type: "Promise Ledger"
title: "Deepak Nitrite Ltd: what management promised, and what happened"
description: "29 statements by Deepak Nitrite Ltd's management, each checked against the company's later filings: 2 kept, 7 slipped, 18 pending, 2 unverifiable."
resource: "https://eqdoc.com/stock/DEEPAKNTR"
tags: ["promise ledger","management guidance","india","deepakntr"]
sources: [{"resource":"https://nsearchives.nseindia.com/corporate/DEEPAKNTR_22052026102706_NSE-CONCALL-Transcript_letter-2026.pdf"},{"resource":"https://nsearchives.nseindia.com/corporate/DEEPAKNTR_18022026153557_NSEConcallTranscript.pdf"},{"resource":"https://nsearchives.nseindia.com/corporate/DEEPAKNTR_03062025170633_NSECONCALLTRANSCRIPT03062025.pdf"},{"resource":"https://nsearchives.nseindia.com/corporate/DEEPAKNTR_21022024150907_NSETRANSCRIPT21224FINAL.pdf"}]
generated: {"by":"process:eqdoc-promise-audit","at":"2026-10-11"}
stale_after: "2027-01-19"
x-eqdoc-symbol: "DEEPAKNTR"
x-eqdoc-counts: {"kept":2,"slipped":7,"missed":0,"pending":18,"unverifiable":2}
---

# How to read this

Each entry is something management said it would do, when it said it, and whether the company's later filings show it happened.
- **Kept**: a later filing shows it done. **Slipped**: done late or in part. **Missed**: the deadline passed without it.
- **Pending**: the deadline has not come, or no later filing yet speaks to it. **Unverifiable**: no filing could settle it.
- Evidence is either a sentence built from figures the company filed, or a quote from a later company document, as marked.

# Promises

## 2026-08-04 · The company aims to achieve full integration across the ammonia-nitration-amines spectrum.: Pending

- Said: Deepak Group to become one of the few global players to achieve full integration across ammonia-nitration-amines spectrum
- By: Company presentation, Investor presentation, 4 Aug 2026
- Verdict: Pending
- Evidence: Not due yet, so it can't be checked.

## 2026-08-04 · The company expects the imminent commissioning of specialty agrochem and multi-purpose plants.: Pending

- Said: imminent commissioning of specialty agrochem and multi-purpose plants for specialty products
- By: Company presentation, Investor presentation, 4 Aug 2026
- Verdict: Pending
- Evidence: Not due yet, so it can't be checked.

## 2026-08-04 · The company is building India's first integrated polycarbonate plant with a capacity of 165,000 MT/yr.: Pending

- Said: India’s first integrated Polycarbonate plant (165,000 MT/yr)
- By: Company presentation, Investor presentation, 4 Aug 2026
- Verdict: Pending
- Evidence: Not due yet, so it can't be checked.

## 2026-08-04 · The company is implementing digital initiatives including SAP S/4HANA migration and AI/ML-driven smart manufacturing.: Pending

- Said: Digital initiatives include SAP S/4HANA migration, AI/ML-driven smart manufacturing, optimize power and predictive analytics through a Digital Innovation Lab
- By: Company presentation, Investor presentation, 4 Aug 2026
- Verdict: Pending
- Evidence: Not due yet, so it can't be checked.

## 2026-08-04 · The company targets a 60-70% renewable energy mix starting from FY27.: Pending

- Said: Target: 60-70% renewable energy mix progressively from FY27.
- By: Company presentation, Investor presentation, 4 Aug 2026
- Due: starting from FY27
- Verdict: Pending
- Evidence: Not due until 31 Mar 2027, after the latest results; later ones will show.

## 2026-08-04 · The company targets the commissioning of its HyCO plant in 2028.: Pending

- Said: Commissioning targeted in 2028, in line with DCTL’s Polycarbonate project timeline
- By: Company presentation, Investor presentation, 4 Aug 2026
- Due: in 2028
- Verdict: Pending
- Evidence: Not due until 31 Dec 2028, after the latest results; later ones will show.

## 2026-05-22 · Agrochemical intermediates and MIBK commissioning: Pending

- Said: We witnessed a steady progress of our multipurpose agrochemical intermediates and MIBK, MIBC projects, which are scheduled for commissioning in Q2 FY27.
- Due: Q2 FY27
- Verdict: Pending
- Filing: <https://nsearchives.nseindia.com/corporate/DEEPAKNTR_22052026102706_NSE-CONCALL-Transcript_letter-2026.pdf>

## 2026-05-22 · Commercial production of new molecules: Pending

- Said: So in all of these, as we said earlier, we anticipate commercial production on a regularized basis from Q3 onwards because this will reach our export customers towards the end of Q3 in time
- Due: Q3 FY27
- Verdict: Pending
- Filing: <https://nsearchives.nseindia.com/corporate/DEEPAKNTR_22052026102706_NSE-CONCALL-Transcript_letter-2026.pdf>

