type: "Promise Ledger"
title: "Hindustan Zinc Ltd: what management promised, and what happened"
description: "24 statements by Hindustan Zinc Ltd's management, each checked against the company's later filings: 1 kept, 7 slipped, 10 pending, 6 unverifiable."
resource: "https://eqdoc.com/stock/HINDZINC"
tags: ["promise ledger","management guidance","india","hindzinc"]
sources: [{"resource":"https://eqdoc.com/pdf/ann/7412403.pdf"},{"resource":"https://eqdoc.com/pdf/ann/7075116.pdf"},{"resource":"https://nsearchives.nseindia.com/corporate/HINDZINCNSE_28042026174558_SEIntimation28042026.pdf"},{"resource":"https://nsearchives.nseindia.com/corporate/HINDZINCNSE_18102025172209_Transcriptearningcall30092025.pdf"},{"resource":"https://nsearchives.nseindia.com/corporate/HINDZINCNSE_27082025162000_transcriptAGM2025.pdf"}]
generated: {"by":"process:eqdoc-promise-audit"}
x-eqdoc-symbol: "HINDZINC"
x-eqdoc-counts: {"kept":1,"slipped":7,"missed":0,"pending":10,"unverifiable":6}
---

# How to read this

Each entry is something management said it would do, when it said it, and whether the company's later filings show it happened.
- **Kept**: a later filing shows it done. **Slipped**: done late or in part. **Missed**: the deadline passed without it.
- **Pending**: the deadline has not come, or no later filing yet speaks to it. **Unverifiable**: no filing could settle it.
- Evidence is either a sentence built from figures the company filed, or a quote from a later company document, as marked.

# Promises

## 2026-10-19 · Achieve 70% renewable power sourcing by FY28.: Pending

- Said: • 70% renewable power by FY28
- By: Company presentation, Investor presentation, 19 Oct 2026
- Due: FY28
- Verdict: Pending
- Evidence: Not due until 31 Mar 2028, after the latest results; later ones will show.
- Filing: <https://eqdoc.com/pdf/ann/7412403.pdf> (page 24)

## 2026-10-19 · Complete REE exploration at Nawatola-Laband by December 2028 and commence mining by June 2030.: Pending

- Said: REE Nawatola-Laband Uttar Pradesh Grant of composite license Dec’28 Jun’30
- By: Company presentation, Investor presentation, 19 Oct 2026
- Due: Jun'30
- Verdict: Pending
- Evidence: Not due until 31 Dec 2028, after the latest results; later ones will show.
- Filing: <https://eqdoc.com/pdf/ann/7412403.pdf> (page 7)

## 2026-10-19 · Conclude exploration for Tungsten at Balepalyam by September 2028 and start mining by September 2030.: Pending

- Said: Tungsten Balepalyam Andhra Pradesh Exploration started in Q4FY26 Sep’28 Sep’30
- By: Company presentation, Investor presentation, 19 Oct 2026
- Due: Sep'30
- Verdict: Pending
- Evidence: Not due until 30 Sep 2028, after the latest results; later ones will show.
- Filing: <https://eqdoc.com/pdf/ann/7412403.pdf> (page 7)

## 2026-07-24 · Commission the 510 KTPA fertilizer plant at Chanderiya by 2QFY27.: Unverifiable

- Said: Fertilizer Plant at Chanderiya aims to support farmers’ needs through DAP fertilizers currently being imported Expected to be completed by 2QFY27
- By: Company presentation, Investor presentation, 24 Jul 2026
- Due: 2QFY27
- Verdict: Unverifiable
- Evidence: We could not match this promise to a figure, and no later call settles it.
- Filing: <https://eqdoc.com/pdf/ann/7075116.pdf> (page 24)

## 2026-07-24 · Complete the 10 MTPA zinc tailings reprocessing plant by 4QFY28.: Pending

- Said: Feed capacity: 10 MTPA ▪ Total approved investment: ₹ 3,823 crore ▪ Target completion: 4QFY28
- By: Company presentation, Investor presentation, 24 Jul 2026
- Due: 4QFY28
- Verdict: Pending
- Evidence: Not due until 31 Mar 2028, after the latest results; later ones will show.
- Filing: <https://eqdoc.com/pdf/ann/7075116.pdf> (page 23)

## 2026-07-24 · Complete the hot acid leaching project at Dariba by 2QFY27, yielding 27 TPA silver and 6 KTPA lead.: Unverifiable

- Said: Potential to produce 27 TPA silver and 6 KTPA lead annually Expected to be completed by 2QFY27
- By: Company presentation, Investor presentation, 24 Jul 2026
- Due: 2QFY27
- Verdict: Unverifiable
- Evidence: We could not match this promise to a figure, and no later call settles it.
- Filing: <https://eqdoc.com/pdf/ann/7075116.pdf> (page 24)

