type: "Promise Ledger"
title: "Endurance Technologies Ltd: what management promised, and what happened"
description: "27 statements by Endurance Technologies Ltd's management, each checked against the company's later filings: 2 kept, 8 slipped, 2 missed, 12 pending, 3 unverifiable."
resource: "https://eqdoc.com/stock/ENDURANCE"
tags: ["promise ledger","management guidance","india","endurance"]
sources: [{"resource":"https://nsearchives.nseindia.com/corporate/ENDURANCE_13082026174651_2026_08_13_-_Investor_Presentation-signed.pdf"},{"resource":"https://nsearchives.nseindia.com/corporate/ENDURANCE_22052026142524_2026_05_22_-_Transcript_of_EarningsCall.pdf"},{"resource":"https://nsearchives.nseindia.com/corporate/ENDURANCE_19022026174447_Transcript.pdf"},{"resource":"https://nsearchives.nseindia.com/corporate/ENDURANCE_20112025174935_2025_11_20_-_Transcript_of_Earnings_Conference_Call_on_13_11_2025.pdf"},{"resource":"https://nsearchives.nseindia.com/corporate/ENDURANCE_22082025153100_20250822TranscriptofEarningsConferenceCallon14082025.pdf"},{"resource":"https://nsearchives.nseindia.com/corporate/ENDURANCE_23052025190735_2025_05_23__Transcript_of_Earnings_Conference_Call_on_16th_May_2025.pdf"},{"resource":"https://nsearchives.nseindia.com/corporate/ENDURANCE_18022025173419_20250218transcriptofearningsconferencecall13thfeb25.pdf"},{"resource":"https://nsearchives.nseindia.com/corporate/ENDURANCE_14112024161425_20241114TranscriptofEarningsConferenceCall7thNovember2024.pdf"},{"resource":"https://nsearchives.nseindia.com/corporate/ENDURANCE_13022024193909_Transcript.pdf"}]
generated: {"by":"process:eqdoc-promise-audit","at":"2026-10-07"}
stale_after: "2027-01-15"
x-eqdoc-symbol: "ENDURANCE"
x-eqdoc-counts: {"kept":2,"slipped":8,"missed":2,"pending":12,"unverifiable":3}
---

# How to read this

Each entry is something management said it would do, when it said it, and whether the company's later filings show it happened.
- **Kept**: a later filing shows it done. **Slipped**: done late or in part. **Missed**: the deadline passed without it.
- **Pending**: the deadline has not come, or no later filing yet speaks to it. **Unverifiable**: no filing could settle it.
- Evidence is either a sentence built from figures the company filed, or a quote from a later company document, as marked.

# Promises

## 2026-08-13 · 4W Battery Packs capacity SOP: Pending

- Said: Capacity expansion to manufacture 4W Battery Packs, SOP expected in Q4FY27.
- Due: Q4FY27
- Verdict: Pending
- Filing: <https://nsearchives.nseindia.com/corporate/ENDURANCE_13082026174651_2026_08_13_-_Investor_Presentation-signed.pdf>

## 2026-08-13 · AURIC Shendra project SOP: Pending

- Said: Setting up AURIC Shendra project in Chh. Sambhajinagar, focused on Machined Castings for 4W and non-automotive. SOP expected by Q2FY27.
- Due: Q2FY27
- Verdict: Pending
- Filing: <https://nsearchives.nseindia.com/corporate/ENDURANCE_13082026174651_2026_08_13_-_Investor_Presentation-signed.pdf>

## 2026-08-13 · Acquisition of remaining Stöferle stake: Pending

- Said: Stake in Stöferle entities in Germany raised to 68%. Acquisition of remaining stake over the next 4 years.
- Due: FY31
- Verdict: Pending
- Filing: <https://nsearchives.nseindia.com/corporate/ENDURANCE_13082026174651_2026_08_13_-_Investor_Presentation-signed.pdf>

## 2026-08-13 · Aluminium Forging plant SOP: Pending

- Said: New plant being constructed to meet growing Aluminium Forging production. SOP expected in Q3FY27.
- Due: Q3FY27
- Verdict: Pending
- Filing: <https://nsearchives.nseindia.com/corporate/ENDURANCE_13082026174651_2026_08_13_-_Investor_Presentation-signed.pdf>

