title: "JSW Energy Ltd: what management promised, and what happened"
description: "20 statements by JSW Energy Ltd's management, each checked against the company's later filings: 3 slipped, 15 pending, 2 unverifiable."
resource: "https://eqdoc.com/stock/JSWENERGY"
tags: ["promise ledger","management guidance","india","jswenergy"]
sources: [{"resource":"https://eqdoc.com/pdf/ann/7447684.pdf"},{"resource":"https://nsearchives.nseindia.com/corporate/KRUTIKAJSWEL_22072026144727_Finalsigned.pdf"},{"resource":"https://eqdoc.com/pdf/ann/7067562.pdf"},{"resource":"https://eqdoc.com/pdf/ann/7084989.pdf"},{"resource":"https://eqdoc.com/pdf/ann/6811327.pdf"},{"resource":"https://nsearchives.nseindia.com/corporate/RITESHJSWEL_22102025185628_TranscriptJSWELQ2.pdf"},{"resource":"https://nsearchives.nseindia.com/corporate/RITESHJSWEL_06082025214119_JSWELLettertoNSEBSESigned.pdf"}]
generated: {"by":"process:eqdoc-promise-audit"}
x-eqdoc-symbol: "JSWENERGY"
x-eqdoc-counts: {"kept":0,"slipped":3,"missed":0,"pending":15,"unverifiable":2}
---

# How to read this

Each entry is something management said it would do, when it said it, and whether the company's later filings show it happened.
- **Kept**: a later filing shows it done. **Slipped**: done late or in part. **Missed**: the deadline passed without it.
- **Pending**: the deadline has not come, or no later filing yet speaks to it. **Unverifiable**: no filing could settle it.
- Evidence is either a sentence built from figures the company filed, or a quote from a later company document, as marked.

# Promises

## 2026-10-28 · Add 1,606 MW of generation capacity in H2 FY27.: Pending

- Said: Estimated H2 FY27 Capacity Target 1,606 MW
- By: Company presentation, Investor presentation, 28 Oct 2026
- Due: H2 FY27
- Verdict: Pending
- Evidence: Not due until 31 Mar 2027, after the latest results; later ones will show.
- Filing: <https://eqdoc.com/pdf/ann/7447684.pdf> (page 6)

## 2026-10-28 · Commission 1.0 GWh of battery energy storage system (BESS) capacity by FY27.: Pending

- Said: Targeting 1.0 GWh BESS by FY27
- By: Company presentation, Investor presentation, 28 Oct 2026
- Due: FY27
- Verdict: Pending
- Evidence: Not due until 31 Mar 2027, after the latest results; later ones will show.
- Filing: <https://eqdoc.com/pdf/ann/7447684.pdf> (page 22)

## 2026-07-22 · Achieve commercial operation date for 1,200 MW of Mahanadi capacity in FY29.: Pending

- Said: 1,200 MW: Target COD - FY29
- By: Company presentation, Investor presentation, 22 Jul 2026
- Due: FY29
- Verdict: Pending
- Evidence: Not due until 31 Mar 2029, after the latest results; later ones will show.
- Filing: <https://nsearchives.nseindia.com/corporate/KRUTIKAJSWEL_22072026144727_Finalsigned.pdf> (page 23)

## 2026-07-22 · Achieve commercial operation date for the 600 MW Mahanadi unit in FY28.: Pending

- Said: 600 MW: Target COD - FY28
- By: Company presentation, Investor presentation, 22 Jul 2026
- Due: FY28
- Verdict: Pending
- Evidence: Not due until 31 Mar 2028, after the latest results; later ones will show.
- Filing: <https://nsearchives.nseindia.com/corporate/KRUTIKAJSWEL_22072026144727_Finalsigned.pdf> (page 23)

## 2026-07-22 · Commission 1.5 GW of capacity by H1 FY27.: Pending

- Said: Commissioning Target of 1.5 GW by H1FY27
- By: Company presentation, Investor presentation, 22 Jul 2026
- Due: H1FY27
- Verdict: Pending
- Evidence: Not due until 31 Mar 2027, after the latest results; later ones will show.
- Filing: <https://eqdoc.com/pdf/ann/7067562.pdf> (page 8)

