type: "Promise Ledger"
title: "HEG Advanced Materials Ltd: what management promised, and what happened"
description: "29 statements by HEG Advanced Materials Ltd's management, each checked against the company's later filings: 1 slipped, 2 missed, 20 pending, 6 unverifiable."
resource: "https://eqdoc.com/stock/HEGAM"
tags: ["promise ledger","management guidance","india","hegam"]
sources: [{"resource":"https://eqdoc.com/pdf/ann/7485558.pdf"},{"resource":"https://nsearchives.nseindia.com/corporate/HEG_23012026185100_Stxintimation_23012026.pdf"},{"resource":"https://nsearchives.nseindia.com/corporate/HEG_25022024150045_ConcalltranscriptQ3FY24.pdf"}]
generated: {"by":"process:eqdoc-promise-audit","at":"2026-11-28"}
stale_after: "2027-03-08"
x-eqdoc-symbol: "HEGAM"
x-eqdoc-counts: {"kept":0,"slipped":1,"missed":2,"pending":20,"unverifiable":6}
---

# How to read this

Each entry is something management said it would do, when it said it, and whether the company's later filings show it happened.
- **Kept**: a later filing shows it done. **Slipped**: done late or in part. **Missed**: the deadline passed without it.
- **Pending**: the deadline has not come, or no later filing yet speaks to it. **Unverifiable**: no filing could settle it.
- Evidence is either a sentence built from figures the company filed, or a quote from a later company document, as marked.

# Promises

## 2026-11-04 · BESS IPP Commissioning: Pending

- Said: BESS IPP 200 MWh Gujarat Under Development Target Commissioning Q3 FY27
- Due: Q3 FY27
- Verdict: Pending
- Filing: <https://eqdoc.com/pdf/ann/7485558.pdf>

## 2026-11-04 · Graphene capacity target: Pending

- Said: Graphene “Wonder Material” – Growth Strategy Initiative 500 MT in 2028
- Due: 2028
- Verdict: Pending
- Filing: <https://eqdoc.com/pdf/ann/7485558.pdf>

## 2026-11-04 · Phase I Anode Plant COD: Pending

- Said: 20 KMT plant under construction with COD of June 2027
- Due: 2027-06-30
- Verdict: Pending
- Filing: <https://eqdoc.com/pdf/ann/7485558.pdf>

## 2026-11-04 · Phase II Anode Plant COD: Pending

- Said: 44K MT Phase II | COD: Mar’29 Additional 24K MT Anode plant expansion to lead next leap of growth
- Due: 2029-03-31
- Verdict: Pending
- Filing: <https://eqdoc.com/pdf/ann/7485558.pdf>

## 2026-07-24 · The company expects to maintain capacity utilization above 90% in future quarters.: Pending

- Said: expect to continue operating at more than 90% in the forthcoming quarters as well.
- By: Ravi Jhunjhunwala, Q1 FY27 earnings call
- Verdict: Pending
- Evidence: Not due yet, so it can't be checked.

## 2026-07-10 · The company aims to grow its green power generation capacity from 292 MW in FY26 to 754 MW by FY28.: Unverifiable

- Said: Green power generation business 292 MW (FY 26) to 754 MW (FY28)
- By: Company presentation, Investor presentation, 10 Jul 2026
- Due: 2026-03-31
- Verdict: Unverifiable
- Evidence: We could not match this promise to a figure, and no later call settles it.

## 2026-07-10 · The company expects to complete the BESS IPP project with 200 MWh capacity by Q3 FY27.: Pending

- Said: BESS IPP 200MWh Q3 FY27
- By: Company presentation, Investor presentation, 10 Jul 2026
- Due: 2026-12-31
- Verdict: Pending
- Evidence: Not due until 31 Dec 2026, after the latest results; later ones will show.

## 2026-07-10 · The company expects to complete the Hydro 3 project with 76 MW capacity by Q4 FY31.: Pending

- Said: Hydro 3 76 MW Q4 FY31
- By: Company presentation, Investor presentation, 10 Jul 2026
- Due: 2031-03-31
- Verdict: Pending
- Evidence: Not due until 31 Mar 2031, after the latest results; later ones will show.

