type: "Promise Ledger"
title: "Greenply Industries Ltd: what management promised, and what happened"
description: "15 statements by Greenply Industries Ltd's management, each checked against the company's later filings: 3 slipped, 1 missed, 8 pending, 3 unverifiable."
resource: "https://eqdoc.com/stock/GREENPLY"
tags: ["promise ledger","management guidance","india","greenply"]
sources: [{"resource":"https://eqdoc.com/pdf/ann/7454402.pdf"},{"resource":"https://eqdoc.com/pdf/ann/7074397.pdf"},{"resource":"https://nsearchives.nseindia.com/corporate/GREEN_01082025182051_TRANSCRIPT_Q1FY26.pdf"}]
generated: {"by":"process:eqdoc-promise-audit"}
x-eqdoc-symbol: "GREENPLY"
x-eqdoc-counts: {"kept":0,"slipped":3,"missed":1,"pending":8,"unverifiable":3}
---

# How to read this

Each entry is something management said it would do, when it said it, and whether the company's later filings show it happened.
- **Kept**: a later filing shows it done. **Slipped**: done late or in part. **Missed**: the deadline passed without it.
- **Pending**: the deadline has not come, or no later filing yet speaks to it. **Unverifiable**: no filing could settle it.
- Evidence is either a sentence built from figures the company filed, or a quote from a later company document, as marked.

# Promises

## 2026-10-29 · Greenply committed to planting 50 million trees as part of its sustainability initiatives.: Pending

- Said: To Plant 50 Mn Trees
- By: Company presentation, Investor presentation, 29 Oct 2026
- Verdict: Pending
- Evidence: Not due yet, so it can't be checked.
- Filing: <https://eqdoc.com/pdf/ann/7454402.pdf> (page 26)

## 2026-10-29 · Greenply is adding 210,000 CBM per annum of MDF capacity under Line 2 in Vadodara, Gujarat.: Pending

- Said: Vadodara, Gujarat Line 2 (WIP) 2,10,000
- By: Company presentation, Investor presentation, 29 Oct 2026
- Verdict: Pending
- Evidence: Not due yet, so it can't be checked.
- Filing: <https://eqdoc.com/pdf/ann/7454402.pdf> (page 29)

## 2026-10-29 · Greenply is setting up a plywood manufacturing capacity of 13.5 Mn SQM per annum in Odisha.: Pending

- Said: Odisha (work in progress) 13.5
- By: Company presentation, Investor presentation, 29 Oct 2026
- Verdict: Pending
- Evidence: Not due yet, so it can't be checked.
- Filing: <https://eqdoc.com/pdf/ann/7454402.pdf> (page 29)

## 2026-10-29 · Greenply plans to expand its product portfolio as part of its strategic outlook.: Pending

- Said: Product portfolio expansion
- By: Company presentation, Investor presentation, 29 Oct 2026
- Verdict: Pending
- Evidence: Not due yet, so it can't be checked.
- Filing: <https://eqdoc.com/pdf/ann/7454402.pdf> (page 27)

## 2026-10-29 · Greenply plans to introduce innovative and futuristic products into its portfolio.: Pending

- Said: Introducing innovative & Futuristic products
- By: Company presentation, Investor presentation, 29 Oct 2026
- Verdict: Pending
- Evidence: Not due yet, so it can't be checked.
- Filing: <https://eqdoc.com/pdf/ann/7454402.pdf> (page 27)

## 2026-10-29 · The company aims to expand its manufacturing base across diversified locations.: Pending

- Said: Expanding Manufacturing base at diversified locations
- By: Company presentation, Investor presentation, 29 Oct 2026
- Verdict: Pending
- Evidence: Not due yet, so it can't be checked.
- Filing: <https://eqdoc.com/pdf/ann/7454402.pdf> (page 27)