## 2026-07-22 · Deliver 3 GW of capacity additions in FY27.: Pending

- Said: Firmly on Track to Deliver 3 GW Capacity Addition in FY27
- By: Company presentation, Investor presentation, 22 Jul 2026
- Due: FY27
- Verdict: Pending
- Evidence: Not due until 31 Mar 2027, after the latest results; later ones will show.
- Filing: <https://eqdoc.com/pdf/ann/7067562.pdf> (page 22)

## 2026-07-22 · Deploy capital expenditure of ₹20,000 crore in FY27.: Pending

- Said: FY27 Capex Guidance of ₹ 20,000 Cr
- By: Company presentation, Investor presentation, 22 Jul 2026
- Due: FY27
- Verdict: Pending
- Evidence: Not due until 31 Mar 2027, after the latest results; later ones will show.
- Filing: <https://eqdoc.com/pdf/ann/7067562.pdf> (page 8)

## 2026-07-22 · Reach 40 GWh of energy storage capacity by 2030.: Pending

- Said: Energy Storage – Target of 40 GWh by 2030; 29.6 GWh Locked-in
- By: Company presentation, Investor presentation, 22 Jul 2026
- Due: by 2030
- Verdict: Pending
- Evidence: Not due until 31 Dec 2030, after the latest results; later ones will show.
- Filing: <https://eqdoc.com/pdf/ann/7067562.pdf> (page 24)

## 2026-07-22 · Reach an installed generation capacity of 30 GW by 2030.: Pending

- Said: Installed capacity to reach 30 GW by 2030, at CAGR of 17%
- By: Company presentation, Investor presentation, 22 Jul 2026
- Due: by 2030
- Verdict: Pending
- Evidence: Not due until 31 Dec 2030, after the latest results; later ones will show.
- Filing: <https://eqdoc.com/pdf/ann/7067562.pdf> (page 20)

## 2026-07-22 · The Chitradurga wind blade manufacturing facility will be commissioned by FY27.: Pending

- Said: The second facility, at Chitradurga, is expected to be commissioned by FY27, with work currently at an advanced stage.
- By: Sharad Mahendra, Q1 FY27 earnings call
- Due: by FY27
- Verdict: Pending
- Evidence: Not due until 31 Mar 2027, after the latest results; later ones will show.
- Filing: <https://eqdoc.com/pdf/ann/7084989.pdf> (page 5)

## 2026-07-22 · The company expects to deliver 3 GW of capacity addition and execute ₹20,000 crore capex in FY27.: Pending

- Said: We remain firmly on track to deliver our FY27 annual target of 3 GW capacity addition and ₹20,000 crore capex
- By: Sharad Mahendra, Q1 FY27 earnings call
- Due: FY27
- Verdict: Pending
- Evidence: Not due until 31 Mar 2027, after the latest results; later ones will show.
- Filing: <https://eqdoc.com/pdf/ann/7084989.pdf> (page 3)

## 2026-07-22 · The fourth 600 MW unit at KSK Mahanadi will be commissioned in FY28.: Pending

- Said: So we will be, as we have said, in FY28, the commissioning of the next fourth unit. We are on track for that
- By: Sharad Mahendra, Q1 FY27 earnings call
- Due: in FY28
- Verdict: Pending
- Evidence: Not due until 31 Mar 2028, after the latest results; later ones will show.
- Filing: <https://eqdoc.com/pdf/ann/7084989.pdf> (page 8)

## 2026-05-11 · The Halol blade manufacturing facility will be commissioned in the first half of FY27.: Pending

- Said: Additionally, our Blade manufacturing facility at Halol, scheduled for commissioning in the first half of FY27, would provide advantage to us in terms of lower capital cost
- By: Sharad Mahendra, Q4 FY26 earnings call
- Due: first half of FY27
- Verdict: Pending
- Evidence: Not due until 31 Mar 2027, after the latest results; later ones will show.
- Filing: <https://eqdoc.com/pdf/ann/6811327.pdf> (page 5)

