type: "Promise Ledger"
title: "JSW Infrastructure Ltd: what management promised, and what happened"
description: "9 statements by JSW Infrastructure Ltd's management, each checked against the company's later filings: 2 slipped, 7 pending."
resource: "https://eqdoc.com/stock/JSWINFRA"
tags: ["promise ledger","management guidance","india","jswinfra"]
sources: [{"resource":"https://eqdoc.com/pdf/ann/7443404.pdf"},{"resource":"https://nsearchives.nseindia.com/corporate/JSWINFRA_05082026153730_IntimationSE_InvestorPresentation_Aug2026.pdf"},{"resource":"https://nsearchives.nseindia.com/corporate/JSWINFRA_21072026162737_SE_Investor_Result_Presentation.pdf"}]
generated: {"by":"process:eqdoc-promise-audit"}
x-eqdoc-symbol: "JSWINFRA"
x-eqdoc-counts: {"kept":0,"slipped":2,"missed":0,"pending":7,"unverifiable":0}
---

# How to read this

Each entry is something management said it would do, when it said it, and whether the company's later filings show it happened.
- **Kept**: a later filing shows it done. **Slipped**: done late or in part. **Missed**: the deadline passed without it.
- **Pending**: the deadline has not come, or no later filing yet speaks to it. **Unverifiable**: no filing could settle it.
- Evidence is either a sentence built from figures the company filed, or a quote from a later company document, as marked.

# Promises

## 2026-10-27 · Commence commercial operations at Keni Port in FY 2030.: Pending

- Said: Commercial operations are expected to commence in FY 2030
- By: Company presentation, Investor presentation, 27 Oct 2026
- Due: FY 2030
- Verdict: Pending
- Evidence: Not due until 31 Mar 2030, after the latest results; later ones will show.
- Filing: <https://eqdoc.com/pdf/ann/7443404.pdf> (page 23)

## 2026-10-27 · Complete Phase I construction at Jatadhar Port by March 2027.: Pending

- Said: Construction to be completed by March 2027
- By: Company presentation, Investor presentation, 27 Oct 2026
- Due: March 2027
- Verdict: Pending
- Evidence: Not due until 31 Mar 2027, after the latest results; later ones will show.
- Filing: <https://eqdoc.com/pdf/ann/7443404.pdf> (page 23)

## 2026-10-27 · Complete construction of the 7 MTPA bulk berth at V.O. Chidambaranar Port by Q4 FY27.: Pending

- Said: Expected completion by Q4 FY27
- By: Company presentation, Investor presentation, 27 Oct 2026
- Due: Q4 FY27
- Verdict: Pending
- Evidence: Not due until 31 Mar 2027, after the latest results; later ones will show.
- Filing: <https://eqdoc.com/pdf/ann/7443404.pdf> (page 21)

## 2026-10-27 · Complete the Kolkata Container Terminal project in Q3 FY28.: Pending

- Said: Expected completion in Q3 FY28
- By: Company presentation, Investor presentation, 27 Oct 2026
- Due: Q3 FY28
- Verdict: Pending
- Evidence: Not due until 31 Dec 2027, after the latest results; later ones will show.
- Filing: <https://eqdoc.com/pdf/ann/7443404.pdf> (page 21)

## 2026-10-27 · Scale rail rake fleet to 110 rakes by March 2027.: Pending

- Said: Targeting 110 rakes by Mar-27
- By: Company presentation, Investor presentation, 27 Oct 2026
- Due: Mar-27
- Verdict: Pending
- Evidence: Not due until 31 Mar 2027, after the latest results; later ones will show.
- Filing: <https://eqdoc.com/pdf/ann/7443404.pdf> (page 7)

## 2026-08-05 · Complete the 302 km slurry pipeline project in Odisha by March 2027.: Pending

- Said: Slurry Pipeline Project (30 mtpa) • 302KM Slurry pipeline in Odisha - Nuagaon to Jagatsinghpur • 256km of welding (85%) and 251km of lowering (83%) completed • Long term Take or Pay Agreement with JSW Steel in place • Estimated Capex - ₹4,000 Crore • Construction to be completed by March 2027
- By: Company presentation, Investor presentation, 5 Aug 2026
- Due: March 2027
- Verdict: Pending
- Evidence: Not due until 31 Mar 2027, after the latest results; later ones will show.
- Filing: <https://nsearchives.nseindia.com/corporate/JSWINFRA_05082026153730_IntimationSE_InvestorPresentation_Aug2026.pdf> (page 19)

## 2026-07-21 · Achieve consolidated operating revenue of ₹6,850 crore in FY27E.: Slipped

- Said: Operating Revenue (₹ Crore) 20% 28% 58% 4,476 5,361 6,850 10,800 FY25 FY26 FY27E FY28E
- By: Company presentation, Investor presentation, 21 Jul 2026
- Due: FY28E
- Verdict: Slipped (a second reading found it pending)
- Evidence: The Investor presentation, 27 Oct 2026 settles it: “Operating Revenue (₹ Crore) 20% 23% 64% CAGR (FY26-28) 42% 4,476 5,361 6,600 10,800 FY25 FY26 FY27E FY28E”
- Filing: <https://nsearchives.nseindia.com/corporate/JSWINFRA_21072026162737_SE_Investor_Result_Presentation.pdf> (page 17)

## 2026-07-21 · Complete the Jaigarh LPG terminal project during FY2027.: Slipped

- Said: Targeting completion during FY2027
- By: Company presentation, Investor presentation, 21 Jul 2026
- Due: FY2027
- Verdict: Slipped
- Evidence: The Investor presentation, 27 Oct 2026 settles it: “Marine operations in new berth to start by March 2027, subsequently tank terminals will be completed by December 2027”
- Filing: <https://nsearchives.nseindia.com/corporate/JSWINFRA_21072026162737_SE_Investor_Result_Presentation.pdf> (page 20)

## 2026-07-21 · Deliver consolidated operating EBITDA of ₹5,000 crore in FY28E.: Pending

- Said: Operating EBITDA (₹ Crore) 15% 15% 67% 2,262 2,604 3,000 5,000 FY25 FY26 FY27E FY28E
- By: Company presentation, Investor presentation, 21 Jul 2026
- Due: FY28E
- Verdict: Pending
- Evidence: Not due until 31 Mar 2028, after the latest results; later ones will show.
- Filing: <https://nsearchives.nseindia.com/corporate/JSWINFRA_21072026162737_SE_Investor_Result_Presentation.pdf> (page 17)

Live record: https://eqdoc.com/stock/JSWINFRA. Not investment advice.