## 2026-08-13 · Dual channel ABS SOP: Pending

- Said: Dual channel ABS SOP expected in Q2FY27.
- Due: Q2FY27
- Verdict: Pending
- Filing: <https://nsearchives.nseindia.com/corporate/ENDURANCE_13082026174651_2026_08_13_-_Investor_Presentation-signed.pdf>

## 2026-08-13 · Sanand plant Actuators SOP: Pending

- Said: Setting up new infrastructure at the Sanand plant in Gujarat to cater to large volume orders for Solar Dampers and Actuators. SOP for Solar Damper took place in Q2FY27, Actuators expected in Q4FY27.
- Due: Q4FY27
- Verdict: Pending
- Filing: <https://nsearchives.nseindia.com/corporate/ENDURANCE_13082026174651_2026_08_13_-_Investor_Presentation-signed.pdf>

## 2026-05-15 · Begin solar actuator business operations from H2 FY27 at the Sanand plant.: Pending

- Said: The solar actuator business will start from H2 of this financial year from a new building at our Sanand plant in Gujarat.
- By: Anurang Jain, Q4 FY26 earnings call
- Due: H2 of this financial year
- Verdict: Pending
- Evidence: Not due until 31 Mar 2027, after the latest results; later ones will show.
- Filing: <https://nsearchives.nseindia.com/corporate/ENDURANCE_22052026142524_2026_05_22_-_Transcript_of_EarningsCall.pdf> (page 7)

## 2026-05-15 · Start SOP for Royal Enfield at the new Chennai plant in July 2026.: Slipped

- Said: From this plant, SOP for Royal Enfield is planned in July 2026, and for other OEMs from Q3 of this financial year.
- By: Anurang Jain, Q4 FY26 earnings call
- Due: July 2026 / Q3 of this financial year
- Verdict: Slipped
- Evidence: The Q1 FY27 call, 14 Aug 2026 settles it: “The SOP for Royal Enfield is expected by next month, with other OEMs following in Q3.”
- Filing: <https://nsearchives.nseindia.com/corporate/ENDURANCE_22052026142524_2026_05_22_-_Transcript_of_EarningsCall.pdf> (page 5)

## 2026-02-13 · Start SOP for dual channel ABS program in March 2026.: Slipped

- Said: For the dual channel ABS program, SOP is now expected to start next month, as we await the final clearance from a key OEM customer.
- By: Anurang Jain, Q3 FY26 earnings call
- Due: next month
- Verdict: Slipped
- Evidence: The Q4 FY26 call, 15 May 2026 settles it: “For our dual-channel ABS, SOP will start in June 2026 for Bajaj Auto, with a sale of 120,000 units per annum”
- Filing: <https://nsearchives.nseindia.com/corporate/ENDURANCE_19022026174447_Transcript.pdf> (page 4)

## 2025-11-13 · Commence SOP for 4W driveshaft in Q4 FY26.: Slipped

- Said: As mentioned earlier, we have started on vehicle testing for our first 4W Driveshaft order. We expect to commence SOP in Q4 FY 26.
- By: Anurang Jain, Q2 FY26 earnings call
- Due: Q4 FY 26
- Verdict: Slipped
- Evidence: The Q4 FY26 call, 15 May 2026 settles it: “The SOP for Tata Motors will start next month in June 2026.”
- Filing: <https://nsearchives.nseindia.com/corporate/ENDURANCE_20112025174935_2025_11_20_-_Transcript_of_Earnings_Conference_Call_on_13_11_2025.pdf> (page 7)

## 2025-08-22 · ABS setup expansion in Waluj: Missed

- Said: This would involve expanding our ABS set-up in Waluj, for which the process has already started and will complete by March 2026.
- Due: 2026-03
- Verdict: Missed
- Later filing says (2026-08-21): Though the government is yet to issue final guidelines, our ABS and CBS hydraulic brake expansion is progressing as planned, with SOP expected in September or early October 2026.
- Filing: <https://nsearchives.nseindia.com/corporate/ENDURANCE_22082025153100_20250822TranscriptofEarningsConferenceCallon14082025.pdf>

