type: "Promise Ledger"
title: "Gateway Distriparks Ltd: what management promised, and what happened"
description: "18 statements by Gateway Distriparks Ltd's management, each checked against the company's later filings: 3 slipped, 9 pending, 6 unverifiable."
resource: "https://eqdoc.com/stock/GATEWAY"
tags: ["promise ledger","management guidance","india","gateway"]
sources: [{"resource":"https://eqdoc.com/pdf/ann/7446760.pdf"},{"resource":"https://eqdoc.com/pdf/ann/7120603.pdf"},{"resource":"https://nsearchives.nseindia.com/corporate/GATEWAY_05082026145452_Investors_Presentation.pdf"}]
generated: {"by":"process:eqdoc-promise-audit"}
x-eqdoc-symbol: "GATEWAY"
x-eqdoc-counts: {"kept":0,"slipped":3,"missed":0,"pending":9,"unverifiable":6}
---

# How to read this

Each entry is something management said it would do, when it said it, and whether the company's later filings show it happened.
- **Kept**: a later filing shows it done. **Slipped**: done late or in part. **Missed**: the deadline passed without it.
- **Pending**: the deadline has not come, or no later filing yet speaks to it. **Unverifiable**: no filing could settle it.
- Evidence is either a sentence built from figures the company filed, or a quote from a later company document, as marked.

# Promises

## 2026-10-28 · Delivery of 2 additional rakes to expand fleet to 37 expected in Q3.: Pending

- Said: 35 RAKES — 2 MORE PURCHASED, DELIVERY IN Q3
- By: Company presentation, Investor presentation, 28 Oct 2026
- Due: Q3
- Verdict: Pending
- Evidence: Not due yet, so it can't be checked.
- Filing: <https://eqdoc.com/pdf/ann/7446760.pdf> (page 4)

## 2026-10-28 · EXIM operations at Ankleshwar MMLP scheduled to begin in Q3 FY27.: Pending

- Said: EXIM operations to begin in Q3. A new hub for JNPT-bound mixed trains.
- By: Company presentation, Investor presentation, 28 Oct 2026
- Due: Q3 FY27
- Verdict: Pending
- Evidence: Not due until 31 Dec 2026, after the latest results; later ones will show.
- Filing: <https://eqdoc.com/pdf/ann/7446760.pdf> (page 10)

## 2026-10-28 · Jaipur ICD to become operational 12 to 18 months after legal matter is resolved.: Unverifiable

- Said: Jaipur ICD To be operational 12–18 months after legal matter is resolved.
- By: Company presentation, Investor presentation, 28 Oct 2026
- Due: 12–18 months after legal matter is resolved
- Verdict: Unverifiable
- Evidence: We could not match this promise to a figure, and no later call settles it.
- Filing: <https://eqdoc.com/pdf/ann/7446760.pdf> (page 10)

## 2026-10-28 · Operations at Indore site scheduled to commence by Q4 FY2028.: Unverifiable

- Said: Construction ongoing and operations will commence in by Q4FY2028
- By: Company presentation, Investor presentation, 28 Oct 2026
- Due: Q4FY2028
- Verdict: Unverifiable
- Evidence: We could not match this promise to a figure, and no later call settles it.
- Filing: <https://eqdoc.com/pdf/ann/7446760.pdf> (page 17)

## 2026-10-28 · Snowman to add 24,000 pallets across Hyderabad, Pune, and Patna by mid-2027.: Pending

- Said: Snowman +24k pallets Hyderabad, Pune & Patna. Further additions planned annually.
- By: Company presentation, Investor presentation, 28 Oct 2026
- Due: Mid 2027
- Verdict: Pending
- Evidence: Not due until 31 Dec 2027, after the latest results; later ones will show.
- Filing: <https://eqdoc.com/pdf/ann/7446760.pdf> (page 10)

## 2026-10-28 · Ten LNG trailers expected to join the fleet in Q3 FY2027.: Unverifiable

- Said: 10 LNG trailers expected in Q3 FY2027.
- By: Company presentation, Investor presentation, 28 Oct 2026
- Due: Q3 FY2027
- Verdict: Unverifiable
- Evidence: We could not match this promise to a figure, and no later call settles it.
- Filing: <https://eqdoc.com/pdf/ann/7446760.pdf> (page 11)

## 2026-08-05 · Delivery of 2 newly purchased rakes expected in Q2 FY27.: Slipped

- Said: RAKES — 2 MORE PURCHASED, DELIVERY IN Q2
- By: Company presentation, Investor presentation, 5 Aug 2026
- Due: Q2
- Verdict: Slipped
- Evidence: The Investor presentation, 28 Oct 2026 settles it: “35 RAKES — 2 MORE PURCHASED, DELIVERY IN Q3”
- Filing: <https://eqdoc.com/pdf/ann/7120603.pdf> (page 4)

