type: "Promise Ledger"
title: "Chalet Hotels Ltd: what management promised, and what happened"
description: "29 statements by Chalet Hotels Ltd's management, each checked against the company's later filings: 4 slipped, 3 missed, 17 pending, 5 unverifiable."
resource: "https://eqdoc.com/stock/CHALET"
tags: ["promise ledger","management guidance","india","chalet"]
sources: [{"resource":"https://nsearchives.nseindia.com/corporate/CHALET_29072026201516_AnalystPresentation29072026.pdf"},{"resource":"https://nsearchives.nseindia.com/corporate/CHALET_22052026113909_Transcript14052026.pdf"},{"resource":"https://nsearchives.nseindia.com/corporate/CHALET_12112025153356_Transcript05112025.pdf"},{"resource":"https://nsearchives.nseindia.com/corporate/CHALET_07082025205058_Transcript31072025.pdf"},{"resource":"https://nsearchives.nseindia.com/corporate/CHALET_01022024212847_Transcript25012024.pdf"}]
generated: {"by":"process:eqdoc-promise-audit","at":"2026-10-16"}
stale_after: "2027-01-24"
x-eqdoc-symbol: "CHALET"
x-eqdoc-counts: {"kept":0,"slipped":4,"missed":3,"pending":17,"unverifiable":5}
---

# How to read this

Each entry is something management said it would do, when it said it, and whether the company's later filings show it happened.
- **Kept**: a later filing shows it done. **Slipped**: done late or in part. **Missed**: the deadline passed without it.
- **Pending**: the deadline has not come, or no later filing yet speaks to it. **Unverifiable**: no filing could settle it.
- Evidence is either a sentence built from figures the company filed, or a quote from a later company document, as marked.

# Promises

## 2026-07-29 · The company aims to double its energy productivity by 2028.: Pending

- Said: EP100 (Energy Productivity): Double energy productivity (revenue per unit of electricity consumed) by 2028
- By: Company presentation, Investor presentation, 29 Jul 2026
- Due: by 2028
- Verdict: Pending
- Evidence: Not due until 31 Dec 2028, after the latest results; later ones will show.

## 2026-07-29 · The company aims to transition to 100% renewable energy by 2030.: Pending

- Said: RE100 (Renewable Energy): Move to 100% renewable energy by 2030
- By: Company presentation, Investor presentation, 29 Jul 2026
- Due: by 2030
- Verdict: Pending
- Evidence: Not due until 31 Dec 2030, after the latest results; later ones will show.

## 2026-07-29 · The company expects to open the Taj Delhi International Airport hotel with approximately 380 rooms by Q4 FY27.: Pending

- Said: Taj Delhi International Airport, New Delhi ~380 rooms New Delhi Q4 FY27*
- By: Company presentation, Investor presentation, 29 Jul 2026
- Due: by Q4 FY27
- Verdict: Pending
- Evidence: Not due until 31 Mar 2027, after the latest results; later ones will show.

## 2026-07-29 · The company has committed to achieving net-zero greenhouse gas emissions by 2040.: Pending

- Said: Chalet Hotels commits to achieve Net- Zero Greenhouse Gas (GHG) Emissions by 2040
- By: Company presentation, Investor presentation, 29 Jul 2026
- Due: by 2040
- Verdict: Pending
- Evidence: Not due until 31 Dec 2040, after the latest results; later ones will show.

## 2026-07-29 · The company plans to complete the construction of CIGNUS Powai Tower II by Q4 FY27.: Pending

- Said: CIGNUS Powai® Tower II 0.9 msf Mumbai Q4 FY27
- By: Company presentation, Investor presentation, 29 Jul 2026
- Due: by Q4 FY27
- Verdict: Pending
- Evidence: Not due until 31 Mar 2027, after the latest results; later ones will show.

## 2026-07-29 · The company plans to open the Athiva Resort & Spa in South Goa with 205 rooms in FY28.: Pending

- Said: Athiva Resort & Spa at Varca, South Goa 205 rooms Goa FY28
- By: Company presentation, Investor presentation, 29 Jul 2026
- Due: in FY28
- Verdict: Pending
- Evidence: Not due until 31 Mar 2028, after the latest results; later ones will show.

## 2026-07-29 · The company plans to open the Hyatt Regency in Navi Mumbai with 276 rooms by Q4 FY29.: Pending

- Said: Hyatt Regency at Airoli, Navi Mumbai 276 rooms Mumbai Q4 FY29
- By: Company presentation, Investor presentation, 29 Jul 2026
- Due: by Q4 FY29
- Verdict: Pending
- Evidence: Not due until 31 Mar 2029, after the latest results; later ones will show.