## 2026-07-24 · Expand refined metal capacity to 1,379 KTPA and mined metal capacity to 1,510 KTPA by 2QFY29.: Pending

- Said: Refined metal capacity expansion: 1,129 KTPA to 1,379 KTPA at Debari ▪ Mined metal capacity expansion: 1,180 KTPA to 1,510 KTPA across mines
- By: Company presentation, Investor presentation, 24 Jul 2026
- Due: 2QFY29
- Verdict: Pending
- Evidence: Not due until 30 Sep 2028, after the latest results; later ones will show.
- Filing: <https://eqdoc.com/pdf/ann/7075116.pdf> (page 23)

## 2026-07-24 · Maintain zinc cost of production below $1,000 per metric tonne.: Unverifiable

- Said: Maintain cost below $1,000/MT via proactive cost saving initiatives, increased scale of production, and operational efficiencies
- By: Company presentation, Investor presentation, 24 Jul 2026
- Verdict: Unverifiable
- Evidence: We could not match this promise to a figure, and no later call settles it.
- Filing: <https://eqdoc.com/pdf/ann/7075116.pdf> (page 25)

## 2026-04-24 · FY27 zinc cost of production will be guided between $975 and $1,000 per ton.: Pending

- Said: For FY27, we have guided zinc cost of production excluding royalty at $975 to $1,000 per ton, reflecting prevailing global uncertainties.
- By: Sandeep Modi, Q4 FY26 earnings call
- Due: FY27
- Verdict: Pending
- Evidence: Not due until 31 Mar 2027, after the latest results; later ones will show.
- Filing: <https://nsearchives.nseindia.com/corporate/HINDZINCNSE_28042026174558_SEIntimation28042026.pdf> (page 6)

## 2026-04-24 · Planned FY27 growth capex is projected to range between $500 million and $600 million.: Pending

- Said: Planned capital expenditure for FY27 is in the range of $500 million to $600 million towards announced growth projects.
- By: Sandeep Modi, Q4 FY26 earnings call
- Due: FY27
- Verdict: Pending
- Evidence: Not due until 31 Mar 2027, after the latest results; later ones will show.
- Filing: <https://nsearchives.nseindia.com/corporate/HINDZINCNSE_28042026174558_SEIntimation28042026.pdf> (page 6)

## 2026-04-24 · Silver production is guided to 680 tons (±10 tons) for the year ahead.: Pending

- Said: and a refined metal production of 1,100 KTPA, plus or minus 10 KT, with an expected refined silver production of 680 tons, plus or minus 10 tons.
- By: Arun Misra, Q4 FY26 earnings call
- Due: the year ahead
- Verdict: Pending
- Evidence: Not due yet, so it can't be checked.
- Filing: <https://nsearchives.nseindia.com/corporate/HINDZINCNSE_28042026174558_SEIntimation28042026.pdf> (page 5)

## 2025-10-17 · Full-year growth capex will be between $350 million and $400 million.: Slipped

- Said: In line with Board approved growth projects, our growth capex guidance for the year would be in the range of $350 million to $400 million.
- By: Sandeep Modi, Q2 FY26 earnings call
- Due: the year
- Verdict: Slipped
- Evidence: The Q3 FY26 call, 19 Jan 2026 settles it: “So, we may be having around $300 million total year growth capex. So that is something which you can factor for the full year”
- Filing: <https://nsearchives.nseindia.com/corporate/HINDZINCNSE_18102025172209_Transcriptearningcall30092025.pdf> (page 6)

## 2025-10-17 · Hot acid leaching commissioning is scheduled for completion in Q4 FY26.: Slipped

- Said: The debottlenecking of Chanderiya Lead Zinc Smelter is on schedule for completion by quarter 3 FY '26, followed by lead, silver recovery plant with hot acid leaching technology by quarter 4 FY26.
- By: Arun Misra, Q2 FY26 earnings call
- Due: quarter 4 FY26
- Verdict: Slipped
- Evidence: The Q4 FY26 call, 24 Apr 2026 settles it: “Given its complexity as a first-of-its-kind project in India, commissioning is now expected in 2Q FY '27.”
- Filing: <https://nsearchives.nseindia.com/corporate/HINDZINCNSE_18102025172209_Transcriptearningcall30092025.pdf> (page 5)

## 2025-10-17 · The renewable energy power mix will exit FY26 at 25%.: Slipped

- Said: 19% was the renewable energy during this quarter, and the exit, we -- as we said earlier, should be 25%.
- By: Sandeep Modi, Q2 FY26 earnings call
- Due: end of FY '26
- Verdict: Slipped
- Evidence: The Q4 FY26 call, 24 Apr 2026 settles it: “So FY26 we closed for the full year around 18% renewable energy and for the full year in FY'27, we should be between 30% to 35%.”
- Filing: <https://nsearchives.nseindia.com/corporate/HINDZINCNSE_18102025172209_Transcriptearningcall30092025.pdf> (page 9)

