type: "Promise Ledger"
title: "Gallantt Ispat Ltd: what management promised, and what happened"
description: "29 statements by Gallantt Ispat Ltd's management, each checked against the company's later filings: 1 kept, 3 slipped, 23 pending, 2 unverifiable."
resource: "https://eqdoc.com/stock/GALLANTT"
tags: ["promise ledger","management guidance","india","gallantt"]
sources: [{"resource":"https://eqdoc.com/pdf/ann/7443151.pdf"},{"resource":"https://eqdoc.com/pdf/ann/7421164.pdf"},{"resource":"https://nsearchives.nseindia.com/corporate/GALLANTT_04082026125517_GIL_04082026.pdf"},{"resource":"https://eqdoc.com/pdf/ann/7094440.pdf"},{"resource":"https://nsearchives.nseindia.com/corporate/GALLANTT_27072026214632_GALLANTT_27072026.pdf"},{"resource":"https://nsearchives.nseindia.com/corporate/GALLANTT_12052026125051_GALLANTT_Transcript.pdf"},{"resource":"https://nsearchives.nseindia.com/corporate/GALLANTT_07052026012604_GIL_Presentation_FY26.pdf"}]
generated: {"by":"process:eqdoc-promise-audit","at":"2026-11-06"}
stale_after: "2027-02-14"
x-eqdoc-symbol: "GALLANTT"
x-eqdoc-counts: {"kept":1,"slipped":3,"missed":0,"pending":23,"unverifiable":2}
---

# How to read this

Each entry is something management said it would do, when it said it, and whether the company's later filings show it happened.
- **Kept**: a later filing shows it done. **Slipped**: done late or in part. **Missed**: the deadline passed without it.
- **Pending**: the deadline has not come, or no later filing yet speaks to it. **Unverifiable**: no filing could settle it.
- Evidence is either a sentence built from figures the company filed, or a quote from a later company document, as marked.

# Promises

## 2026-10-27 · Commission backward integration sponge iron plant in Gujarat in Q4.: Pending

- Said: Whereas we are also setting up a sponge iron plant to integrate it backwards, and that is expected to commission in Q4.
- By: Mayank Agrawal, Q2 FY27 earnings call
- Due: Q4
- Verdict: Pending
- Evidence: Not due yet, so it can't be checked.
- Filing: <https://eqdoc.com/pdf/ann/7443151.pdf> (page 12)

## 2026-10-27 · Operate enhanced Gorakhpur capacity in November 2026.: Pending

- Said: The enhanced Gorakhpur capacity is expected to be operational in November '26.
- By: Mayank Agarwal, Q2 FY27 earnings call
- Due: November '26
- Verdict: Pending
- Evidence: Not due until 30 Nov 2026, after the latest results; later ones will show.
- Filing: <https://eqdoc.com/pdf/ann/7443151.pdf> (page 5)

## 2026-10-27 · Present medium-term growth plan in Q4 FY27.: Pending

- Said: We therefore intend to present our growth plan in Quarter 4 '27.
- By: Dindayal Jalan, Q2 FY27 earnings call
- Due: Quarter 4 '27
- Verdict: Pending
- Evidence: Not due until 31 Mar 2027, after the latest results; later ones will show.
- Filing: <https://eqdoc.com/pdf/ann/7443151.pdf> (page 4)

## 2026-10-21 · Operationalize captive iron ore mines by FY30.: Pending

- Said: Iron ore mines (operational) FY30 In progress
- By: Company presentation, Investor presentation, 21 Oct 2026
- Due: FY30
- Verdict: Pending
- Evidence: Not due until 31 Mar 2030, after the latest results; later ones will show.
- Filing: <https://eqdoc.com/pdf/ann/7421164.pdf> (page 9)