## 2026-07-29 · The company plans to open the Ritz Carlton in Hyderabad with 330 rooms by Q4 FY29.: Pending

- Said: Ritz Carlton at Hyderabad 330 rooms Hyderabad Q4 FY29
- By: Company presentation, Investor presentation, 29 Jul 2026
- Due: by Q4 FY29
- Verdict: Pending
- Evidence: Not due until 31 Mar 2029, after the latest results; later ones will show.

## 2026-07-29 · The company plans to transition its entire guest transportation fleet to electric vehicles by 2025.: Unverifiable

- Said: EV100 (Electric Vehicles): Move entire fleet to EVs for guest transportation by 2025
- By: Company presentation, Investor presentation, 29 Jul 2026
- Due: by 2025
- Verdict: Unverifiable
- Evidence: We could not match this promise to a figure, and no later call settles it.

## 2026-07-29 · Commercial space delivery timeline: Pending

- Said: Commercial FY28
- Due: FY28
- Verdict: Pending
- Filing: <https://nsearchives.nseindia.com/corporate/CHALET_29072026201516_AnalystPresentation29072026.pdf>

## 2026-07-29 · Residential Phase 2 handover completion: Pending

- Said: Residential 168 units (Phase - II) FY27
- Due: FY27
- Verdict: Pending
- Filing: <https://nsearchives.nseindia.com/corporate/CHALET_29072026201516_AnalystPresentation29072026.pdf>

## 2026-07-29 · Taj Delhi Airport operational launch: Pending

- Said: 70-rooms to be operational by Q4 FY27; balance in Q1 FY28
- Due: Q4 FY27
- Verdict: Pending
- Filing: <https://nsearchives.nseindia.com/corporate/CHALET_29072026201516_AnalystPresentation29072026.pdf>

## 2026-05-15 · The company expects monthly rental income to reach INR 300 million during fiscal year 2027.: Pending

- Said: We expect monthly rentals to scale up to INR300 million during FY '27.
- By: Nitin Khanna, Q4 FY26 earnings call
- Due: during fiscal year 2027
- Verdict: Pending
- Evidence: Not due until 31 Mar 2027, after the latest results; later ones will show.
- Filing: <https://nsearchives.nseindia.com/corporate/CHALET_22052026113909_Transcript14052026.pdf> (page 7)

## 2025-11-12 · Cignus 2 completion: Pending

- Said: Our second commercial tower - Cignus 2 at Westin Powai Lake is also on track for completion in Q4 FY27.
- Due: Q4 FY27
- Verdict: Pending
- Filing: <https://nsearchives.nseindia.com/corporate/CHALET_12112025153356_Transcript05112025.pdf>

## 2025-11-12 · Delhi Airport hotel opening: Pending

- Said: construction at our upcoming Delhi Airport hotel is progressing on schedule with the opening expected in the first half of next financial year.
- Due: H1 FY27
- Verdict: Pending
- Filing: <https://nsearchives.nseindia.com/corporate/CHALET_12112025153356_Transcript05112025.pdf>

## 2025-11-12 · Monthly rental exit run rate: Missed

- Said: From my earlier statement, exit of March, we are still expected to exit at INR30 crores per month rental.
- Due: 2026-03-31
- Verdict: Missed
- Later filing says (2026-05-22): The monthly rental exit run rate in March '26 stood at INR280 million.
- Filing: <https://nsearchives.nseindia.com/corporate/CHALET_12112025153356_Transcript05112025.pdf>

## 2025-11-05 · The company plans to invest INR25 billion in capital expenditure over the next 3 years.: Pending

- Said: Under our current strategy, we have planned capex of INR25 billion over the next 3 years, primarily funded through our internal accruals.
- By: Nitin Khanna, Q2 FY26 earnings call
- Verdict: Pending
- Evidence: Not due until 5 Nov 2028, after the latest results; later ones will show.
- Filing: <https://nsearchives.nseindia.com/corporate/CHALET_12112025153356_Transcript05112025.pdf> (page 7)

## 2025-11-12 · Varca Goa construction commencement: Missed

- Said: For our property in Varca, Goa, we still await the final approvals and aim to commence construction in Q4 of the current financial year.
- Due: Q4 FY26
- Verdict: Missed
- Later filing says (2026-08-05): We still hope to start construction by the end of this quarter, essentially once the rainy season is behind us.
- Filing: <https://nsearchives.nseindia.com/corporate/CHALET_12112025153356_Transcript05112025.pdf>

## 2025-08-01 · The company expects to reach a total of 5,000 hotel rooms by the end of the current financial year.: Unverifiable

- Said: I see no reason why our pipeline plus operating hotels will not cross the 5,000 marks in the current financial year itself.
- By: Sanjay Sethi, Q1 FY26 earnings call
- Verdict: Unverifiable
- Evidence: We could not match this promise to a figure, and no later call settles it.
- Filing: <https://nsearchives.nseindia.com/corporate/CHALET_07082025205058_Transcript31072025.pdf> (page 7)

## 2024-10-25 · The Taj hotel at Delhi Airport is expected to open by June 2026.: Pending

- Said: The Taj at the T3 Terminal in Delhi international airport, which was scheduled to open by end of FY '26 is now delayed and expected to open potentially by June of 2026.
- By: Sanjay Sethi, Q2 FY25 earnings call
- Due: by June 2026
- Verdict: Pending
- Evidence: Not due until 31 Dec 2026, after the latest results; later ones will show.