## 2026-07-24 · Greenply is focusing on implementing automation and digitization across business operations.: Pending

- Said: Automation & digitization
- By: Company presentation, Investor presentation, 24 Jul 2026
- Verdict: Pending
- Evidence: Not due yet, so it can't be checked.
- Filing: <https://eqdoc.com/pdf/ann/7074397.pdf> (page 23)

## 2025-07-30 · The company expects its net debt to decrease to a ratio of 0.5 by the end of the fiscal year.: Unverifiable

- Said: we remain confident that our net debt will decline and return to the guided level of 0.5 by the end of the year.
- By: Manoj Tulsian, Q1 FY26 earnings call
- Verdict: Unverifiable
- Evidence: We could not match this promise to a figure, and no later call settles it.
- Filing: <https://nsearchives.nseindia.com/corporate/GREEN_01082025182051_TRANSCRIPT_Q1FY26.pdf> (page 4)

## 2025-04-29 · The company projects a total capital expenditure of approximately INR 60 to 65 crores for FY 2026.: Unverifiable

- Said: In FY '26, we are looking at a total capex again of around INR60 crores, INR65 crores
- By: Manoj Tulsian, Q4 FY25 earnings call
- Due: for FY 2026
- Verdict: Unverifiable
- Evidence: We could not match this promise to a figure, and no later call settles it.

## 2025-02-07 · The company expects to achieve plywood margins of over 10%.: Pending

- Said: we should be able to move to 10% plus margin.
- By: Manoj Tulsian, Q3 FY25 earnings call
- Verdict: Pending
- Evidence: Not due yet, so it can't be checked.

## 2025-02-07 · The company expects to reach its target of 50% growth for the MDF business for the full year.: Slipped

- Said: For MDF, we had initially targeted almost a 50% growth over last year. We should be around that number for the full year.
- By: Manoj Tulsian, Q3 FY25 earnings call
- Verdict: Slipped
- Evidence: The Q2 FY26 call, 4 Nov 2025 settles it: “maybe for the full year MDF with this guidance may reach around 14.5%, 15% margin for the full year.”

## 2024-10-29 · The HDF flooring line installation is expected to be finished in Q3 FY '25.: Missed

- Said: The installation of the line is likely to be completed in Q3 FY '25.
- By: Sanidhya Mittal, Q2 FY25 earnings call
- Due: in Q3 FY '25
- Verdict: Missed
- Evidence: The Q3 FY25 call, 7 Feb 2025 settles it: “Construction of our HDF flooring line has been delayed by 6 months due to the late arrival of major equipment, which is likely to arrive in the month of March”

## 2024-07-31 · The company expects MDF margins to be around 16% for the current fiscal year.: Unverifiable

- Said: I think we already gave the guidance on MDF one on the margin side, we said we'll be around 16% this year.
- By: Manoj Tulsian, Q1 FY25 earnings call
- Verdict: Unverifiable
- Evidence: We could not match this promise to a figure, and no later call settles it.

## 2024-07-31 · The company expects its net debt to be approximately INR450 crores by the end of the fiscal year.: Slipped

- Said: We continue to maintain our year-end debt guidance of around INR450 crores.
- By: Manoj Tulsian, Q1 FY25 earnings call
- Verdict: Slipped
- Evidence: The Q1 FY27 call, 24 Jul 2026 settles it: “at the end of this fiscal year which is 31st March ‘27, we will hit peak debt around in absolute value anything between 710 to 725, 730”

## 2024-07-31 · The company expects plywood volume growth to be between 8% and 10% for the current fiscal year.: Slipped

- Said: And coming to plywood, we said that our volume growth this year would be close to around 8% to 10%.
- By: Manoj Tulsian, Q1 FY25 earnings call
- Verdict: Slipped
- Evidence: The Q3 FY25 call, 7 Feb 2025 settles it: “we will try to be anywhere around 7% plus.”

Live record: https://eqdoc.com/stock/GREENPLY. Not investment advice.