## 2025-10-17 · The 150 MW Tidong Hydro Power Plant is projected to be commissioned by October 2026.: Unverifiable

- Said: Expected to be commissioned by October 2026, the plant has a 22-year Power Purchase Agreement (PPA) with Uttar Pradesh Power Corporation for 75 MW
- By: Sharad Mahendra, Q2 FY26 earnings call
- Due: October 2026
- Verdict: Unverifiable
- Evidence: We could not match this promise to a figure, and no later call settles it.
- Filing: <https://nsearchives.nseindia.com/corporate/RITESHJSWEL_22102025185628_TranscriptJSWELQ2.pdf> (page 6)

## 2025-07-31 · Both wind blade manufacturing plants will be commissioned in the current fiscal year (FY26).: Slipped

- Said: We are going to commission both the blade plants in the current fiscal.
- By: Sharad Mahendra, Q1 FY26 earnings call
- Due: current fiscal
- Verdict: Slipped
- Evidence: The Q4 FY26 call, 11 May 2026 settles it: “Additionally, our Blade manufacturing facility at Halol, scheduled for commissioning in the first half of FY27, would provide advantage to us in terms of lower capital cost”
- Filing: <https://nsearchives.nseindia.com/corporate/RITESHJSWEL_06082025214119_JSWELLettertoNSEBSESigned.pdf> (page 12)

## 2025-07-31 · JSW Energy will reach 30 GW of generation capacity by 2030.: Pending

- Said: And also, as we have announced, if you remember, 30 gigawatt by 2030 in our Strategy 3.0, and we have been maintaining for quite some time that 2/3 of green
- By: Sharad Mahendra, Q1 FY26 earnings call
- Due: 2030
- Verdict: Pending
- Evidence: Not due until 31 Dec 2030, after the latest results; later ones will show.
- Filing: <https://nsearchives.nseindia.com/corporate/RITESHJSWEL_06082025214119_JSWELLettertoNSEBSESigned.pdf> (page 14)

## 2025-07-31 · The company targets to add 3 to 4 GW of capacity during FY26.: Slipped

- Said: we are well-positioned to achieve our target of 3 to 4 GW of capacity addition during the current fiscal year.
- By: Sharad Mahendra, Q1 FY26 earnings call
- Due: current fiscal year
- Verdict: Slipped
- Evidence: The Q3 FY26 call, 23 Jan 2026 settles it: “And in the current quarter, the capacity additions, which are going to take place, we will be meeting the guidance what we have given for 1.5 GW in second half”
- Filing: <https://nsearchives.nseindia.com/corporate/RITESHJSWEL_06082025214119_JSWELLettertoNSEBSESigned.pdf> (page 7)

## 2025-07-31 · Trial runs for the battery energy storage assembly plant will start by the end of Q2 FY26.: Slipped

- Said: and we are confident that we will start the trial runs in this quarter, by the end of quarter 2 for this battery energy storage systems
- By: Sharad Mahendra, Q1 FY26 earnings call
- Due: by the end of quarter 2
- Verdict: Slipped
- Evidence: The Q2 FY26 call, 17 Oct 2025 settles it: “This facility, dedicated to supporting Battery Energy Storage Systems (BESS), is expected to be operational in Q3 FY26.”
- Filing: <https://nsearchives.nseindia.com/corporate/RITESHJSWEL_06082025214119_JSWELLettertoNSEBSESigned.pdf> (page 11)

## 2025-05-15 · The company expects to spend between Rs. 15,000 crores and Rs. 18,000 crores on capital expenditure in fiscal 2026.: Pending

- Said: For fiscal 2026, we are expecting to end up spending anything between Rs. 15,000 crores to Rs. 18,000 crores in that range to complete the ongoing projects
- By: Pritesh Vinay, Q4 FY25 earnings call
- Verdict: Pending
- Evidence: Not due until 31 Dec 2026, after the latest results; later ones will show.

## 2025-05-15 · The company plans to invest ₹1,30,000 crore in capital expenditure between FY26 and FY30.: Unverifiable

- Said: By FY30, we expect our EBITDA on a run-rate basis to grow 2.7x–3.0x over FY25 proforma EBITDA levels. To support this, we plan to invest ₹1,30,000 crore in capital expenditure
- By: Sharad Mahendra, Q4 FY25 earnings call
- Due: between FY26 and FY30
- Verdict: Unverifiable
- Evidence: We could not match this promise to a figure, and no later call settles it.

Live record: https://eqdoc.com/stock/JSWENERGY. Not investment advice.