## 2026-08-05 · EXIM operations at MMLP Ankleshwar to commence from September 2026.: Slipped

- Said: MMLP Ankleshwar received Customs permission to handle EXIM volumes, operations to commence from September 2026.
- By: Company presentation, Investor presentation, 5 Aug 2026
- Due: September 2026
- Verdict: Slipped
- Evidence: The Investor presentation, 28 Oct 2026 settles it: “EXIM operations to begin in Q3. A new hub for JNPT-bound mixed trains.”
- Filing: <https://eqdoc.com/pdf/ann/7120603.pdf> (page 14)

## 2026-08-05 · Operations at the Indore ICD facility will commence in 2028.: Pending

- Said: Construction ongoing and operations will commence in 2028.
- By: Company presentation, Investor presentation, 5 Aug 2026
- Due: 2028
- Verdict: Pending
- Evidence: Not due until 31 Dec 2028, after the latest results; later ones will show.
- Filing: <https://nsearchives.nseindia.com/corporate/GATEWAY_05082026145452_Investors_Presentation.pdf> (page 14)

## 2026-02-06 · The company expects to reach a total of 37 rakes by May or June.: Unverifiable

- Said: So by the end of May, June, we would be at 37 rakes.
- By: Samvid Gupta, Q3 FY26 earnings call
- Verdict: Unverifiable
- Evidence: We could not match this promise to a figure, and no later call settles it.

## 2025-02-03 · Snowman Logistics targets revenue between Rs. 800 crores and Rs. 900 crores by the end of FY27.: Pending

- Said: We are targeting say by end of FY27, anywhere between Rs. 800 crores to Rs. 900 crores of revenue.
- By: Ishaan Gupta, Q3 FY25 earnings call
- Due: by the end of FY27
- Verdict: Pending
- Evidence: Not due until 31 Mar 2027, after the latest results; later ones will show.

## 2025-02-03 · The company plans to spend Rs. 250 crores to Rs. 300 crores for the development of two new terminals.: Pending

- Said: So, the two new terminals that we are talking about, it's the same figures we are saying, maybe about Rs. 250 crores to Rs. 300 crores, the total when these are developed.
- By: Samvid Gupta, Q3 FY25 earnings call
- Verdict: Pending
- Evidence: Not due yet, so it can't be checked.

## 2024-11-11 · The company targets an EBITDA per TEU of INR10,500 to INR11,000 once the DFC is fully operational.: Pending

- Said: So given that full DFC is under – till it's all the way there till Bombay, INR10,500 to INR11,000 EBITDA per TEU is something we can look at.
- By: Samvid Gupta, Q2 FY25 earnings call
- Verdict: Pending
- Evidence: Not due yet, so it can't be checked.

## 2024-11-11 · The company will make its Kolkata and Krishnapatnam facilities functional by Jan end.: Unverifiable

- Said: we will have our Kolkata facility also functional. And by Jan end, we'll have our Krishnapatnam facility function.
- By: Sunil Nair, Q2 FY25 earnings call
- Verdict: Unverifiable
- Evidence: We could not match this promise to a figure, and no later call settles it.

## 2024-08-09 · The Jaipur facility is expected to be operational in 12 months.: Slipped

- Said: According to our present estimates, we will be operational in about 12-months from now.
- By: management, Q1 FY25 earnings call
- Verdict: Slipped
- Evidence: The Q3 FY26 call, 6 Feb 2026 settles it: “So it should be operational within 2 years, and we're looking at about 120,000 TEUs per year capacity at the terminal.”

## 2024-08-09 · The company aims to increase its stake in Snowman Logistics to over 50% within the financial year.: Pending

- Said: if we complete the full 5% acquisition in this financial year, so we should be ending up little over 50%
- By: management, Q1 FY25 earnings call
- Verdict: Pending
- Evidence: Not due yet, so it can't be checked.

## 2024-08-09 · The company expects 12% to 15% growth in the warehousing business for the year.: Unverifiable

- Said: considering all these, we expect around 12% to 15% growth in warehousing business this year.
- By: Sunil Nair, Q1 FY25 earnings call
- Verdict: Unverifiable
- Evidence: We could not match this promise to a figure, and no later call settles it.

## 2024-08-09 · The company targets a volume of at least 3,000 TEUs per month for the Jaipur facility in the medium term.: Pending

- Said: in the medium term for three years, we are looking at at least doing 3,000 TEUs from that per month.
- By: Samvid Gupta, Q1 FY25 earnings call
- Verdict: Pending
- Evidence: Not due yet, so it can't be checked.

Live record: https://eqdoc.com/stock/GATEWAY. Not investment advice.