## 2025-08-22 · AURIC Bidkin alloy wheel plant SOP: Slipped

- Said: I am pleased to inform you that the SOP at our 2W alloy wheel plant in AURIC Bidkin will start in week 4 of this month.
- Due: 2025-08
- Verdict: Slipped
- Later filing says (2025-11-12): Production commenced at the Alloy Wheel plant at AURIC Bidkin in Oct 2025, with 3.6 Mn wheels/annum capacity fully booked.
- Filing: <https://nsearchives.nseindia.com/corporate/ENDURANCE_22082025153100_20250822TranscriptofEarningsConferenceCallon14082025.pdf>

## 2025-08-22 · AURIC Shendra facility SOP: Pending

- Said: The SOP is now planned in Quarter 4 of this financial year.
- Due: FY26-Q4
- Verdict: Pending
- Filing: <https://nsearchives.nseindia.com/corporate/ENDURANCE_22082025153100_20250822TranscriptofEarningsConferenceCallon14082025.pdf>

## 2025-08-22 · Aluminum forging supplies to JLR: Missed

- Said: Our supplies to Jaguar Land Rover are expected to begin in January 2026.
- Due: 2026-01
- Verdict: Missed
- Later filing says (2026-05-22): supplies to Jaguar Land Rover are scheduled for August 2026.
- Filing: <https://nsearchives.nseindia.com/corporate/ENDURANCE_22082025153100_20250822TranscriptofEarningsConferenceCallon14082025.pdf>

## 2025-08-22 · Battery pack facility SOP: Slipped

- Said: Protos will be submitted in this quarter, which is in line with our planned SOP in January 2026.
- Due: 2026-01
- Verdict: Slipped
- Later filing says (2026-08-13): Production commenced at the Battery Pack plant in Pune in Q1FY27.
- Filing: <https://nsearchives.nseindia.com/corporate/ENDURANCE_22082025153100_20250822TranscriptofEarningsConferenceCallon14082025.pdf>

## 2025-08-22 · Maxwell BMS supply for electric buggies: Pending

- Said: airport cargo handling electric buggies where BMS supply will begin in November 2025.
- Due: 2025-11
- Verdict: Pending
- Filing: <https://nsearchives.nseindia.com/corporate/ENDURANCE_22082025153100_20250822TranscriptofEarningsConferenceCallon14082025.pdf>

## 2025-05-16 · Begin operations for the battery pack plant in January 2026.: Slipped

- Said: The SOP is planned in January 2026.
- By: Anurang Jain, Q4 FY25 earnings call
- Due: January 2026
- Verdict: Slipped
- Evidence: The Q3 FY26 call, 13 Feb 2026 settles it: “Post OEM and regulatory approvals, commercial ramp-up activities will be started to support the SOP from end of March 2026 or early April 2026.”
- Filing: <https://nsearchives.nseindia.com/corporate/ENDURANCE_23052025190735_2025_05_23__Transcript_of_Earnings_Conference_Call_on_16th_May_2025.pdf> (page 4)

## 2025-05-16 · Make the G45 Waluj R&D facility fully operational within one month.: Unverifiable

- Said: Our G45 Waluj R&D facility for two, three and four -wheeler suspensions will be fully operational in a month
- By: Anurang Jain, Q4 FY25 earnings call
- Due: in a month
- Verdict: Unverifiable
- Evidence: We could not match this promise to a figure, and no later call settles it.
- Filing: <https://nsearchives.nseindia.com/corporate/ENDURANCE_23052025190735_2025_05_23__Transcript_of_Earnings_Conference_Call_on_16th_May_2025.pdf> (page 5)

## 2025-02-13 · Close the Stöferle acquisition transaction by the end of FY25.: Unverifiable

- Said: I presume that within the end of this financial year, we can close the transaction.
- By: Massimo Venuti, Q3 FY25 earnings call
- Due: end of this financial year
- Verdict: Unverifiable
- Evidence: We could not match this promise to a figure, and no later call settles it.
- Filing: <https://nsearchives.nseindia.com/corporate/ENDURANCE_18022025173419_20250218transcriptofearningsconferencecall13thfeb25.pdf> (page 15)