## 2025-08-27 · Chanderiya smelter debottlenecking will complete by Q2 FY26.: Slipped

- Said: Our smelter de-bottlenecking projects at Dariba and Chanderiya are progressing well and expected to complete in Q2 of FY26.
- By: Arun Misra, Q1 FY26 earnings call
- Due: in Q2 of FY26
- Verdict: Slipped
- Evidence: The Q2 FY26 call, 17 Oct 2025 settles it: “The debottlenecking of Chanderiya Lead Zinc Smelter is on schedule for completion by quarter 3 FY '26, followed by lead, silver recovery plant with hot acid leaching technology by quarter 4 FY26.”
- Filing: <https://nsearchives.nseindia.com/corporate/HINDZINCNSE_27082025162000_transcriptAGM2025.pdf> (page 6)

## 2025-08-27 · Operations will transition to 70% renewable energy by FY28.: Pending

- Said: Today, nearly 13% of our operations are powered by renewable energy and we are on track to scale this to 70% by FY28.
- By: Priya Agarwal, Q1 FY26 earnings call
- Due: by FY28
- Verdict: Pending
- Evidence: Not due until 31 Mar 2028, after the latest results; later ones will show.
- Filing: <https://nsearchives.nseindia.com/corporate/HINDZINCNSE_27082025162000_transcriptAGM2025.pdf> (page 5)

## 2025-08-27 · The fertilizer plant at Chanderiya will be commissioned by Q1 FY27.: Slipped

- Said: the fertilizer plant at Chanderiya is expected to be commissioned by Q1 of next financial year.
- By: Arun Misra, Q1 FY26 earnings call
- Due: by Q1 of next financial year
- Verdict: Slipped
- Evidence: The Q4 FY26 call, 24 Apr 2026 settles it: “The fertilizer project is also on track for commissioning in early 2Q FY '27.”
- Filing: <https://nsearchives.nseindia.com/corporate/HINDZINCNSE_27082025162000_transcriptAGM2025.pdf> (page 6)

## 2025-04-25 · The company expects to reach 1.2 million tons of metal exit capacity by the next fiscal year.: Unverifiable

- Said: by the next year, we should be there in 1.2 million ton metal exit capacity in next fiscal year itself.
- By: Arun Misra, Q4 FY25 earnings call
- Verdict: Unverifiable
- Evidence: We could not match this promise to a figure, and no later call settles it.

## 2025-01-28 · The company expects the renewable energy share to be between 18% and 20% by the end of the quarter.: Kept

- Said: Renewable energy exit, we should be around between 18% to 20%.
- By: Arun Misra, Q3 FY25 earnings call
- Verdict: Kept
- Evidence: The Q2 FY26 call, 17 Oct 2025 settles it: “19% was the renewable energy during this quarter, and the exit, we -- as we said earlier, should be 25%.”

## 2025-01-28 · The fertilizer plant will get commissioned by the fourth quarter of 2026.: Pending

- Said: The fertilizer plant will get commissioned by the Q4 ‘26.
- By: Sandeep Modi, Q3 FY25 earnings call
- Due: 2026-12-31
- Verdict: Pending
- Evidence: Not due until 31 Dec 2026, after the latest results; later ones will show.

## 2024-10-18 · The company aims to reach at least 1.2 million tons of metal production in the next financial year.: Unverifiable

- Said: Yes, yes, of course. Of course, we will try. We will -- at least 1.2 million ton next financial year.
- By: Arun Misra, Q2 FY25 earnings call
- Verdict: Unverifiable
- Evidence: We could not match this promise to a figure, and no later call settles it.

## 2024-10-18 · The company expects the renewable energy share to reach 23% to 25% by the end of the fourth quarter.: Slipped

- Said: And by quarter 4, we will be exiting around 23% to 25% with the renewable energy share.
- By: Sandeep Modi, Q2 FY25 earnings call
- Verdict: Slipped
- Evidence: The Q3 FY25 call, 28 Jan 2025 settles it: “Renewable energy exit, we should be around between 18% to 20%.”

## 2024-10-18 · The company expects to achieve costs at the lower end of its $1,050 to $1,100 guidance range.: Unverifiable

- Said: we are confident that we will be delivering towards the lower end of the cost band.
- By: Sandeep Modi, Q2 FY25 earnings call
- Verdict: Unverifiable
- Evidence: We could not match this promise to a figure, and no later call settles it.

## 2024-10-18 · The fertilizer plant is scheduled to start operations around the third quarter of fiscal year 2026.: Slipped

- Said: So fertilizer as per the committed time line is going to start in the FY '26 around Q3.
- By: Sandeep Modi, Q2 FY25 earnings call
- Due: 2025-12-31
- Verdict: Slipped
- Evidence: The Q1 FY27 call, 24 Jul 2026 settles it: “Fertilizer plant should come in place by quarter 1 of next financial year.”

Live record: https://eqdoc.com/stock/HINDZINC. Not investment advice.