type: "Promise Ledger"
title: "Kanpur Plastipack Ltd: what management promised, and what happened"
description: "15 statements by Kanpur Plastipack Ltd's management, each checked against the company's later filings: 1 kept, 2 slipped, 9 pending, 3 unverifiable."
resource: "https://eqdoc.com/stock/KANPRPLA"
tags: ["promise ledger","management guidance","india","kanprpla"]
sources: [{"resource":"https://eqdoc.com/pdf/ann/7444912.pdf"},{"resource":"https://eqdoc.com/pdf/ann/7083453.pdf"},{"resource":"https://nsearchives.nseindia.com/corporate/KANPRPLA_25022026164934_Submission_Transcript_ConferenceCall.pdf"},{"resource":"https://nsearchives.nseindia.com/corporate/KANPRPLA_22082025173050_Submission_Transcript_ConferenceCall.pdf"}]
generated: {"by":"process:eqdoc-promise-audit"}
x-eqdoc-symbol: "KANPRPLA"
x-eqdoc-counts: {"kept":1,"slipped":2,"missed":0,"pending":9,"unverifiable":3}
---

# How to read this

Each entry is something management said it would do, when it said it, and whether the company's later filings show it happened.
- **Kept**: a later filing shows it done. **Slipped**: done late or in part. **Missed**: the deadline passed without it.
- **Pending**: the deadline has not come, or no later filing yet speaks to it. **Unverifiable**: no filing could settle it.
- Evidence is either a sentence built from figures the company filed, or a quote from a later company document, as marked.

# Promises

## 2026-10-27 · Commission the Needle Punching and Ironing Machine for the Non-Woven Fabrics Project by 15 November 2026.: Pending

- Said: The Needle Punching and Ironing Machine, received in August 2026, is expected to be commissioned by 15 November 2026.
- By: Company presentation, Investor presentation, 27 Oct 2026
- Due: 15 November 2026
- Verdict: Pending
- Evidence: Not due until 30 Nov 2026, after the latest results; later ones will show.
- Filing: <https://eqdoc.com/pdf/ann/7444912.pdf> (page 24)

## 2026-10-27 · Commission the second machine for the Non-Woven Fabrics Project by the end of March 2027.: Pending

- Said: Commissioning is expected by the end of March 2027.
- By: Company presentation, Investor presentation, 27 Oct 2026
- Due: end of March 2027
- Verdict: Pending
- Evidence: Not due until 31 Mar 2027, after the latest results; later ones will show.
- Filing: <https://eqdoc.com/pdf/ann/7444912.pdf> (page 24)

## 2026-10-27 · Complete Modern Roll Management System building construction by 15 November 2026.: Pending

- Said: Work is progressing in line with the revised schedule, with completion expected by 15 November 2026.
- By: Company presentation, Investor presentation, 27 Oct 2026
- Due: 15 November 2026
- Verdict: Pending
- Evidence: Not due until 30 Nov 2026, after the latest results; later ones will show.
- Filing: <https://eqdoc.com/pdf/ann/7444912.pdf> (page 24)

## 2026-10-27 · Complete construction of the new FIBC Division Unit 3 building by 30 October 2026.: Unverifiable

- Said: Construction of the new building is expected to be completed by 30 October 2026.
- By: Company presentation, Investor presentation, 27 Oct 2026
- Due: 30 October 2026
- Verdict: Unverifiable
- Evidence: We could not match this promise to a figure, and no later call settles it.
- Filing: <https://eqdoc.com/pdf/ann/7444912.pdf> (page 24)

## 2026-10-27 · Scale Premium PP Taslan Yarn revenue to INR 1,000 mn by FY30 with EBITDA margins of 20-25%.: Pending

- Said: Targeting revenue from INR 100 mn in FY27 to INR 1,000 mn in FY30, with EBITDA margin of 20-25%
- By: Company presentation, Investor presentation, 27 Oct 2026
- Due: FY30
- Verdict: Pending
- Evidence: Not due until 31 Mar 2030, after the latest results; later ones will show.
- Filing: <https://eqdoc.com/pdf/ann/7444912.pdf> (page 22)

## 2026-07-29 · The company expects annual savings of Rs. 3 to 5 crores from renewable energy.: Pending

- Said: What we are able to save annually is about close to Rs. 3 crores to Rs. 5 crores a year is what we are able to save annually.
- By: Shashank Agarwal, Q1 FY27 earnings call
- Verdict: Pending
- Evidence: Not due yet, so it can't be checked.

