title: "Garden Reach Shipbuilders & Engineers Ltd: what management promised, and what happened"
description: "30 statements by Garden Reach Shipbuilders & Engineers Ltd's management, each checked against the company's later filings: 3 kept, 8 slipped, 15 pending, 4 unverifiable."
resource: "https://eqdoc.com/stock/GRSE"
tags: ["promise ledger","management guidance","india","grse"]
sources: [{"resource":"https://nsearchives.nseindia.com/corporate/GRSE_11082026161819_Transcript_Investors_Analyst_Conference_Call_Q1_GRSE.pdf"},{"resource":"https://nsearchives.nseindia.com/corporate/GRSE_19052026111732_Transcript_Analyst__Call_for_Q4_and_FY_26_GRSE.pdf"},{"resource":"https://nsearchives.nseindia.com/corporate/GRSE_14112025165242_Transcript_of_Analyst_Meeet_-_Con_Call__for_Q2_FY_26_-_GRSE.pdf"},{"resource":"https://nsearchives.nseindia.com/corporate/GRSE_26082025150337_Transcript_of_Investors_Analyst_Conference_Call_Q1_FY26_GRSE_Reg_30.pdf"},{"resource":"https://nsearchives.nseindia.com/corporate/GRSE_27052025155142_Transcript_of_Inv_Analyst_Conf_Call_Q4_FY_25_of_GRSE.pdf"},{"resource":"https://nsearchives.nseindia.com/corporate/GRSE_20022025155019_Transcript__of_AnalystandBrokers_Meet_for_Q3_FY25.pdf"},{"resource":"https://nsearchives.nseindia.com/corporate/GRSE_21112024103627_Transcript_of_Analyst_Meeet_Con_Call_for_Q2_FY_24_GRSE.pdf"},{"resource":"https://nsearchives.nseindia.com/corporate/GRSE_21032024115934_Transcript_of_Analyst_Meet_Con_Call_for_Q3_FY_23_24_GRSE.pdf"}]
generated: {"by":"process:eqdoc-promise-audit","at":"2026-10-07"}
stale_after: "2027-01-15"
x-eqdoc-symbol: "GRSE"
x-eqdoc-counts: {"kept":3,"slipped":8,"missed":0,"pending":15,"unverifiable":4}
---

# How to read this

Each entry is something management said it would do, when it said it, and whether the company's later filings show it happened.
- **Kept**: a later filing shows it done. **Slipped**: done late or in part. **Missed**: the deadline passed without it.
- **Pending**: the deadline has not come, or no later filing yet speaks to it. **Unverifiable**: no filing could settle it.
- Evidence is either a sentence built from figures the company filed, or a quote from a later company document, as marked.

# Promises

## 2026-08-06 · Deliver the remaining four anti-submarine shallow water craft ships during FY27.: Pending

- Said: and the balance of four ships shall be delivered during the current financial year.
- By: P. R. Hari, Q1 FY27 earnings call
- Due: during the current financial year
- Verdict: Pending
- Evidence: Not due until 31 Mar 2027, after the latest results; later ones will show.
- Filing: <https://nsearchives.nseindia.com/corporate/GRSE_11082026161819_Transcript_Investors_Analyst_Conference_Call_Q1_GRSE.pdf> (page 5)

## 2026-08-06 · Expand concurrent shipbuilding capacity to 32 platforms by the end of calendar year 2026.: Pending

- Said: With ongoing modernization within our geographical premises, we expect this to be increased to concurrent construction of 32 platforms by the end of the calendar year,
- By: P. R. Hari, Q1 FY27 earnings call
- Due: by the end of the calendar year
- Verdict: Pending
- Evidence: Not due until 31 Dec 2026, after the latest results; later ones will show.
- Filing: <https://nsearchives.nseindia.com/corporate/GRSE_11082026161819_Transcript_Investors_Analyst_Conference_Call_Q1_GRSE.pdf> (page 6)

