title: "Ambuja Cements Ltd: what management promised, and what happened"
description: "17 statements by Ambuja Cements Ltd's management, each checked against the company's later filings: 1 slipped, 13 pending, 3 unverifiable."
resource: "https://eqdoc.com/stock/AMBUJACEM"
tags: ["promise ledger","management guidance","india","ambujacem"]
sources: [{"resource":"https://eqdoc.com/pdf/ann/7453403.pdf"},{"resource":"https://eqdoc.com/pdf/ann/7086961.pdf"},{"resource":"https://nsearchives.nseindia.com/corporate/AMBUJACEM_08112025162953_ACL_Earning_call__1_.pdf"},{"resource":"https://nsearchives.nseindia.com/corporate/AMBUJACEM_06082025193356_ACL_Transcriptofearningcall.pdf"}]
generated: {"by":"process:eqdoc-promise-audit"}
x-eqdoc-symbol: "AMBUJACEM"
x-eqdoc-counts: {"kept":0,"slipped":1,"missed":0,"pending":13,"unverifiable":3}
---

# How to read this

Each entry is something management said it would do, when it said it, and whether the company's later filings show it happened.
- **Kept**: a later filing shows it done. **Slipped**: done late or in part. **Missed**: the deadline passed without it.
- **Pending**: the deadline has not come, or no later filing yet speaks to it. **Unverifiable**: no filing could settle it.
- Evidence is either a sentence built from figures the company filed, or a quote from a later company document, as marked.

# Promises

## 2026-10-29 · A total of 150 EV trucks will be operating for clinker and cement transport by end of December 2027.: Pending

- Said: EV induction already started . By end of Dec 2027 , total 150 EV trucks will be running for clinker and cement
- By: Company presentation, Investor presentation, 29 Oct 2026
- Due: Dec 2027
- Verdict: Pending
- Evidence: Not due until 31 Dec 2027, after the latest results; later ones will show.
- Filing: <https://eqdoc.com/pdf/ann/7453403.pdf> (page 22)

## 2026-10-29 · Debottlenecking and firmed-up expansions will scale total cement capacity to 155 MTPA by FY30.: Pending

- Said: Firmed-up expansion of +29.7 MTPA to take capacity to 149 MTPA | Debottlenecking to scale it further to 155 MTPA
- By: Company presentation, Investor presentation, 29 Oct 2026
- Due: Target (FY’30)
- Verdict: Pending
- Evidence: Not due until 31 Mar 2030, after the latest results; later ones will show.
- Filing: <https://eqdoc.com/pdf/ann/7453403.pdf> (page 12)

## 2026-10-29 · In H2 FY27, 3.2 MTPA capacity will ramp up and 2.4 MTPA will be commissioned.: Pending

- Said: H2 FY’27: 3.2 MTPA ramping up; 2.4 MTPA to be commissioned
- By: Company presentation, Investor presentation, 29 Oct 2026
- Due: H2 FY'27
- Verdict: Pending
- Evidence: Not due until 31 Mar 2027, after the latest results; later ones will show.
- Filing: <https://eqdoc.com/pdf/ann/7453403.pdf> (page 10)

## 2026-10-29 · The merger scheme is expected to be effective with NCLT approvals by January 2027.: Pending

- Said: NCLT approvals & effectiveness | Expected completion by Jan’27
- By: Company presentation, Investor presentation, 29 Oct 2026
- Due: Jan’27
- Verdict: Pending
- Evidence: Not due until 31 Jan 2027, after the latest results; later ones will show.
- Filing: <https://eqdoc.com/pdf/ann/7453403.pdf> (page 13)

## 2026-07-28 · Cement capacity will increase to 119 MTPA by FY27.: Pending

- Said: Cement capacity stood at 109 MTPA as on 30th June 2026 and is expected to increase to 119 MTPA by FY’27.
- By: Company presentation, Investor presentation, 28 Jul 2026
- Due: FY'27
- Verdict: Pending
- Evidence: Not due until 31 Mar 2027, after the latest results; later ones will show.
- Filing: <https://eqdoc.com/pdf/ann/7086961.pdf> (page 16)

## 2026-07-28 · Cement cost will decline to approximately Rs 4,000 PMT by FY28.: Pending

- Said: Rs ~4,000 PMT (FY’28 E)
- By: Company presentation, Investor presentation, 28 Jul 2026
- Due: FY'28 E
- Verdict: Pending
- Evidence: Not due until 31 Mar 2028, after the latest results; later ones will show.
- Filing: <https://eqdoc.com/pdf/ann/7086961.pdf> (page 17)

## 2026-07-28 · Green power share will increase to 60% by FY28 alongside 376 MW WHRS and 1,122 MW renewable capacity.: Pending

- Said: 40 228 376 83 973 1,122 At the time of acquisition As of 30th Jun’26 Target (FY’28) WHRS RE Green Power Share 7% 34% 60%
- By: Company presentation, Investor presentation, 28 Jul 2026
- Due: FY'28
- Verdict: Pending
- Evidence: Not due until 31 Mar 2028, after the latest results; later ones will show.
- Filing: <https://eqdoc.com/pdf/ann/7086961.pdf> (page 17)