## 2026-05-22 · MIBK MIBC plant commissioning timeline: Pending

- Said: And at some point, maybe perhaps at the tail end of Q1 or the early part of Q2 is when we will be looking at commissioning of the asset
- Due: Q2 FY27
- Verdict: Pending
- Filing: <https://nsearchives.nseindia.com/corporate/DEEPAKNTR_22052026102706_NSE-CONCALL-Transcript_letter-2026.pdf>

## 2026-05-22 · Polycarbonate project commissioning: Pending

- Said: So we've clarified earlier, and we are, by and large, remaining kind of in line with that, and we are expecting it to be commissioned by June 2028.
- Due: 2028-06-30
- Verdict: Pending
- Filing: <https://nsearchives.nseindia.com/corporate/DEEPAKNTR_22052026102706_NSE-CONCALL-Transcript_letter-2026.pdf>

## 2026-05-22 · Project funding equity drawdown debt: Pending

- Said: And once we put in 25% of equity as per the bank condition of 40%, we'll start drawing from the debt.
- Verdict: Pending
- Filing: <https://nsearchives.nseindia.com/corporate/DEEPAKNTR_22052026102706_NSE-CONCALL-Transcript_letter-2026.pdf>

## 2026-05-18 · The company expects financial performance in the first quarter of fiscal year 2027 to be better than the fourth quarter: Pending

- Said: I can say that our Q1 looks on track for numbers, which are better than Q4, whether it is on standalone or on a consolidated basis.
- By: Maulik Mehta, Q4 FY26 earnings call
- Due: in the first quarter of fiscal year 2027
- Verdict: Pending
- Evidence: Not due until 31 Dec 2027, after the latest results; later ones will show.

## 2026-02-13 · The company expects financial performance in Q4 FY26 to exceed that of Q3 FY26.: Kept

- Said: I definitely expect Q4 FY26 to be better than Q3 FY26.
- By: Maulik Mehta, Q3 FY26 earnings call
- Due: in Q4 FY26
- Verdict: Kept
- Evidence: Net profit went from ₹100 cr in the Dec 2025 quarter to ₹220 cr in the Mar 2026 quarter.
- Filing: <https://nsearchives.nseindia.com/corporate/DEEPAKNTR_18022026153557_NSEConcallTranscript.pdf> (page 10)

## 2025-11-14 · The company expects to commission the polycarbonate project in the January to March 2028 quarter.: Slipped

- Said: So commissioning, we had mentioned earlier, it will be in the month of January to March 2028 quarter.
- By: Sanjay Upadhyay, Q2 FY26 earnings call
- Verdict: Slipped
- Evidence: The Q4 FY26 call, 18 May 2026 settles it: “we are expecting it to be commissioned by June 2028.”

## 2025-06-03 · FY26 cash capex guidance: Pending

- Said: our cash capex for this year should be around INR 1,500 crore.
- Due: FY26
- Verdict: Pending
- Filing: <https://nsearchives.nseindia.com/corporate/DEEPAKNTR_03062025170633_NSECONCALLTRANSCRIPT03062025.pdf>

## 2025-06-03 · MIBK and MIBC project commissioning: Slipped

- Said: By the second half of FY26, we expect to commission the MIBK and MIBC project, which are downstream derivatives of acetone.
- Due: H2 FY26
- Verdict: Slipped
- Later filing says (2026-08-11): MIBK as well as MIBC will be commissioned along with acetophenone in August itself, and the rest of them will be commissioned within Q2.
- Filing: <https://nsearchives.nseindia.com/corporate/DEEPAKNTR_03062025170633_NSECONCALLTRANSCRIPT03062025.pdf>

## 2025-06-03 · Nitric acid unit commissioning: Slipped

- Said: The nitric acid unit will be commissioned towards the end of Q1, early Q2.
- Due: Q2 FY26
- Verdict: Slipped
- Later filing says (2026-02-18): So we commissioned the nitric acid plant in the middle of December 2025.
- Filing: <https://nsearchives.nseindia.com/corporate/DEEPAKNTR_03062025170633_NSECONCALLTRANSCRIPT03062025.pdf>

## 2025-06-03 · R&D center commissioning in Savli: Kept

- Said: By the second quarter, we anticipate the commissioning of our state-of-the-art R&D center in Savli, Vadodara. This involves over INR 100 crore of capex.
- Due: Q2 FY26
- Verdict: Kept
- Later filing says (2025-11-13): New R&D Centre at Savli, Vadodara was inaugurated on 1st October 2025, built with an investment of ₹100 Crore and spread across a 5-acre campus
- Filing: <https://nsearchives.nseindia.com/corporate/DEEPAKNTR_03062025170633_NSECONCALLTRANSCRIPT03062025.pdf>

## 2025-06-03 · Renewable power share target: Pending

- Said: benefits from renewable hybrid power arrangements, which will encompass almost 60% of our total consumption by the end of next year.
- Due: FY26
- Verdict: Pending
- Filing: <https://nsearchives.nseindia.com/corporate/DEEPAKNTR_03062025170633_NSECONCALLTRANSCRIPT03062025.pdf>

## 2024-11-14 · The company expects margin expansion starting from the fourth quarter.: Unverifiable

- Said: moving forward from Q4 onwards, we are anticipating with reasonable confidence that there will be margin expansion.
- By: Maulik Mehta, Q2 FY25 earnings call
- Verdict: Unverifiable
- Evidence: We could not match this promise to a figure, and no later call settles it.