## 2026-05-19 · ASW SWC ship delivery: Pending

- Said: The last two ships, Ships 7 and 8, have touched around 60% physical progress of construction, and we will be delivering these ships during the current financial year
- Due: FY27
- Verdict: Pending
- Filing: <https://nsearchives.nseindia.com/corporate/GRSE_19052026111732_Transcript_Analyst__Call_for_Q4_and_FY_26_GRSE.pdf>

## 2026-05-19 · EBITDA margin guidance: Pending

- Said: We will be able to maintain similar margins in the coming year, that is the current year.
- Due: FY27
- Verdict: Pending
- Filing: <https://nsearchives.nseindia.com/corporate/GRSE_19052026111732_Transcript_Analyst__Call_for_Q4_and_FY_26_GRSE.pdf>

## 2026-05-19 · Ferries project completion: Pending

- Said: This project shall be completed by the end of the current financial year.
- Due: FY27
- Verdict: Pending
- Filing: <https://nsearchives.nseindia.com/corporate/GRSE_19052026111732_Transcript_Analyst__Call_for_Q4_and_FY_26_GRSE.pdf>

## 2026-05-19 · NGOPV project completion: Pending

- Said: we intend completing this project during Financial Year ‘29.
- Due: FY29
- Verdict: Pending
- Filing: <https://nsearchives.nseindia.com/corporate/GRSE_19052026111732_Transcript_Analyst__Call_for_Q4_and_FY_26_GRSE.pdf>

## 2026-05-19 · P-17 Alpha ship delivery: Pending

- Said: we intend delivering this ship during the current calendar year.
- Due: CY2026
- Verdict: Pending
- Filing: <https://nsearchives.nseindia.com/corporate/GRSE_19052026111732_Transcript_Analyst__Call_for_Q4_and_FY_26_GRSE.pdf>

## 2026-05-19 · Shipbuilding capacity expansion: Pending

- Said: this capacity will get increased to 32 ships by the end of the calendar year.
- Due: CY2026
- Verdict: Pending
- Filing: <https://nsearchives.nseindia.com/corporate/GRSE_19052026111732_Transcript_Analyst__Call_for_Q4_and_FY_26_GRSE.pdf>

## 2025-11-11 · Complete the 13 hybrid ferries project by 2027.: Pending

- Said: The project is on track and the delivery of these vessels shall commence from early 2026. The project completion is scheduled by 2027.
- By: P.R. Hari, Q2 FY26 earnings call
- Due: by 2027
- Verdict: Pending
- Evidence: Not due until 31 Dec 2027, after the latest results; later ones will show.
- Filing: <https://nsearchives.nseindia.com/corporate/GRSE_14112025165242_Transcript_of_Analyst_Meeet_-_Con_Call__for_Q2_FY_26_-_GRSE.pdf> (page 4)

## 2025-11-11 · Maintain 25% to 30% year-on-year revenue growth in FY26.: Unverifiable

- Said: We have been maintaining about 25% to 30% year-on-year growth and we expect to maintain similar trend during the current financial year too.
- By: P.R. Hari, Q2 FY26 earnings call
- Due: during the current financial year
- Verdict: Unverifiable
- Evidence: We could not match this promise to a figure, and no later call settles it.
- Filing: <https://nsearchives.nseindia.com/corporate/GRSE_14112025165242_Transcript_of_Analyst_Meeet_-_Con_Call__for_Q2_FY_26_-_GRSE.pdf> (page 7)

## 2025-06-30 · Conclude contract negotiations and acquire a greenfield shipyard facility within a year.: Pending

- Said: And we have already identified suitable areas; the discussions and deliberations are currently in progress. And within a year, we will conclude the negotiations and acquire this facility.
- By: P. R. Hari, Q4 FY25 earnings call
- Due: within a year
- Verdict: Pending
- Evidence: Not due yet, so it can't be checked.
- Filing: <https://nsearchives.nseindia.com/corporate/GRSE_26082025150337_Transcript_of_Investors_Analyst_Conference_Call_Q1_FY26_GRSE_Reg_30.pdf> (page 7)

