Not due yet, so it can't be checked.

## 2026-08-06 · The company plans to maintain a debt gearing ratio of 0.6x.: Pending

- Said: debt gearing ratio of 0.6x capped to 3.5 times of EBITDA
- By: Company presentation, Investor presentation, 6 Aug 2026
- Verdict: Pending
- Evidence: Not due yet, so it can't be checked.

## 2026-06-09 · The first phase of the new liquid capacity is expected to be operational in Q1 of FY27.: Slipped

- Said: the first phase of the new liquid capacity is expected to be operational in Q1 of FY27
- By: Raj Chandaria, Q4 FY26 earnings call
- Due: 2026-06-30
- Verdict: Slipped
- Evidence: The Q1 FY27 call, 14 Aug 2026 settles it: “The first phase of the liquid storage expansion, comprising approximately 100,000 cubic meters, is expected to be commissioned in Q3 of FY27 and will start contributing as the capacity becomes operational.”

## 2026-02-05 · Ammonia terminal completion: Kept

- Said: construction of India's first independent ammonia terminal with a static capacity of 36,000 metric tons is progressing well, and is expected to be completed before the first quarter of the next fiscal year.
- Due: Q1 FY27
- Verdict: Kept
- Later filing says (2026-08-19): We have already commissioned our ammonia cryogenic terminal
- Filing: <https://nsearchives.nseindia.com/corporate/AVTL_05022026115705_AVTL_CV_Transcript_Merged.pdf>

## 2026-02-05 · JNPT liquid capacity phase 1: Missed

- Said: The overall project, which involves a capital expenditure of INR1,675 crores, is advancing well, with the first phase of the new liquid capacity scheduled to come online in Q1 of FY27.
- Due: Q1 FY27
- Verdict: Missed
- Later filing says (2026-08-19): The first phase of the liquid storage expansion, comprising approximately 100,000 cubic meters, is expected to be commissioned in Q3 of FY27
- Filing: <https://nsearchives.nseindia.com/corporate/AVTL_05022026115705_AVTL_CV_Transcript_Merged.pdf>

## 2026-02-05 · Kandla Gorakhpur LPG Pipeline connection: Missed

- Said: while the Kandla Gorakhpur LPG Pipeline is scheduled to be connected by June 2026.
- Due: 2026-06-30
- Verdict: Missed
- Later filing says (2026-08-19): the Kandla-Gorakhpur LPG pipeline is progressing well and is now expected to be connected during the first half of FY27.
- Filing: <https://nsearchives.nseindia.com/corporate/AVTL_05022026115705_AVTL_CV_Transcript_Merged.pdf>

## 2026-02-05 · Long-term capex roadmap: Pending

- Said: in line with our long-term vision, we have charted a capex roadmap of approximately $5 billion to be achieved by 2030.
- Due: 2030
- Verdict: Pending
- Filing: <https://nsearchives.nseindia.com/corporate/AVTL_05022026115705_AVTL_CV_Transcript_Merged.pdf>

## 2026-02-05 · Mangalore rail gantry operationalization: Pending

- Said: Rail gantry work has started. It will take 9 months. So probably by September '26, it will be operational.
- Due: 2026-09-30
- Verdict: Pending
- Filing: <https://nsearchives.nseindia.com/corporate/AVTL_05022026115705_AVTL_CV_Transcript_Merged.pdf>

## 2026-02-05 · Petroleum products volume management: Pending

- Said: AVTL will manage over half a million metric tons annually, starting at the end of this calendar year, providing strong volume visibility
- Due: 2026-12-31
- Verdict: Pending
- Filing: <https://nsearchives.nseindia.com/corporate/AVTL_05022026115705_AVTL_CV_Transcript_Merged.pdf>

## 2026-01-30 · The Kandla-Gorakhpur LPG Pipeline is scheduled to be connected by June 2026.: Slipped

- Said: the Kandla Gorakhpur LPG Pipeline is scheduled to be connected by June 2026.
- By: Raj Chandaria, Q3 FY26 earnings call
- Due: 2026-06-30
- Verdict: Slipped
- Evidence: The Q1 FY27 call, 14 Aug 2026 settles it: “the Kandla-Gorakhpur LPG pipeline is progressing well and is now expected to be connected during the first half of FY27.”

