type: "Promise Ledger"
title: "Great Eastern Shipping Company Ltd: what management promised, and what happened"
description: "19 statements by Great Eastern Shipping Company Ltd's management, each checked against the company's later filings: 3 kept, 1 slipped, 11 pending, 4 unverifiable."
resource: "https://eqdoc.com/stock/GESHIP"
tags: ["promise ledger","management guidance","india","geship"]
sources: [{"resource":"https://nsearchives.nseindia.com/corporate/GESHIP_04022026142500_earningscalltranscript.pdf"},{"resource":"https://nsearchives.nseindia.com/corporate/GESHIP_14112025162016_earningscalltranscript.pdf"},{"resource":"https://nsearchives.nseindia.com/corporate/GESHIP_05022024163959_earningscalltranscript.pdf"}]
generated: {"by":"process:eqdoc-promise-audit","at":"2026-10-09"}
stale_after: "2027-01-17"
x-eqdoc-symbol: "GESHIP"
x-eqdoc-counts: {"kept":3,"slipped":1,"missed":0,"pending":11,"unverifiable":4}
---

# How to read this

Each entry is something management said it would do, when it said it, and whether the company's later filings show it happened.
- **Kept**: a later filing shows it done. **Slipped**: done late or in part. **Missed**: the deadline passed without it.
- **Pending**: the deadline has not come, or no later filing yet speaks to it. **Unverifiable**: no filing could settle it.
- Evidence is either a sentence built from figures the company filed, or a quote from a later company document, as marked.

# Promises

## 2026-08-04 · The company expects to reprice three rigs during the 2027 fiscal year.: Pending

- Said: 3 Rigs to be repriced in FY27
- By: Company presentation, Investor presentation, 4 Aug 2026
- Due: during the 2027 fiscal year
- Verdict: Pending
- Evidence: Not due until 31 Mar 2027, after the latest results; later ones will show.

## 2026-08-04 · The company has remaining debt of USD 119 million that is scheduled to mature by November 2028.: Pending

- Said: remaining USD 119 mn debt matures by Nov’28
- By: Company presentation, Investor presentation, 4 Aug 2026
- Due: by November 2028
- Verdict: Pending
- Evidence: Not due until 31 Dec 2028, after the latest results; later ones will show.

## 2026-08-04 · The company has secured offshore revenue coverage for 92% of vessels and 75% of rigs for 2Q27.: Pending

- Said: 2Q27 Offshore days covered: About 92% for Vessels and 75% for Rigs; 3 Rigs to be repriced in FY27
- By: Company presentation, Investor presentation, 4 Aug 2026
- Verdict: Pending
- Evidence: Not due until 31 Mar 2027, after the latest results; later ones will show.

## 2026-08-04 · The company has secured revenue coverage for 46% of Crude Tankers, 61% for Products, 100% for LPG, and 57% for Dry Bulk: Pending

- Said: 2Q27 days covered: About 46% for Crude Tankers 61% for Products; 100% for LPG & 57% for Dry Bulk
- By: Company presentation, Investor presentation, 4 Aug 2026
- Verdict: Pending
- Evidence: Not due yet, so it can't be checked.

## 2026-05-15 · The company expects to be debt-free within two years.: Pending

- Said: As of March 31, we had $157 million of debt in the Group, and that will be out within the next 2 years or so.
- By: G. Shivakumar, Q4 FY26 earnings call
- Verdict: Pending
- Evidence: Not due until 15 May 2028, after the latest results; later ones will show.

## 2026-01-30 · The company expects its dividend distribution to be approximately 25% for the current year.: Unverifiable

- Said: We are now little about 20%, probably closer to 25% for this year.
- By: G. Shivakumar, Q3 FY26 earnings call
- Verdict: Unverifiable
- Evidence: We could not match this promise to a figure, and no later call settles it.
- Filing: <https://nsearchives.nseindia.com/corporate/GESHIP_04022026142500_earningscalltranscript.pdf> (page 11)

## 2026-01-30 · The company has secured 80% coverage for its offshore vessel fleet for the 2027 fiscal year.: Pending

- Said: in FY '27, we are largely fixed out at these rates, at about 80% is our coverage.
- By: Rahul Sheth, Q3 FY26 earnings call
- Due: for the 2027 fiscal year
- Verdict: Pending
- Evidence: Not due until 31 Mar 2027, after the latest results; later ones will show.
- Filing: <https://nsearchives.nseindia.com/corporate/GESHIP_04022026142500_earningscalltranscript.pdf> (page 21)

## 2025-11-14 · Delivery of Jag Lok and Jag Pooja tankers: Kept

- Said: one is a crew carrier Jag Lok and the other is the product tanker Jag Pooja, both of which will be delivered in this quarter.
- Due: Q3 FY26
- Verdict: Kept
- Later filing says (2026-01-29): Vessels removed from the fleet in 3Q26 (Sales) Sr. No. Vessel Name Type DWT Built 1 Jag Pooja Medium Range (Product Tanker) 48,539 2005 2 Jag Lok Suezmax (Crude Tanker) 1,58,280 2005
- Filing: <https://nsearchives.nseindia.com/corporate/GESHIP_14112025162016_earningscalltranscript.pdf>

