type: "Promise Ledger"
title: "Grasim Industries Ltd: what management promised, and what happened"
description: "8 statements by Grasim Industries Ltd's management, each checked against the company's later filings: 1 slipped, 3 pending, 4 unverifiable."
resource: "https://eqdoc.com/stock/GRASIM"
tags: ["promise ledger","management guidance","india","grasim"]
sources: [{"resource":"https://nsearchives.nseindia.com/corporate/GRASIM_13022026172025_SEIntimationTranscriptFinalsigned.pdf"},{"resource":"https://nsearchives.nseindia.com/corporate/GRASIM_11112025131039_SEIntimationTranscript.pdf"},{"resource":"https://nsearchives.nseindia.com/corporate/GRASIM_14082025155011_SEIntimationTranscript.pdf"}]
generated: {"by":"process:eqdoc-promise-audit"}
x-eqdoc-symbol: "GRASIM"
x-eqdoc-counts: {"kept":0,"slipped":1,"missed":0,"pending":3,"unverifiable":4}
---

# How to read this

Each entry is something management said it would do, when it said it, and whether the company's later filings show it happened.
- **Kept**: a later filing shows it done. **Slipped**: done late or in part. **Missed**: the deadline passed without it.
- **Pending**: the deadline has not come, or no later filing yet speaks to it. **Unverifiable**: no filing could settle it.
- Evidence is either a sentence built from figures the company filed, or a quote from a later company document, as marked.

# Promises

## 2026-02-11 · The company expects to reach Rs.10,000 crores in revenue in the third full year of paint operations.: Unverifiable

- Said: we continue to guide that we will deliver the Rs.10,000 crores in third full year operation.
- By: Himanshu Kapania, Q3 FY26 earnings call
- Verdict: Unverifiable
- Evidence: We could not match this promise to a figure, and no later call settles it.
- Filing: <https://nsearchives.nseindia.com/corporate/GRASIM_13022026172025_SEIntimationTranscriptFinalsigned.pdf> (page 11)

## 2025-11-05 · The company expects chlorine integration to reach 70% after the completion of ongoing projects.: Pending

- Said: The mechanical completion is expected by Q3 FY '26. Post completion of ongoing projects, chlorine integration is expected to reach 70% compared to current 64%.
- By: Hemant Kadel, Q2 FY26 earnings call
- Verdict: Pending
- Evidence: Not due yet, so it can't be checked.
- Filing: <https://nsearchives.nseindia.com/corporate/GRASIM_11112025131039_SEIntimationTranscript.pdf> (page 8)

## 2025-11-05 · The company expects its PaintCraft service to reach over 300 towns by the third quarter (FY26).: Unverifiable

- Said: We're happy to announce that PaintCraft has already scaled up across 170 towns and expected to reach 300+ towns by quarter 3
- By: Himanshu Kapania, Q2 FY26 earnings call
- Due: FY26
- Verdict: Unverifiable
- Evidence: We could not match this promise to a figure, and no later call settles it.
- Filing: <https://nsearchives.nseindia.com/corporate/GRASIM_11112025131039_SEIntimationTranscript.pdf> (page 5)

## 2025-11-05 · The company targets a total gray cement capacity of over 240 million metric tons per annum by March 2028.: Pending

- Said: The business has recently announced capacity expansion targeting total gray cement capacity of over 240 million metric ton per annum by March 2028.
- By: Hemant Kadel, Q2 FY26 earnings call
- Due: by March 2028
- Verdict: Pending
- Evidence: Not due until 31 Dec 2028, after the latest results; later ones will show.
- Filing: <https://nsearchives.nseindia.com/corporate/GRASIM_11112025131039_SEIntimationTranscript.pdf> (page 8)

## 2025-08-08 · Birla Pivot aims to achieve a revenue run rate of ₹8,500 crore by FY'27.: Pending

- Said: The business annualized the revenue run rate continues to rise and remains on track to achieve ₹8,500 crore that is the billion-dollar ambition by FY'27.
- By: management, Q1 FY26 earnings call
- Due: by FY'27
- Verdict: Pending
- Evidence: Not due until 31 Mar 2027, after the latest results; later ones will show.
- Filing: <https://nsearchives.nseindia.com/corporate/GRASIM_14082025155011_SEIntimationTranscript.pdf> (page 6)

## 2025-02-11 · The amalgamation of Aditya Birla Finance with Aditya Birla Capital is expected to be completed by March 2025.: Unverifiable

- Said: The amalgamation scheme now awaits approval from NCLT Ahmedabad and is expected to get completed by March '25.
- By: Pavan Jain, Q3 FY25 earnings call
- Due: by March 2025
- Verdict: Unverifiable
- Evidence: We could not match this promise to a figure, and no later call settles it.

## 2024-11-15 · The company expects its sixth paint plant in Kharagpur to begin operations in Q4 FY 2025.: Slipped

- Said: Our sixth plant at Kharagpur in West Bengal is expected to go live in Q4 FY '25.
- By: Pavan Jain, Q2 FY25 earnings call
- Due: in Q4 FY 2025
- Verdict: Slipped
- Evidence: The Q3 FY25 call, 11 Feb 2025 settles it: “Our sixth plant at Kharagpur in West Bengal is expected to go live in Q1 FY '26”

## 2024-08-09 · The company plans to increase its renewable energy capacity from 1-GW to 2-GW by the end of the current financial year (: Unverifiable

- Said: we aim to double the capacity by this financial year, okay? And the projects are already under implementation. So from 1-GW to 2-GW in this financial year
- By: Pavan Jain, Q1 FY25 earnings call
- Due: FY25
- Verdict: Unverifiable
- Evidence: We could not match this promise to a figure, and no later call settles it.

Live record: https://eqdoc.com/stock/GRASIM. Not investment advice.