## 2025-06-30 · Deliver the final P-17 Alpha ship by August 2026.: Slipped

- Said: The ship which has achieved around 80% progress is expected to be delivered by April 2026 and the last ship by August 2026.
- By: P. R. Hari, Q4 FY25 earnings call
- Due: by April 2026 and by August 2026
- Verdict: Slipped
- Evidence: The Q1 FY27 call, 6 Aug 2026 settles it: “The large ship has clocked nearly 85% physical progress of construction, and we intend to deliver the ship during this calendar year. By November, we should be able to deliver”
- Filing: <https://nsearchives.nseindia.com/corporate/GRSE_26082025150337_Transcript_of_Investors_Analyst_Conference_Call_Q1_FY26_GRSE_Reg_30.pdf> (page 5)

## 2025-06-30 · Expects to conclude the Next-Generation Corvette contract during FY26.: Slipped

- Said: The order value is expected to be to the tune of around ₹25,000 crores. And I expect this contract to be concluded during the current financial year.
- By: P. R. Hari, Q4 FY25 earnings call
- Due: during the current financial year
- Verdict: Slipped
- Evidence: The Q3 FY26 call, 31 Mar 2026 settles it: “Our current assessment is that the contract will be signed during the current quarter that is June.”
- Filing: <https://nsearchives.nseindia.com/corporate/GRSE_26082025150337_Transcript_of_Investors_Analyst_Conference_Call_Q1_FY26_GRSE_Reg_30.pdf> (page 5)

## 2025-06-30 · Expects to deliver the fourth Survey Vessel Large by the end of calendar year 2025.: Slipped

- Said: The last ship, the ship number four has achieved around 82% physical progress of construction, and this shift is expected to be delivered by the end of this calendar year.
- By: P. R. Hari, Q4 FY25 earnings call
- Due: by the end of this calendar year
- Verdict: Slipped
- Evidence: The Q2 FY26 call, 11 Nov 2025 settles it: “It shall now be made ready for delivery planned during February, 2026.”
- Filing: <https://nsearchives.nseindia.com/corporate/GRSE_26082025150337_Transcript_of_Investors_Analyst_Conference_Call_Q1_FY26_GRSE_Reg_30.pdf> (page 5)

## 2025-05-27 · Oceanographic Research Vessel delivery: Pending

- Said: and the delivery of the ship is planned during October 2027
- Due: 2027-10
- Verdict: Pending
- Filing: <https://nsearchives.nseindia.com/corporate/GRSE_27052025155142_Transcript_of_Inv_Analyst_Conf_Call_Q4_FY_25_of_GRSE.pdf>

## 2025-05-27 · P-17 Alpha third ship delivery: Pending

- Said: The third ship has attained 54 % of physical progress and this ship is planned for delivery during August 2026.
- Due: 2026-08
- Verdict: Pending
- Filing: <https://nsearchives.nseindia.com/corporate/GRSE_27052025155142_Transcript_of_Inv_Analyst_Conf_Call_Q4_FY_25_of_GRSE.pdf>

## 2025-05-27 · Shipbuilding capacity augmentation: Pending

- Said: we intend taking it up to 30 ships within the next two years.
- Due: 2027-05
- Verdict: Pending
- Filing: <https://nsearchives.nseindia.com/corporate/GRSE_27052025155142_Transcript_of_Inv_Analyst_Conf_Call_Q4_FY_25_of_GRSE.pdf>