## 2026-08-04 · Capacity expansion to 1.23 MT: Pending

- Said: Our capacity expansion from 1 million to 1.23 million tonnes, part of our INR 3,000 crores capex program continues to progress well and remains on course for commissioning in the second half of this financial year.
- Due: H2 FY27
- Verdict: Pending
- Filing: <https://nsearchives.nseindia.com/corporate/GALLANTT_04082026125517_GIL_04082026.pdf>

## 2026-07-28 · Commission 18 MW solar project in Gujarat in Q2 FY27 next month.: Slipped

- Said: 18 megawatt being installed in Gujarat would be commissioned in Q2 FY27 itself, very soon next month.
- By: Mayank Agrawal, Q1 FY27 earnings call
- Due: Q2 FY27
- Verdict: Slipped (a second reading found it kept)
- Evidence: The Q2 FY27 call, 27 Oct 2026 settles it: “Our 18-megawatt solar plant at Siddhpur in Gujarat is completed and set to resume operations by November 2026”
- Filing: <https://nsearchives.nseindia.com/corporate/GALLANTT_04082026125517_GIL_04082026.pdf> (page 9)

## 2026-07-28 · Finish debottlenecking work at Gujarat facility within the current financial year.: Pending

- Said: debottlenecking work at our Gujarat unit continues as planned and remains on track for completion within this financial year.
- By: Mayank Agrawal, Q1 FY27 earnings call
- Due: within this financial year
- Verdict: Pending
- Evidence: Not due until 31 Mar 2027, after the latest results; later ones will show.
- Filing: <https://nsearchives.nseindia.com/corporate/GALLANTT_04082026125517_GIL_04082026.pdf> (page 6)

## 2026-08-04 · Mine geological exploration completion: Pending

- Said: In UP, we are expecting them to be completed over the next two to three months and in Rajasthan maybe in six months.
- Due: FY27
- Verdict: Pending
- Filing: <https://nsearchives.nseindia.com/corporate/GALLANTT_04082026125517_GIL_04082026.pdf>

## 2026-08-04 · Operationalize captive iron ore blocks: Pending

- Said: work continues on our captive iron ore blocks in Rajasthan and Uttar Pradesh, with FY28 remaining our internal target for these to become operational.
- Due: FY28
- Verdict: Pending
- Filing: <https://nsearchives.nseindia.com/corporate/GALLANTT_04082026125517_GIL_04082026.pdf>

## 2026-08-04 · Renewable energy program commissioning: Pending

- Said: Our renewable energy program, 18 megawatt at Gujarat and 67megawatt at Gorakhpur remains on track for commissioning in Q2 and Q4 respectively of the current financial year
- Due: Q4 FY27
- Verdict: Pending
- Filing: <https://nsearchives.nseindia.com/corporate/GALLANTT_04082026125517_GIL_04082026.pdf>

## 2026-07-29 · Achieve an EBITDA improvement of approximately ₹2,000 per tonne via raw material backward integration.: Pending

- Said: Securing raw material linkage and achieving EBITDA improvement of ~₹2,000/tonne
- By: Company presentation, Investor presentation, 29 Jul 2026
- Verdict: Pending
- Evidence: Not due yet, so it can't be checked.
- Filing: <https://eqdoc.com/pdf/ann/7094440.pdf> (page 18)

## 2026-07-27 · Commission a 60 MW solar power plant at Prayagraj, UP by Q4 FY2027.: Unverifiable

- Said: Solar Power Plant 60 MW (Q4 FY2027) Prayagraj, UP
- By: Company presentation, Investor presentation, 29 Jul 2026
- Due: Q4 FY2027
- Verdict: Unverifiable (a second reading found it pending)
- Evidence: We could not match this promise to a figure, and no later call settles it.
- Filing: <https://eqdoc.com/pdf/ann/7094440.pdf> (page 10)

## 2026-07-27 · Commission an 18 MW solar power plant at Sidhpur, Gujarat in July 2026.: Unverifiable

- Said: Solar Power Plant 18 MW (Jul 2026) Sidhpur, Gujarat
- By: Company presentation, Investor presentation, 29 Jul 2026
- Due: Jul 2026
- Verdict: Unverifiable (a second reading found it kept)
- Evidence: We could not match this promise to a figure, and no later call settles it.
- Filing: <https://eqdoc.com/pdf/ann/7094440.pdf> (page 10)

