type: "Promise Ledger"
title: "JSW Steel Ltd: what management promised, and what happened"
description: "9 statements by JSW Steel Ltd's management, each checked against the company's later filings: 8 pending, 1 unverifiable."
resource: "https://eqdoc.com/stock/JSWSTEEL"
tags: ["promise ledger","management guidance","india","jswsteel"]
sources: [{"resource":"https://eqdoc.com/pdf/ann/7433395.pdf"},{"resource":"https://nsearchives.nseindia.com/corporate/jessydenny_17072026161358_Analyst_Presentation.pdf"}]
generated: {"by":"process:eqdoc-promise-audit"}
x-eqdoc-symbol: "JSWSTEEL"
x-eqdoc-counts: {"kept":0,"slipped":0,"missed":0,"pending":8,"unverifiable":1}
---

# How to read this

Each entry is something management said it would do, when it said it, and whether the company's later filings show it happened.
- **Kept**: a later filing shows it done. **Slipped**: done late or in part. **Missed**: the deadline passed without it.
- **Pending**: the deadline has not come, or no later filing yet speaks to it. **Unverifiable**: no filing could settle it.
- Evidence is either a sentence built from figures the company filed, or a quote from a later company document, as marked.

# Promises

## 2026-10-23 · Commission the 0.55mtpa CRNO plant in Vijayanagar by March 2028.: Pending

- Said: 0.55mtpa CRNO plant in Vijayanagar • Equipment ordered. To be commissioned by March 2028
- By: Company presentation, Investor presentation, 23 Oct 2026
- Due: March 2028
- Verdict: Pending
- Evidence: Not due until 31 Mar 2028, after the latest results; later ones will show.
- Filing: <https://eqdoc.com/pdf/ann/7433395.pdf> (page 42)

## 2026-10-23 · Commission the 30mtpa Odisha slurry pipeline by March 2027.: Pending

- Said: 30mtpa Slurry Pipeline in Odisha (302km)1 • Progressing well; to be commissioned by Mar’27
- By: Company presentation, Investor presentation, 23 Oct 2026
- Due: Mar'27
- Verdict: Pending
- Evidence: Not due until 31 Mar 2027, after the latest results; later ones will show.
- Filing: <https://eqdoc.com/pdf/ann/7433395.pdf> (page 41)

## 2026-10-23 · Commission the Dolvi Phase-III expansion from 10 to 15mtpa by September 2027.: Pending

- Said: Dolvi Phase-III - Expansion from 10 to 15mtpa • Civil work and equipment erection underway • Project to be commissioned by Sep’27
- By: Company presentation, Investor presentation, 23 Oct 2026
- Due: Sep'27
- Verdict: Pending
- Evidence: Not due until 30 Sep 2027, after the latest results; later ones will show.
- Filing: <https://eqdoc.com/pdf/ann/7433395.pdf> (page 41)

## 2026-07-17 · Achieve consolidated crude steel production of 29.75mt and sales of 28.6mt in FY27.: Pending

- Said: Guidance of Total Consolidated Volumes for FY27: Production 29.75mt & Sales 28.6mt
- By: Company presentation, Investor presentation, 17 Jul 2026
- Due: FY27
- Verdict: Pending
- Evidence: Not due until 31 Mar 2027, after the latest results; later ones will show.
- Filing: <https://nsearchives.nseindia.com/corporate/jessydenny_17072026161358_Analyst_Presentation.pdf> (page 30)

## 2026-07-17 · Commission the 1mtpa EAF and structural mill at Kadapa by FY29.: Pending

- Said: 1mtpa EAF and Structural mill at Kadapa • Equipment ordered • To be commisioned by FY29
- By: Company presentation, Investor presentation, 17 Jul 2026
- Due: FY29
- Verdict: Pending
- Evidence: Not due until 31 Mar 2029, after the latest results; later ones will show.
- Filing: <https://nsearchives.nseindia.com/corporate/jessydenny_17072026161358_Analyst_Presentation.pdf> (page 43)

## 2026-07-17 · Commission the JSW Utkal blast furnace, SMS, and HSM-2 by FY30.: Pending

- Said: 5mtpa Blast Furnace, 6mtpa SMS and 6mtpa HSM-2: scheduled to be commissioned by FY30
- By: Company presentation, Investor presentation, 17 Jul 2026
- Due: FY30
- Verdict: Pending
- Evidence: Not due until 31 Mar 2030, after the latest results; later ones will show.
- Filing: <https://nsearchives.nseindia.com/corporate/jessydenny_17072026161358_Analyst_Presentation.pdf> (page 43)

## 2026-07-17 · Commission two 8mtpa pellet plants at JSW Utkal by FY28.: Pending

- Said: Two Pellet Plants (8mtpa each): scheduled to be commissioned by FY28
- By: Company presentation, Investor presentation, 17 Jul 2026
- Due: FY28
- Verdict: Pending
- Evidence: Not due until 31 Mar 2028, after the latest results; later ones will show.
- Filing: <https://nsearchives.nseindia.com/corporate/jessydenny_17072026161358_Analyst_Presentation.pdf> (page 43)

## 2026-07-17 · Spend between ₹22,000 crore and ₹24,000 crore on consolidated capex in FY27.: Pending

- Said: Capex spend for FY27 expected at ₹22,000-24,000 crore
- By: Company presentation, Investor presentation, 17 Jul 2026
- Due: FY27
- Verdict: Pending
- Evidence: Not due until 31 Mar 2027, after the latest results; later ones will show.
- Filing: <https://nsearchives.nseindia.com/corporate/jessydenny_17072026161358_Analyst_Presentation.pdf> (page 42)

## 2024-10-31 · The company held an earnings conference call following the board meeting.: Unverifiable

- Said: Transcripts of the Q2FY25 Earnings Conference Call conducted after the meeting of Board of Directors
- By: Lancy Varghese, Q2 FY25 earnings call
- Verdict: Unverifiable
- Evidence: We could not match this promise to a figure, and no later call settles it.

Live record: https://eqdoc.com/stock/JSWSTEEL. Not investment advice.