## 2024-10-25 · The company expects its net debt to peak at between INR 1,850 crores and INR 1,900 crores.: Unverifiable

- Said: And expect us to peak at no more than INR1,850 crores, INR1,900 crores.
- By: Sanjay Sethi, Q2 FY25 earnings call
- Verdict: Unverifiable
- Evidence: We could not match this promise to a figure, and no later call settles it.

## 2024-07-26 · The company expects 90% of its office portfolio to be leased by the end of the calendar year.: Unverifiable

- Said: We continue to expect 90% of the office portfolio leased out by end of the calendar year.
- By: Sanjay Sethi, Q1 FY25 earnings call
- Verdict: Unverifiable
- Evidence: We could not match this promise to a figure, and no later call settles it.

## 2024-07-26 · The company plans to invest INR15 billion in capital expenditure over the next 7 quarters.: Unverifiable

- Said: The company continues to invest in its growth and has a capex plan of around INR15 billion for the next 7 quarters
- By: Nitin Khanna, Q1 FY25 earnings call
- Verdict: Unverifiable
- Evidence: We could not match this promise to a figure, and no later call settles it.

## 2024-02-01 · Bangalore building leasing timeline: Missed

- Said: So Bangalore, we expect entire building of 6.5 lakh square feet will be leased out by this end of financial year.
- Due: FY24
- Verdict: Missed
- Later filing says (2024-05-17): We had roughly, If I recall, about 4 lakh square foot of Bangalore that was leased out earlier. We've and you'll probably see from the presentation another, I think, 40,000-odd square feet
- Filing: <https://nsearchives.nseindia.com/corporate/CHALET_01022024212847_Transcript25012024.pdf>

## 2024-02-01 · CAPEX plan next 15 months: Pending

- Said: The company has CAPEX plan of around Rs 8 billion for the next 15 months for the projects which are already announced and this CAPEX will be largely funded through internal accruals.
- Due: FY25
- Verdict: Pending
- Filing: <https://nsearchives.nseindia.com/corporate/CHALET_01022024212847_Transcript25012024.pdf>

## 2024-02-01 · Commercial tower sale post OC: Slipped

- Said: The commercial tower of 1.5 lakh square feet will be sold post receipt of OC in FY'26.
- Due: FY26
- Verdict: Slipped
- Later filing says (2026-05-22): The project also includes 160,000 square feet of commercial space, which is yet to be developed and will be leased post completion.
- Filing: <https://nsearchives.nseindia.com/corporate/CHALET_01022024212847_Transcript25012024.pdf>

## 2024-02-01 · Dukes Retreat expansion room count: Slipped

- Said: We'll end up somewhere between 140 and 150 rooms at the end of after we've completed the renovation expansion by Q3 of the next financial year.
- Due: Q3 FY25
- Verdict: Slipped
- Later filing says (2025-05-19): The Dukes Retreat, Khandala is undergoing the final stage of upgradation and repositioning. As I mentioned last quarter, 73 rooms are in operation and by end of this month, the banquet hall
- Filing: <https://nsearchives.nseindia.com/corporate/CHALET_01022024212847_Transcript25012024.pdf>

## 2024-02-01 · Hyatt Regency Airoli work commencement: Slipped

- Said: Work at Hyatt Regency, Airoli will commence in next quarter after receipt of the revised construction approvals.
- Due: Q4 FY24
- Verdict: Slipped
- Later filing says (2026-05-22): Mindspace has begun excavation work at Hyderabad and Airoli. Both the projects are on track.
- Filing: <https://nsearchives.nseindia.com/corporate/CHALET_01022024212847_Transcript25012024.pdf>

## 2024-02-01 · Powai commercial leasing completion: Slipped

- Said: We expect around 4,50,000 to 5,00,000 to be signed by this year end and balance in the next financial year. In Q4 of next financial year, I mean, everything will be leased out
- Due: Q4 FY25
- Verdict: Slipped
- Later filing says (2026-05-22): Occupancy at Powai remains strong at 90%.
- Filing: <https://nsearchives.nseindia.com/corporate/CHALET_01022024212847_Transcript25012024.pdf>