## 2026-07-29 · Deploy a ₹3,000 crore capex program over the next 2-3 years for backward integration and phased capacity expansion.: Pending

- Said: Capex program of ₹3000 Cr being deployed, with significant allocation toward backward integration of key raw materials. The remaining investment is directed towards phased capacity expansion over the next 2-3 years.
- By: Company presentation, Investor presentation, 29 Jul 2026
- Due: next 2-3 years
- Verdict: Pending
- Evidence: Not due until 28 Jul 2029, after the latest results; later ones will show.
- Filing: <https://eqdoc.com/pdf/ann/7094440.pdf> (page 18)

## 2026-07-27 · Deploy ₹300 crore capex for a 78 MW solar plant project.: Pending

- Said: Capex deployment of ₹300 Cr for 78MW solar plant
- By: Company presentation, Investor presentation, 29 Jul 2026
- Verdict: Pending
- Evidence: Not due yet, so it can't be checked.
- Filing: <https://eqdoc.com/pdf/ann/7094440.pdf> (page 18)

## 2026-07-29 · Invest ₹1,200 crore capex in steelmaking to address infrastructure demand.: Pending

- Said: Meeting infrastructure-led demand through ₹1,200 Cr capex in steelmaking
- By: Company presentation, Investor presentation, 29 Jul 2026
- Verdict: Pending
- Evidence: Not due yet, so it can't be checked.
- Filing: <https://eqdoc.com/pdf/ann/7094440.pdf> (page 18)

## 2026-07-27 · Spend ₹1,500 crore capex across Sonbhadra and Todpura mines.: Pending

- Said: Capex of ₹1,500 Cr capex in Sonbhadra (UP) mines and Todpura (Rajasthan) mines
- By: Company presentation, Investor presentation, 29 Jul 2026
- Verdict: Pending
- Evidence: Not due yet, so it can't be checked.
- Filing: <https://eqdoc.com/pdf/ann/7094440.pdf> (page 18)

## 2026-07-27 · Phased steel capacity expansion: Pending

- Said: Phased expansion to total installed capacity of ~12.3 lakh MT across Gorakhpur & Kutch units
- Due: FY29
- Verdict: Pending
- Filing: <https://nsearchives.nseindia.com/corporate/GALLANTT_27072026214632_GALLANTT_27072026.pdf>

## 2026-05-06 · Commission 18 MW solar plant at Gujarat in Q2 FY27.: Slipped

- Said: investing about INR 225 crores in solar capacity, comprising 18 megawatts at Gujarat, which is scheduled to be commissioned in Q2 FY27, and 60 megawatts at Gorakhpur, Uttar Pradesh,
- By: Mayank Agrawal, Q4 FY26 earnings call
- Due: Q2 FY27
- Verdict: Slipped (a second reading found it unverifiable)
- Evidence: The Q2 FY27 call, 27 Oct 2026 settles it: “Our 18-megawatt solar plant at Siddhpur in Gujarat is completed and set to resume operations by November 2026”
- Filing: <https://nsearchives.nseindia.com/corporate/GALLANTT_12052026125051_GALLANTT_Transcript.pdf> (page 5)

## 2026-05-06 · Commission 60 MW solar plant at Gorakhpur in Q4 FY27.: Pending

- Said: 60 megawatts at Gorakhpur, Uttar Pradesh, expected to commission in Q4 27.
- By: Mayank Agrawal, Q4 FY26 earnings call
- Due: Q4 27
- Verdict: Pending
- Evidence: Not due until 31 Mar 2027, after the latest results; later ones will show.
- Filing: <https://nsearchives.nseindia.com/corporate/GALLANTT_12052026125051_GALLANTT_Transcript.pdf> (page 5)