## 2025-05-27 · Shipbuilding capacity expansion: Kept

- Said: So, we intend increasing the shipbuilding capacity from 24 to 28 ships by 2025-year end.
- Due: 2025-12
- Verdict: Kept
- Later filing says (2025-08-26): In 2024, through revamping and revitalizing some of our facilities, we have increased the shipbuilding capacity to 24 ships. And now we have a capacity to build 28 platforms
- Filing: <https://nsearchives.nseindia.com/corporate/GRSE_27052025155142_Transcript_of_Inv_Analyst_Conf_Call_Q4_FY_25_of_GRSE.pdf>

## 2025-02-13 · All 8 Anti-Submarine Shallow Water Craft ships will be delivered by October 2026.: Pending

- Said: Our contract delivery time line is by October, 2026. So, construction of all the 8 ships are on track. We'll be able to deliver by October, 2026.
- By: Cmde PR Hari, Q3 FY25 earnings call
- Due: by October, 2026
- Verdict: Pending
- Evidence: Not due until 31 Oct 2026, after the latest results; later ones will show.
- Filing: <https://nsearchives.nseindia.com/corporate/GRSE_20022025155019_Transcript__of_AnalystandBrokers_Meet_for_Q3_FY25.pdf> (page 5)

## 2025-02-13 · GRSE will maintain a PAT margin above 8%.: Unverifiable

- Said: I have been consistent in my views on this, that we'll be able to maintain PAT margin above 8%.
- By: Cmde PR Hari, Q3 FY25 earnings call
- Verdict: Unverifiable
- Evidence: The promise is not about net profit, the figure we hold that comes nearest; none of our figures settles it, and no later call does.
- Filing: <https://nsearchives.nseindia.com/corporate/GRSE_20022025155019_Transcript__of_AnalystandBrokers_Meet_for_Q3_FY25.pdf> (page 14)

## 2025-02-13 · Shipbuilding capacity will increase to 28 ships concurrently by the end of calendar year 2025.: Unverifiable

- Said: With what we have by end of this year, that means the end of the calendar year 25, we'll be increasing to 28 ships.
- By: Cmde PR Hari, Q3 FY25 earnings call
- Due: end of the calendar year 25
- Verdict: Unverifiable
- Evidence: We could not match this promise to a figure, and no later call settles it.
- Filing: <https://nsearchives.nseindia.com/corporate/GRSE_20022025155019_Transcript__of_AnalystandBrokers_Meet_for_Q3_FY25.pdf> (page 9)

## 2025-02-13 · The contract for two Coastal Research Vessels will be signed by 31 March 2025.: Slipped

- Said: The contract negotiations are currently in progress. We expect the contract to be signed by 31st March. That is our expectation.
- By: Cmde PR Hari, Q3 FY25 earnings call
- Due: by 31st March
- Verdict: Slipped
- Evidence: The Q3 FY25 call, 31 Mar 2025 settles it: “We already received the letter of intent, and the contract for this vessel is expected to be signed during June this year.”
- Filing: <https://nsearchives.nseindia.com/corporate/GRSE_20022025155019_Transcript__of_AnalystandBrokers_Meet_for_Q3_FY25.pdf> (page 4)

## 2025-02-13 · The fourth Survey Vessel Large will be delivered in July or August 2025.: Unverifiable

- Said: we intend delivery during this calendar year, which means the third ship, we expect to be delivered by June, and the fourth ship by July/August 2025.
- By: Cmde PR Hari, Q3 FY25 earnings call
- Due: July/August 2025
- Verdict: Unverifiable
- Evidence: We could not match this promise to a figure, and no later call settles it.
- Filing: <https://nsearchives.nseindia.com/corporate/GRSE_20022025155019_Transcript__of_AnalystandBrokers_Meet_for_Q3_FY25.pdf> (page 5)

## 2024-11-15 · The first Anti-Submarine Shallow Water Craft will be delivered in January 2025.: Slipped

- Said: We expect the ship to be delivered during January, 2025.
- By: management, Q2 FY25 earnings call
- Due: January, 2025
- Verdict: Slipped
- Evidence: The Q3 FY25 call, 13 Feb 2025 settles it: “We are confident of delivering this vessel by 15th of March this year.”
- Filing: <https://nsearchives.nseindia.com/corporate/GRSE_21112024103627_Transcript_of_Analyst_Meeet_Con_Call_for_Q2_FY_24_GRSE.pdf> (page 4)

