type: "Promise Ledger"
title: "Gujarat Industries Power Company Ltd: what management promised, and what happened"
description: "10 statements by Gujarat Industries Power Company Ltd's management, each checked against the company's later filings: 9 pending, 1 unverifiable."
resource: "https://eqdoc.com/stock/GIPCL"
tags: ["promise ledger","management guidance","india","gipcl"]
sources: [{"resource":"https://nsearchives.nseindia.com/corporate/Gipcl7868_15072026111913_GIPCL_SE_Transcript_Con_Call_15072026_signed.pdf"}]
generated: {"by":"process:eqdoc-promise-audit"}
x-eqdoc-symbol: "GIPCL"
x-eqdoc-counts: {"kept":0,"slipped":0,"missed":0,"pending":9,"unverifiable":1}
---

# How to read this

Each entry is something management said it would do, when it said it, and whether the company's later filings show it happened.
- **Kept**: a later filing shows it done. **Slipped**: done late or in part. **Missed**: the deadline passed without it.
- **Pending**: the deadline has not come, or no later filing yet speaks to it. **Unverifiable**: no filing could settle it.
- Evidence is either a sentence built from figures the company filed, or a quote from a later company document, as marked.

# Promises

## 2026-07-10 · Achieve EBITDA of INR 350 to INR 360 crores from the 600 MW Khavda plant.: Pending

- Said: INR350 to INR360 crores you can roughly assume.
- By: K.K. Bhatt, Q1 FY27 earnings call
- Verdict: Pending
- Evidence: Not due yet, so it can't be checked.
- Filing: <https://nsearchives.nseindia.com/corporate/Gipcl7868_15072026111913_GIPCL_SE_Transcript_Con_Call_15072026_signed.pdf> (page 6)

## 2026-07-10 · Commission the 750 MW thermal lignite expansion across three 250 MW units by 2031 to 2033.: Pending

- Said: 3 into 250 capacity will be commissioned by 31, 32 and '33. That is the right now target.
- By: management, Q1 FY27 earnings call
- Due: by 31, 32 and '33
- Verdict: Pending
- Evidence: Not due until 31 Dec 2031, after the latest results; later ones will show.
- Filing: <https://nsearchives.nseindia.com/corporate/Gipcl7868_15072026111913_GIPCL_SE_Transcript_Con_Call_15072026_signed.pdf> (page 8)

## 2026-07-10 · Commission the remaining 500 MW solar capacity in phases starting with 200 MW post-monsoon.: Pending

- Said: I think post-monsoon they will be ready, so we may be able to commission the first phase of 200 megawatt and followed by another 200, 100 megawatts in next couple
- By: K.K. Bhatt, Q1 FY27 earnings call
- Due: next couple of months
- Verdict: Pending
- Evidence: Not due yet, so it can't be checked.
- Filing: <https://nsearchives.nseindia.com/corporate/Gipcl7868_15072026111913_GIPCL_SE_Transcript_Con_Call_15072026_signed.pdf> (page 6)

## 2026-07-10 · Expect FY27 interest costs around INR 250 to 260 crores and depreciation around INR 425 to 450 crores.: Pending

- Said: roughly interest would be around 250 to 260 crores and depreciation would be around 425 to 450 crores.
- By: management, Q1 FY27 earnings call
- Due: '26, '27
- Verdict: Pending
- Evidence: Not due until 31 Mar 2027, after the latest results; later ones will show.
- Filing: <https://nsearchives.nseindia.com/corporate/Gipcl7868_15072026111913_GIPCL_SE_Transcript_Con_Call_15072026_signed.pdf> (page 30)

## 2026-07-10 · Generate peak O&M revenue of INR 55 to 60 crores from solar park developers.: Pending

- Said: Revenue would be around INR55 crores to INR60 crores.
- By: K.K. Bhatt, Q1 FY27 earnings call
- Due: at the peak
- Verdict: Pending
- Evidence: Not due yet, so it can't be checked.
- Filing: <https://nsearchives.nseindia.com/corporate/Gipcl7868_15072026111913_GIPCL_SE_Transcript_Con_Call_15072026_signed.pdf> (page 13)

## 2026-07-10 · Generate roughly INR 420 crores of revenue from the 600 MW Khavda plant.: Unverifiable

- Said: It would be around Rs. 420 crores - for 600 MW Khavda only
- By: management, Q1 FY27 earnings call
- Due: FY26-'27
- Verdict: Unverifiable
- Evidence: We could not match this promise to a figure, and no later call settles it.
- Filing: <https://nsearchives.nseindia.com/corporate/Gipcl7868_15072026111913_GIPCL_SE_Transcript_Con_Call_15072026_signed.pdf> (page 4)

## 2026-07-10 · Incur capital expenditure of INR 250 to 300 crores for the Baroda BESS project.: Pending

- Said: Capex would be around INR250 crores to INR300 crores.
- By: K.K. Bhatt, Q1 FY27 earnings call
- Verdict: Pending
- Evidence: Not due yet, so it can't be checked.
- Filing: <https://nsearchives.nseindia.com/corporate/Gipcl7868_15072026111913_GIPCL_SE_Transcript_Con_Call_15072026_signed.pdf> (page 20)

## 2026-07-10 · Incur thermal capex of INR 6,000 to INR 7,000 crores for the 750 MW capacity expansion.: Pending

- Said: Around INR6,500 crores to INR7,000 crores would be required for thermal capex capacity of 750, it would be around -- yes, we are expecting INR6,000 crores capex
- By: management, Q1 FY27 earnings call
- Due: starting from 2027 till 2032, '33
- Verdict: Pending
- Evidence: Not due until 31 Dec 2027, after the latest results; later ones will show.
- Filing: <https://nsearchives.nseindia.com/corporate/Gipcl7868_15072026111913_GIPCL_SE_Transcript_Con_Call_15072026_signed.pdf> (page 15)

## 2026-07-10 · Maintain long-term debt at approximately INR 4,500 crores post-commissioning of the 500 MW solar plant.: Pending

- Said: It would be around INR4500 crores roughly you can say would be the debt portion after commissioning of the 500 megawatts.
- By: K.K. Bhatt, Q1 FY27 earnings call
- Due: after commissioning of the 500 megawatts
- Verdict: Pending
- Evidence: Not due yet, so it can't be checked.
- Filing: <https://nsearchives.nseindia.com/corporate/Gipcl7868_15072026111913_GIPCL_SE_Transcript_Con_Call_15072026_signed.pdf> (page 7)

## 2026-07-10 · Reach full-year company EBITDA of INR 950 to INR 1,000 crores once all stations are fully operational.: Pending

- Said: Once, all the stations are commissioned and full year of operation, this EBITDA margin of INR950 crores to INR1,000 crores will be there, as you rightly mentioned.
- By: K.K. Bhatt, Q1 FY27 earnings call
- Due: full operational year / next year
- Verdict: Pending
- Evidence: Not due yet, so it can't be checked.
- Filing: <https://nsearchives.nseindia.com/corporate/Gipcl7868_15072026111913_GIPCL_SE_Transcript_Con_Call_15072026_signed.pdf> (page 9)

Live record: https://eqdoc.com/stock/GIPCL. Not investment advice.