## 2026-07-10 · The company expects to complete the Solar CNI project with 300 MWp capacity by Q2 FY28.: Pending

- Said: Solar CNI 300 MWp Q2 FY 28
- By: Company presentation, Investor presentation, 10 Jul 2026
- Due: 2027-09-30
- Verdict: Pending
- Evidence: Not due until 30 Sep 2027, after the latest results; later ones will show.

## 2026-07-10 · The company plans to expand its REPlus gigafactory capacity to 6 GWh by the second half of FY27.: Pending

- Said: REPlus - State-of-the-Art 1 GWh Gigafactory expanding to 6GWh by H2 FY27
- By: Company presentation, Investor presentation, 10 Jul 2026
- Due: 2027-03-31
- Verdict: Pending
- Evidence: Not due until 31 Mar 2027, after the latest results; later ones will show.

## 2026-07-10 · The company plans to expand its battery energy solution capacity from 1 GWh in FY26 to 6 GWh by FY27.: Unverifiable

- Said: Battery Energy Solution 1 GWh (FY26) to 6 GWh (FY 27)
- By: Company presentation, Investor presentation, 10 Jul 2026
- Due: 2026-03-31
- Verdict: Unverifiable
- Evidence: We could not match this promise to a figure, and no later call settles it.

## 2026-07-10 · The company plans to increase its graphite electrode capacity from 100,000 tonnes in FY26 to 115,000 tonnes by FY29.: Unverifiable

- Said: Graphite Electrode • 1,00,000 (FY 26) to 1,15,000 Tonne Capacity (FY 29)
- By: Company presentation, Investor presentation, 10 Jul 2026
- Due: 2026-03-31
- Verdict: Unverifiable
- Evidence: We could not match this promise to a figure, and no later call settles it.

## 2026-07-10 · The company targets scaling up production to reach 60,000 metric tonnes by FY32.: Pending

- Said: Production Scale-Up Targeted To Reach 60 KMT By FY32
- By: Company presentation, Investor presentation, 10 Jul 2026
- Due: 2032-03-31
- Verdict: Pending
- Evidence: Not due until 31 Mar 2032, after the latest results; later ones will show.

## 2026-07-10 · The start of production for the Phase I 20K MT anode facility is scheduled for Q1 FY28.: Pending

- Said: SOP: Q1 FY 28
- By: Company presentation, Investor presentation, 10 Jul 2026
- Due: 2027-06-30
- Verdict: Pending
- Evidence: Not due until 30 Jun 2027, after the latest results; later ones will show.

## 2026-05-04 · The company expects EBITDA margins for the full year FY26 to be above 20%.: Pending

- Said: Yes, (+20%).
- By: Ravi Tripathi, Q4 FY26 earnings call
- Verdict: Pending
- Evidence: Not due until 31 Mar 2027, after the latest results; later ones will show.

## 2026-01-23 · Accumulated capex target: Pending

- Said: taking it to overall capex of 7700 crores.
- Due: FY30
- Verdict: Pending
- Filing: <https://nsearchives.nseindia.com/corporate/HEG_23012026185100_Stxintimation_23012026.pdf>

## 2026-01-23 · Anode capacity expansion: Pending

- Said: We aim to expand this overall capacity to 60 kTPA by FY32.
- Due: FY32
- Verdict: Pending
- Filing: <https://nsearchives.nseindia.com/corporate/HEG_23012026185100_Stxintimation_23012026.pdf>

## 2026-01-23 · Anode plant operational timeline: Pending

- Said: The large amount will be invested because the plant needs to be LIVE by April'27, March'27.
- Due: 2027-04-30
- Verdict: Pending
- Filing: <https://nsearchives.nseindia.com/corporate/HEG_23012026185100_Stxintimation_23012026.pdf>

## 2026-01-23 · BESS and Solar portfolio target: Pending

- Said: Over the next five years, we intend to build a total portfolio of about 5.9 gigawatt hour in BESS and about 3.7 gigawatt hour in the solar.
- Due: FY31
- Verdict: Pending
- Filing: <https://nsearchives.nseindia.com/corporate/HEG_23012026185100_Stxintimation_23012026.pdf>