## 2024-03-21 · Electric vessel delivery to West Bengal: Slipped

- Said: We intend to deliver this vessel to the Government of West Bengal next month i.e., April 2024.
- Due: 2024-04-30
- Verdict: Slipped
- Later filing says (2024-08-22): So, we have done the technical delivery of the vessel to the Government of West Bengal and we expect the formal takeover during the coming month.
- Filing: <https://nsearchives.nseindia.com/corporate/GRSE_21032024115934_Transcript_of_Analyst_Meet_Con_Call_for_Q3_FY_23_24_GRSE.pdf>

## 2024-03-21 · P17 Alpha delivery schedule: Kept

- Said: We intend to deliver the first ship during mid of 2025 that is August 2, a target for delivery of the first ship, and the second ship would be February 2026, and the third ship by August 2026.
- Due: 2025-08-02
- Verdict: Kept
- Later filing says (2025-08-26): Most happy to inform you that GRSE has delivered the first P‐17 Alpha ship to the Indian Navy on 31st of July, this year.
- Filing: <https://nsearchives.nseindia.com/corporate/GRSE_21032024115934_Transcript_of_Analyst_Meet_Con_Call_for_Q3_FY_23_24_GRSE.pdf>

## 2024-03-21 · Ship repairs revenue target: Pending

- Said: May be again, our internal target is by 2025 at least 200 to 250 crore from ship repairs.
- Due: 2025
- Verdict: Pending
- Filing: <https://nsearchives.nseindia.com/corporate/GRSE_21032024115934_Transcript_of_Analyst_Meet_Con_Call_for_Q3_FY_23_24_GRSE.pdf>

## 2024-03-21 · Shipbuilding capacity enhancement target: Kept

- Said: the aim is to enhance our shipbuilding capacity from concurrent construction of 20 warships to 24 warships and we intend to achieve this target by calendar year 2025.
- Due: 2025
- Verdict: Kept
- Later filing says (2025-08-26): In 2024, through revamping and revitalizing some of our facilities, we have increased the shipbuilding capacity to 24 ships.
- Filing: <https://nsearchives.nseindia.com/corporate/GRSE_21032024115934_Transcript_of_Analyst_Meet_Con_Call_for_Q3_FY_23_24_GRSE.pdf>

## 2024-03-21 · Survey Vessel Large deliveries: Slipped

- Said: My appreciation for delivery of the ship would be May or June this year. Thereafter, by December 2024, we will be delivering the second of the remaining three ships
- Due: 2024-06-30
- Verdict: Slipped
- Later filing says (2025-05-27): During the period intervening the last financial year, and now we have delivered one Survey Vessel Large that is the second in a series of Four ships that we are building for the Navy.
- Filing: <https://nsearchives.nseindia.com/corporate/GRSE_21032024115934_Transcript_of_Analyst_Meet_Con_Call_for_Q3_FY_23_24_GRSE.pdf>

## 2024-03-21 · Underwater surface platform productionizing: Slipped

- Said: They wanted certain modifications which are being presently undertaken and we intend the productionizing this underwater platform by end of this calendar year.
- Due: 2024-12-31
- Verdict: Slipped
- Later filing says (2026-08-11): In addition, an autonomous underwater platform, which was developed by us. Again, the prototype successfully proved in the Tengangsu Lake about a year back.
- Filing: <https://nsearchives.nseindia.com/corporate/GRSE_21032024115934_Transcript_of_Analyst_Meet_Con_Call_for_Q3_FY_23_24_GRSE.pdf>

Live record: https://eqdoc.com/stock/GRSE. Not investment advice.