## 2026-01-30 · The company commits to maintaining a debt gearing ratio of 0.6 times.: Pending

- Said: Our financial strategy remains firmly anchored in prudence, with a commitment to maintain the debt gearing ratio of 0.6 times, and ensuring that overall leverage does not exceed 3.5 times EBITDA.
- By: Raj Chandaria, Q3 FY26 earnings call
- Verdict: Pending
- Evidence: Not due yet, so it can't be checked.

## 2025-11-07 · JLPL connectivity is expected to be operational by the 3rd quarter of FY '26, so that is probably by December 2025.: Unverifiable

- Said: JLPL connectivity is expected to be operational by the 3rd quarter of FY '26, so that is probably by December 2025.
- By: Raj Chandaria, Q2 FY26 earnings call
- Due: 2025-12-31
- Verdict: Unverifiable
- Evidence: We could not match this promise to a figure, and no later call settles it.

## 2025-11-07 · The company aims to achieve an aggregate capital expenditure of around USD 5 billion by 2030.: Pending

- Said: aim to achieve an aggregate CAPEX of around USD 5 billion by 2030.
- By: Raj Chandaria, Q2 FY26 earnings call
- Due: 2030-12-31
- Verdict: Pending
- Evidence: Not due until 31 Dec 2030, after the latest results; later ones will show.

## 2025-08-13 · Aggregate capital expenditure target: Pending

- Said: we are targeting to reach a $5 billion aggregate capital expenditure by 2030
- Due: 2030
- Verdict: Pending
- Filing: <https://nsearchives.nseindia.com/corporate/AVTL_13082025140354_AVTL_TranscriptQ1FY26_Signed.pdf>

## 2025-08-13 · Kandla CRL-4 liquid terminal operationalization: Pending

- Said: the same will be operationalized in the next year.
- Due: FY27
- Verdict: Pending
- Filing: <https://nsearchives.nseindia.com/corporate/AVTL_13082025140354_AVTL_TranscriptQ1FY26_Signed.pdf>

## 2025-08-13 · Mangalore rail LPG gantry operationalization: Pending

- Said: we are constructing a rail LPG gantry over there, which is expected to become operational in six to nine months from now.
- Due: Q4 FY26
- Verdict: Pending
- Filing: <https://nsearchives.nseindia.com/corporate/AVTL_13082025140354_AVTL_TranscriptQ1FY26_Signed.pdf>

## 2025-08-13 · Mangalore railway gantry construction completion: Pending

- Said: And we expect to have a railway gantry built in about the next nine to 12 months.
- Due: Q1 FY27
- Verdict: Pending
- Filing: <https://nsearchives.nseindia.com/corporate/AVTL_13082025140354_AVTL_TranscriptQ1FY26_Signed.pdf>

## 2025-08-13 · Phase two equity dilution timeline: Pending

- Said: We are mandated by law-to-dilute up to 25% within three years of our IPO. The second dilution will happen sometime from now, until three years.
- Due: 2028-06-02
- Verdict: Pending
- Filing: <https://nsearchives.nseindia.com/corporate/AVTL_13082025140354_AVTL_TranscriptQ1FY26_Signed.pdf>

## 2025-08-08 · The ammonia terminal project is expected to be completed before Q1 of the next fiscal year.: Slipped

- Said: This project is expected to be completed before Q1 of the next fiscal year
- By: Raj Chandaria, Q1 FY26 earnings call
- Verdict: Slipped (a second reading found it kept)
- Evidence: The Q3 FY26 call, 30 Jan 2026 settles it: “construction of India's first independent ammonia terminal with a static capacity of 36,000 metric tons is progressing well, and is expected to be completed before the first quarter of the next fiscal year.”
- Filing: <https://nsearchives.nseindia.com/corporate/AVTL_13082025140354_AVTL_TranscriptQ1FY26_Signed.pdf> (page 5)

## 2025-08-08 · The revenue from both these terminals will start accruing from Q2 of FY 2026.: Slipped

- Said: the revenue from both these terminals will start accruing from Q2 of FY 2026.
- By: Raj Chandaria, Q1 FY26 earnings call
- Due: 2019-09-30
- Verdict: Slipped
- Evidence: The Q4 FY26 call, 9 Jun 2026 settles it: “the first phase of the new liquid capacity is expected to be operational in Q1 of FY27”
- Filing: <https://nsearchives.nseindia.com/corporate/AVTL_13082025140354_AVTL_TranscriptQ1FY26_Signed.pdf> (page 4)

Live record: https://eqdoc.com/stock/AEGISVOPAK. Not investment advice.