## 2026-05-06 · Complete captive mine development project by FY28.: Pending

- Said: And the third part is the mines with a capex of somewhere around INR 1,500 crore. That is likely to be completed by FY28.
- By: Dindayal Jalan, Q4 FY26 earnings call
- Due: by FY28
- Verdict: Pending
- Evidence: Not due until 31 Mar 2028, after the latest results; later ones will show.
- Filing: <https://nsearchives.nseindia.com/corporate/GALLANTT_12052026125051_GALLANTT_Transcript.pdf> (page 8)

## 2026-05-06 · Present medium-term growth plan alongside capex program in Q2 FY27.: Slipped

- Said: In addition, we are evaluating a medium-term growth plan alongside the ongoing INR 3,000 crores capex program and intend to present this opportunity in Q2 FY27.
- By: Mayank Agrawal, Q4 FY26 earnings call
- Due: Q2 FY27
- Verdict: Slipped (a second reading found it unverifiable)
- Evidence: The Q2 FY27 call, 27 Oct 2026 settles it: “We therefore intend to present our growth plan in Quarter 4 '27.”
- Filing: <https://nsearchives.nseindia.com/corporate/GALLANTT_12052026125051_GALLANTT_Transcript.pdf> (page 4)

## 2026-05-06 · Steel capacity expansion to commence production in H2 of FY27.: Pending

- Said: One part is the capacity expansion of steel, which is somewhere around INR 1,200 crore, which is underway, and this should commence production sometime in H2 of this financial year.
- By: Dindayal Jalan, Q4 FY26 earnings call
- Due: H2 of this financial year
- Verdict: Pending
- Evidence: Not due until 31 Mar 2027, after the latest results; later ones will show.
- Filing: <https://nsearchives.nseindia.com/corporate/GALLANTT_12052026125051_GALLANTT_Transcript.pdf> (page 8)

## 2026-05-07 · Mines development capex: Pending

- Said: Capex of ₹1,500 Cr capex in Sonbhadra (UP) mines and Todpura (Rajasthan) mines
- Verdict: Pending
- Filing: <https://nsearchives.nseindia.com/corporate/GALLANTT_07052026012604_GIL_Presentation_FY26.pdf>

## 2026-05-07 · Prayagraj solar plant commissioning: Pending

- Said: Solar Power Plant 60 MW (Oct 2026) Prayagraj, UP
- Due: 2026-10
- Verdict: Pending
- Filing: <https://nsearchives.nseindia.com/corporate/GALLANTT_07052026012604_GIL_Presentation_FY26.pdf>

## 2026-05-07 · Sidhpur solar plant commissioning: Kept

- Said: Solar Power Plant 18 MW (Jul 2026) Sidhpur, Gujarat
- Due: 2026-07
- Verdict: Kept
- Later filing says (2026-10-21): Capacity Added 18 MW Solar Commissioned Jul 2026
- Filing: <https://nsearchives.nseindia.com/corporate/GALLANTT_07052026012604_GIL_Presentation_FY26.pdf>

## 2026-05-07 · Solar plant capex deployment: Pending

- Said: Capex deployment of ₹300 Cr for 78MW solar plant
- Verdict: Pending
- Filing: <https://nsearchives.nseindia.com/corporate/GALLANTT_07052026012604_GIL_Presentation_FY26.pdf>

## 2026-05-07 · Steel capacity expansion: Pending

- Said: Phased expansion to total installed capacity of ~12.3 lakh MT across Gorakhpur & Kutch units
- Due: FY27
- Verdict: Pending
- Filing: <https://nsearchives.nseindia.com/corporate/GALLANTT_07052026012604_GIL_Presentation_FY26.pdf>

## 2026-05-07 · Steelmaking capex spend: Pending

- Said: Meeting infrastructure-led demand through ₹1,200 Cr capex in steelmaking
- Verdict: Pending
- Filing: <https://nsearchives.nseindia.com/corporate/GALLANTT_07052026012604_GIL_Presentation_FY26.pdf>