## 2026-07-28 · Maratha clinker line (4 MTPA) will be commissioned in calendar year 2027.: Pending

- Said: Kalamboli (1 MTPA), Warisaliganj (2.4 MTPA) will have trials in Q2 and Maratha clinker line (4 MTPA) will be commissioned in 2027.
- By: Company presentation, Investor presentation, 28 Jul 2026
- Due: 2027
- Verdict: Pending
- Evidence: Not due until 31 Dec 2027, after the latest results; later ones will show.
- Filing: <https://eqdoc.com/pdf/ann/7086961.pdf> (page 16)

## 2026-07-28 · The company will achieve a cost reduction of Rs 250 PMT in FY27 to reach Rs 4,250 PMT.: Pending

- Said: Ambuja remains firmly on track to deliver a Rs 250 PMT cost reduction in FY'27, to achieve committed cost target of Rs 4,250 PMT
- By: Company presentation, Investor presentation, 28 Jul 2026
- Due: FY'27
- Verdict: Pending
- Evidence: Not due until 31 Mar 2027, after the latest results; later ones will show.
- Filing: <https://eqdoc.com/pdf/ann/7086961.pdf> (page 16)

## 2026-01-30 · The company expects to reach a total capacity of 155 million tons by March 2028.: Pending

- Said: These initiatives will provide a clear and capital-efficient pathway to reach our aim of hitting 155 million tons by March of '28
- By: Vinod Bahety, Q3 FY26 earnings call
- Due: by March 2028
- Verdict: Pending
- Evidence: Not due until 31 Dec 2028, after the latest results; later ones will show.

## 2025-11-03 · The company expects to reach 1,122 megawatts of renewable energy capacity by FY 2027.: Pending

- Said: renewable energy capacity at 673 megawatts expected to reach almost 900-megawatt by the end of this financial year and 1,122 megawatts by FY '27.
- By: Vinod Bahety, Q2 FY26 earnings call
- Due: by FY 2027
- Verdict: Pending
- Evidence: Not due until 31 Mar 2027, after the latest results; later ones will show.
- Filing: <https://nsearchives.nseindia.com/corporate/AMBUJACEM_08112025162953_ACL_Earning_call__1_.pdf> (page 5)

## 2025-07-31 · The company targets a green power share of 60% by FY28.: Pending

- Said: Green power share uptake with every passing quarter. It improved by 9.7% to 28.1% and it is targeted to reach 60% by FY28.
- By: management, Q1 FY26 earnings call
- Due: by FY28
- Verdict: Pending
- Evidence: Not due until 31 Mar 2028, after the latest results; later ones will show.
- Filing: <https://nsearchives.nseindia.com/corporate/AMBUJACEM_06082025193356_ACL_Transcriptofearningcall.pdf> (page 5)

## 2025-04-29 · The company expects cement demand growth to be 8% in FY '26.: Slipped

- Said: we are expecting that it will have a continued improvement and reach, say, 8% overall demand growth for FY '26.
- By: Vinod Bahety, Q4 FY25 earnings call
- Due: in FY '26
- Verdict: Slipped
- Evidence: The Q4 FY26 call, 4 May 2026 settles it: “At an industry level, we believe that given the headlines of inflation and weak monsoon, the industry may grow at around, say, 5% to 5.5%.”

## 2025-01-29 · The company expects full-year capital expenditure to be between INR6,800 and INR7,000 crores for FY25.: Unverifiable

- Said: I think our number for the full year should be around INR6,800 crores to INR7,000 crores.
- By: Ajay Kapur, Q3 FY25 earnings call
- Due: for FY25
- Verdict: Unverifiable
- Evidence: We could not match this promise to a figure, and no later call settles it.

## 2025-01-29 · The company targets a cost of INR 3,650 per ton by March 2028.: Pending

- Said: In December 2023, if you remember, we have indicated a cost reduction target of INR530 per ton, wherein we aspire to achieve and reach to INR3,650 per ton by FY '28.
- By: Vinod Bahety, Q3 FY25 earnings call
- Due: by March 2028
- Verdict: Pending
- Evidence: Not due until 31 Mar 2028, after the latest results; later ones will show.

## 2024-07-31 · The company expects to commission 4 million tons of clinker and 6.4 million tons of cement capacity in FY25.: Unverifiable

- Said: 4 million ton clinkering and 6.4 million ton cement capacity is expected to be commissioned in FY25.
- By: Ajay Kapur, Q1 FY25 earnings call
- Due: in FY25
- Verdict: Unverifiable
- Evidence: We could not match this promise to a figure, and no later call settles it.

## 2024-07-31 · The company expects to reach a cement capacity of 100 million tons by Q2 FY26.: Unverifiable

- Said: With commissioning of these projects, we shall be reaching cement capacity of 100 million tons by Quarter 2 FY26
- By: Ajay Kapur, Q1 FY25 earnings call
- Due: by Q2 FY26
- Verdict: Unverifiable
- Evidence: We could not match this promise to a figure, and no later call settles it.