## 2026-01-23 · Capex deployment: Pending

- Said: By end of FY27, we intend to deploy almost 4300 crores capital.
- Due: FY27
- Verdict: Pending
- Filing: <https://nsearchives.nseindia.com/corporate/HEG_23012026185100_Stxintimation_23012026.pdf>

## 2026-01-23 · Graphene derivative plant setup: Pending

- Said: and then we intend to set up a 4,000 metric tonnes of graphene derivative plant within the same premises where the anode plant is coming up.
- Verdict: Pending
- Filing: <https://nsearchives.nseindia.com/corporate/HEG_23012026185100_Stxintimation_23012026.pdf>

## 2025-02-14 · The company expects EBITDA margins to remain in the current range of 16% to 17% for the next two quarters.: Unverifiable

- Said: So, we can more or less -- we more or less know our -- if not full 2 quarters, we know at any point of time what does the next quarter
- By: Ravi Jhunjhunwala, Q3 FY25 earnings call
- Verdict: Unverifiable
- Evidence: We could not match this promise to a figure, and no later call settles it.

## 2024-11-15 · The company expects EBITDA margins to remain in the current 17% range for upcoming quarters.: Unverifiable

- Said: Yes we are expecting the similar range in the coming quarters too.
- By: Ravi Kant Tripathi, Q2 FY25 earnings call
- Verdict: Unverifiable
- Evidence: We could not match this promise to a figure, and no later call settles it.

## 2024-08-20 · The company expects to maintain 75% capacity utilization for the full fiscal year FY25.: Unverifiable

- Said: we hope to be close to 75% for the full year despite steel not doing very well in the world.
- By: Ravi Jhunjhunwala, Q1 FY25 earnings call
- Verdict: Unverifiable
- Evidence: We could not match this promise to a figure, and no later call settles it.

## 2024-02-25 · Anode plant production start: Missed

- Said: The plant production should start around March or April of 2025.
- Due: 2025-04-30
- Verdict: Missed
- Later filing says (2026-01-16): SOP: 1st April 2027
- Filing: <https://nsearchives.nseindia.com/corporate/HEG_25022024150045_ConcalltranscriptQ3FY24.pdf>

## 2024-02-25 · Capacity utilization recovery to 85%: Slipped

- Said: we are sure that within a matter of one year, we will be back at 85% on 100,000 tons also.
- Due: FY25
- Verdict: Slipped
- Later filing says (2026-02-16): We continue to operate at the highest capacity utilizations in the industry, all around the world, at 85% in previous quarter and 89% in the last three quarters combined
- Filing: <https://nsearchives.nseindia.com/corporate/HEG_25022024150045_ConcalltranscriptQ3FY24.pdf>

## 2024-02-25 · Commercial sales from expanded capacity: Pending

- Said: We'll start selling electrodes from this quarter from this expanded capacity.
- Due: Q4 FY24
- Verdict: Pending
- Filing: <https://nsearchives.nseindia.com/corporate/HEG_25022024150045_ConcalltranscriptQ3FY24.pdf>

## 2024-02-25 · FY24 sales volume growth: Pending

- Said: and by the time we close the year, we believe that we would have sold about 10% to 12% more than last year.
- Due: FY24
- Verdict: Pending
- Filing: <https://nsearchives.nseindia.com/corporate/HEG_25022024150045_ConcalltranscriptQ3FY24.pdf>

## 2024-02-25 · Graphite anode powder plant completion: Missed

- Said: and the construction has started, which we intend to complete by mid-2025.
- Due: 2025-07-31
- Verdict: Missed
- Later filing says (2026-11-12): On the anode front, our Phase 1 20,000 metric ton plant at Dewas is already 61% complete, tracking for commercial commissioning by June 2027.
- Filing: <https://nsearchives.nseindia.com/corporate/HEG_25022024150045_ConcalltranscriptQ3FY24.pdf>

Live record: https://eqdoc.com/stock/HEGAM. Not investment advice.