## 2025-02-13 · Start SOP at the AURIC Shendra plant in June 2025.: Slipped

- Said: The plant infrastructure is set to be ready by the end of February, 2025 and the SOP is planned for June 2025.
- By: Anurang Jain, Q3 FY25 earnings call
- Due: June 2025
- Verdict: Slipped
- Evidence: The Q1 FY26 call, 14 Aug 2025 settles it: “The SOP is now planned in Quarter 4 of this financial year.”
- Filing: <https://nsearchives.nseindia.com/corporate/ENDURANCE_18022025173419_20250218transcriptofearningsconferencecall13thfeb25.pdf> (page 5)

## 2024-11-07 · Begin production at the AURIC Bidkin alloy wheel plant in September 2025.: Unverifiable

- Said: And this plant is going to start in September 2025.
- By: Anurang Jain, Q2 FY25 earnings call
- Due: September 2025
- Verdict: Unverifiable
- Evidence: We could not match this promise to a figure, and no later call settles it.
- Filing: <https://nsearchives.nseindia.com/corporate/ENDURANCE_14112024161425_20241114TranscriptofEarningsConferenceCall7thNovember2024.pdf> (page 9)

## 2024-11-07 · Start SOP for the two-channel ABS in Q4 FY25.: Slipped

- Said: The two-channel ABS is also at an advanced stage and is expected to start SOP in Q4 of this financial year.
- By: Anurang Jain, Q2 FY25 earnings call
- Due: Q4 of this financial year
- Verdict: Slipped
- Evidence: The Q4 FY26 call, 15 May 2026 settles it: “For our dual-channel ABS, SOP will start in June 2026 for Bajaj Auto, with a sale of 120,000 units per annum”
- Filing: <https://nsearchives.nseindia.com/corporate/ENDURANCE_14112024161425_20241114TranscriptofEarningsConferenceCall7thNovember2024.pdf> (page 5)

## 2024-02-13 · 4-wheeler business share target: Pending

- Said: We want to increase our 4-wheeler share of consolidated business in the four wheeler industry from 26% today to 45% by FY30.
- Due: FY30
- Verdict: Pending
- Filing: <https://nsearchives.nseindia.com/corporate/ENDURANCE_13022024193909_Transcript.pdf>

## 2024-02-13 · Aftermarket sales share target: Pending

- Said: Our focus is to reach 10% of India sales in the aftermarket business by FY28.
- Due: FY28
- Verdict: Pending
- Filing: <https://nsearchives.nseindia.com/corporate/ENDURANCE_13022024193909_Transcript.pdf>

## 2024-02-13 · Alloy wheel capacity expansion SOP: Kept

- Said: With new order wins from Royal Enfield and TVS, we've now expanded the capacity to supply 5.5 million wheels per annum, and the SOP will start from April, 2024 onwards.
- Due: 2024-04
- Verdict: Kept
- Later filing says (2024-05-24): With the new order wins from Royal Enfield and TVS, we are now expanding to supply 5.5 million wheels per annum and the SOP has already started for April 24 for Royal Enfield
- Filing: <https://nsearchives.nseindia.com/corporate/ENDURANCE_13022024193909_Transcript.pdf>

## 2024-02-13 · European capacity capex investment: Kept

- Said: And we are investing EUR 50 million in this financial year to put in place the production capacity to cater to the new orders.
- Due: FY24
- Verdict: Kept
- Later filing says (2024-05-24): In FY24, we booked capex of €62 million of investment in order to install this production capacity.
- Filing: <https://nsearchives.nseindia.com/corporate/ENDURANCE_13022024193909_Transcript.pdf>

## 2024-02-13 · KTM air suspension forks supply: Pending

- Said: The new 35 dia air suspension inverted front forks for supply to KTM Austria will start by Q3 FY25
- Due: Q3 FY25
- Verdict: Pending
- Filing: <https://nsearchives.nseindia.com/corporate/ENDURANCE_13022024193909_Transcript.pdf>

Live record: https://eqdoc.com/stock/ENDURANCE. Not investment advice.