## 2025-11-14 · Delivery of Ultramax bulk carrier: Kept

- Said: We have also purchased our first Ultramax bulk carrier which will be delivered by Q4 FY26.
- Due: Q4 FY26
- Verdict: Kept
- Later filing says (2026-05-15): Vessels added to the fleet in 4Q26 (Purchases) Sr. No. Vessel Name Type DWT Built 1 Jag Vijay Very Large Gas Carrier 54,564 2015 2 Jag Riddhi Ultramax (Dry Bulk Carrier) 63,480 2019
- Filing: <https://nsearchives.nseindia.com/corporate/GESHIP_14112025162016_earningscalltranscript.pdf>

## 2025-11-14 · Mobilization of fourth rig on short-term contract: Pending

- Said: It is just being mobilized for a short-term contract off the coast of India, that should hopefully go on higher by end of November. That is a seven-month contract.
- Due: 2025-11-30
- Verdict: Pending
- Filing: <https://nsearchives.nseindia.com/corporate/GESHIP_14112025162016_earningscalltranscript.pdf>

## 2025-11-14 · Upload earnings call audio and transcript: Pending

- Said: The transcript and the audio will be put up on our website shortly.
- Verdict: Pending
- Filing: <https://nsearchives.nseindia.com/corporate/GESHIP_14112025162016_earningscalltranscript.pdf>

## 2025-11-10 · The company will reach a fleet size of 40 vessels following the delivery of its first Ultramax bulk carrier.: Unverifiable

- Said: We have also purchased our first Ultramax bulk carrier which will be delivered by Q4 FY26. So, with these, the commitments, we will be at 40 vessels.
- By: G Shivakumar, Q2 FY26 earnings call
- Verdict: Unverifiable
- Evidence: We could not match this promise to a figure, and no later call settles it.
- Filing: <https://nsearchives.nseindia.com/corporate/GESHIP_14112025162016_earningscalltranscript.pdf> (page 4)

## 2025-05-12 · 80% of the company's vessel capacity for fiscal year 2026 is locked in at profitable rates.: Pending

- Said: So otherwise, 80% of our vessel capacity for FY ‘26 has already been locked in at profitable rates.
- By: G. Shivakumar, Q4 FY25 earnings call
- Due: for fiscal year 2026
- Verdict: Pending
- Evidence: Not due until 31 Dec 2026, after the latest results; later ones will show.

## 2025-05-12 · The company targets a minimum 10% internal rate of return on ship acquisitions in U.S. dollar terms.: Pending

- Said: We would like to make at least a 10% IRR on the ships that we buy in U.S dollar terms.
- By: G. Shivakumar, Q4 FY25 earnings call
- Verdict: Pending
- Evidence: Not due yet, so it can't be checked.

## 2024-11-11 · The company does not expect the second half of the year to perform as well as the first quarter for the offshore busines: Unverifiable

- Said: As it stands, it is somewhat unlikely. Just let me tell you why. In the first quarter, so the first quarter was a very good quarter for the offshore business.
- By: G. Shivakumar, Q2 FY25 earnings call
- Verdict: Unverifiable
- Evidence: We could not match this promise to a figure, and no later call settles it.

## 2024-08-01 · Five vessels are scheduled for repricing within the next three months.: Unverifiable

- Said: we have 5 vessels coming up for repricing in the next 3 months itself.
- By: management, Q1 FY25 earnings call
- Verdict: Unverifiable
- Evidence: We could not match this promise to a figure, and no later call settles it.

## 2024-02-05 · Q4 FY24 dry docking schedule: Pending

- Said: I think we have two or three vessels being dry docked and some of these can spill one month here and there. So, two to three ships being dry docked in this quarter.
- Due: Q4 FY24
- Verdict: Pending
- Filing: <https://nsearchives.nseindia.com/corporate/GESHIP_05022024163959_earningscalltranscript.pdf>

## 2024-02-05 · Rigs repricing timeline: Slipped

- Said: two rigs which are due for repricing in FY25 will get repriced very late in FY25.
- Due: FY25
- Verdict: Slipped
- Later filing says (2025-08-06): Two of our rigs, that is the Chetna and the Chaaya, have got short-term contracts, a four-month contract and a seven-month contract, both of which will start after the monsoon
- Filing: <https://nsearchives.nseindia.com/corporate/GESHIP_05022024163959_earningscalltranscript.pdf>

## 2024-02-05 · VLGCs repricing timeline: Kept

- Said: The other two will be repriced somewhere between March and June of this year.
- Due: 2024-06-30
- Verdict: Kept
- Later filing says (2024-11-13): A lot of it was made up by LPG, where all our four vessels were repriced during the last year or so, and have got repriced at significantly higher rates than their previous contracts.
- Filing: <https://nsearchives.nseindia.com/corporate/GESHIP_05022024163959_earningscalltranscript.pdf>

Live record: https://eqdoc.com/stock/GESHIP. Not investment advice.