## 2024-08-08 · The Rs. 2,000 crore capital expenditure project is expected to be completed by the end of the fourth quarter.: Slipped

- Said: Rs. 2,000 crores capex, by and large, it will be over by fourth quarter end.
- By: Sanjay Upadhyay, Q1 FY25 earnings call
- Verdict: Slipped
- Evidence: The Q3 FY25 call, 17 Feb 2025 settles it: “projects which were targeted to be commissioned in Q3 and Q4 have faced delays in their final stretches and are now set to add value from Q1 onwards.”

## 2024-08-08 · The company expects a meaningful recovery in performance starting in the latter part of the third quarter.: Unverifiable

- Said: we maintain our short-term guidance of meaningful recovery starting from latter part of Quarter 3.
- By: Maulik Mehta, Q1 FY25 earnings call
- Verdict: Unverifiable
- Evidence: We could not match this promise to a figure, and no later call settles it.

## 2024-08-08 · The company expects to commission its new acetophenone facility in approximately 12 months.: Slipped

- Said: Further, we are implementing world-scale capabilities of acetophenone... This is under implementation and is likely to be commissioned in about 12 months.
- By: Maulik Mehta, Q1 FY25 earnings call
- Verdict: Slipped
- Evidence: The Q3 FY25 call, 17 Feb 2025 settles it: “MIBK, MIBC, acetophenone and other backward and forward integrations are expected to be commissioned in H1 FY2026.”

## 2024-02-21 · Completion of MoU investments: Pending

- Said: Projects covered by this investment of about Rs. 9,000 crore will be completed by 2027. The projects of all the investments that have been announced will be completed by 2027.
- Due: 2027
- Verdict: Pending
- Filing: <https://nsearchives.nseindia.com/corporate/DEEPAKNTR_21022024150907_NSETRANSCRIPT21224FINAL.pdf>

## 2024-02-21 · Fluorination and Photochlorination commissioning: Pending

- Said: The operation and commissioning team are actively involved in preparing for the system handover of the high-pressure fluorination and Photochlorination project, with commissioning being anticipated within this current quarter.
- Due: Q4 FY24
- Verdict: Pending
- Filing: <https://nsearchives.nseindia.com/corporate/DEEPAKNTR_21022024150907_NSETRANSCRIPT21224FINAL.pdf>

## 2024-02-21 · Greenfield Phenol expansion commissioning: Pending

- Said: Before 2027, it should be commissioned, before end of 2027 that is when we will be consuming this increased amount of propylene.
- Due: 2027-12-31
- Verdict: Pending
- Filing: <https://nsearchives.nseindia.com/corporate/DEEPAKNTR_21022024150907_NSETRANSCRIPT21224FINAL.pdf>

## 2024-02-21 · Project commissioning pipeline: Slipped

- Said: Our project pipeline remains robust and investment of around Rs. 2,000 crores are expected to be commissioned between January to December 2024.
- Due: 2024-12-31
- Verdict: Slipped
- Later filing says (2025-02-21): Finally, projects which were targeted to be commissioned in Q3 and Q4 have faced delays in their final stretches and are now set to add value from Q1 onwards.
- Filing: <https://nsearchives.nseindia.com/corporate/DEEPAKNTR_21022024150907_NSETRANSCRIPT21224FINAL.pdf>

## 2024-02-21 · Propylene and hydrogen offtake: Pending

- Said: We are set to uptake 250 KTPA propylene and 11 KTPA of hydrogen over a 15-year period from the initial delivery.
- Verdict: Pending
- Filing: <https://nsearchives.nseindia.com/corporate/DEEPAKNTR_21022024150907_NSETRANSCRIPT21224FINAL.pdf>

## 2024-02-21 · R&D center operationalization: Slipped

- Said: We will also be putting up an investment for a world class research and development center which is also by the way, progressing well and should see the light of day maybe by about 12 months from now.
- Due: 2025-02-15
- Verdict: Slipped
- Later filing says (2025-11-13): New R&D Centre at Savli, Vadodara was inaugurated on 1st October 2025, built with an investment of ₹100 Crore and spread across a 5-acre campus
- Filing: <https://nsearchives.nseindia.com/corporate/DEEPAKNTR_21022024150907_NSETRANSCRIPT21224FINAL.pdf>