## 2026-07-29 · The non-woven fabric facility is scheduled to be commissioned by Q3 of 2026-27.: Pending

- Said: The Company remains on track to commission the non-woven fabric facility by Q3 of 2026-'27.
- By: Manoj Agarwal, Q1 FY27 earnings call
- Verdict: Pending
- Evidence: Not due until 31 Dec 2026, after the latest results; later ones will show.

## 2026-07-27 · Commission the Technical Textiles Nonwoven Fabrics facility by Q3 FY26-27.: Pending

- Said: we remain on track to commission the Technical Textiles - Nonwoven Fabrics facility by Q3 FY26-27
- By: Company presentation, Investor presentation, 27 Jul 2026
- Due: Q3 FY26-27
- Verdict: Pending
- Evidence: Not due until 31 Dec 2026, after the latest results; later ones will show.
- Filing: <https://eqdoc.com/pdf/ann/7083453.pdf> (page 19)

## 2026-07-27 · Complete construction of the modern automated roll management system by September 2026.: Slipped

- Said: Construction is on track and expected to be completed by September 2026
- By: Company presentation, Investor presentation, 27 Jul 2026
- Due: September 2026
- Verdict: Slipped
- Evidence: The Investor presentation, 27 Oct 2026 settles it: “Work is progressing in line with the revised schedule, with completion expected by 15 November 2026.”
- Filing: <https://eqdoc.com/pdf/ann/7083453.pdf> (page 13)

## 2026-07-27 · Complete the first and second floors for the FIBC Division capacity expansion by 15 September 2026.: Slipped

- Said: First and second floor are on track to be completed by 15th September 2026
- By: Company presentation, Investor presentation, 27 Jul 2026
- Due: 15th September 2026
- Verdict: Slipped
- Evidence: The Investor presentation, 27 Oct 2026 settles it: “Construction of the new building is expected to be completed by 30 October 2026.”
- Filing: <https://eqdoc.com/pdf/ann/7083453.pdf> (page 13)

## 2026-07-27 · Expand FIBC capacity by 6,000 MT per annum over the next 5 years.: Pending

- Said: Adds 6,000 MT p/a over the next 5 years.
- By: Company presentation, Investor presentation, 27 Jul 2026
- Due: over the next 5 years
- Verdict: Pending
- Evidence: Not due until 27 Jul 2031, after the latest results; later ones will show.
- Filing: <https://eqdoc.com/pdf/ann/7083453.pdf> (page 13)

## 2026-02-20 · The company expects Q4 manufacturing turnover to exceed Q3 levels.: Unverifiable

- Said: But yes Q4 will be better than Q3 in terms of the manufacturing turnover.
- By: Shashank Agarwal, Q3 FY26 earnings call
- Verdict: Unverifiable
- Evidence: We could not match this promise to a figure, and no later call settles it.
- Filing: <https://nsearchives.nseindia.com/corporate/KANPRPLA_25022026164934_Submission_Transcript_ConferenceCall.pdf> (page 11)

## 2026-02-20 · The company expects to increase total capacity to 24,000 tons upon completion of the expansion.: Pending

- Said: So we will move from a -- so the current capacity is at about 18,000 tons. So this will become 24,000 tons by the end of the expansion.
- By: Shashank Agarwal, Q3 FY26 earnings call
- Verdict: Pending
- Evidence: Not due yet, so it can't be checked.
- Filing: <https://nsearchives.nseindia.com/corporate/KANPRPLA_25022026164934_Submission_Transcript_ConferenceCall.pdf> (page 15)

## 2025-08-19 · The company expects its sustainable EBITDA margins to be between 9% and 10%.: Kept

- Said: So, the sustainable margin will remain between 9% to 10%.
- By: Shashank Agarwal, Q1 FY26 earnings call
- Verdict: Kept
- Evidence: Operating margin for the Mar 2026 quarter came to 11.2% — beat the top of the 9% to 10% promised, by 1.2 points.
- Filing: <https://nsearchives.nseindia.com/corporate/KANPRPLA_22082025173050_Submission_Transcript_ConferenceCall.pdf> (page 6)

## 2025-08-19 · The company expects to reduce its long-term debt to INR 15 crores by the end of the year.: Unverifiable

- Said: By end of this year, we should be in a position of having about INR15 crores of long-term debt and about INR110 crores of working capital limit.
- By: Shashank Agarwal, Q1 FY26 earnings call
- Verdict: Unverifiable
- Evidence: We could not match this promise to a figure, and no later call settles it.
- Filing: <https://nsearchives.nseindia.com/corporate/KANPRPLA_22082025173050_Submission_Transcript_ConferenceCall.pdf> (page 15)