# How to read this

Each entry is something management said it would do, when it said it, and whether the company's later filings show it happened.
- **Kept**: a later filing shows it done. **Slipped**: done late or in part. **Missed**: the deadline passed without it.
- **Pending**: the deadline has not come, or no later filing yet speaks to it. **Unverifiable**: no filing could settle it.
- Evidence is either a sentence built from figures the company filed, or a quote from a later company document, as marked.

# Promises

## 2025-02-12 · The company expects to generate between Rs. 600 crore and Rs. 700 crore in revenue during the fourth quarter of FY25.: Kept

- Said: we are quite hopeful like around Rs. 600 crores, Rs. 700 crores in Q4
- By: Atul Bohra, Q3 FY25 earnings call
- Verdict: Kept
- Evidence: Sales for the Mar 2025 quarter came to ₹719 cr — past the ₹600 cr promised.

## 2024-11-13 · The company estimates an EBITDA margin of 11% to 12% for the financial year FY25.: Missed

- Said: So at least for the financial year, we estimate around 11%, 12% is achievable number.
- By: Atul Bohra, Q2 FY25 earnings call
- Due: 2025-03-31
- Verdict: Missed
- Evidence: Operating margin for FY25 came to 10.2% — short of the 11% to 12% promised, with the window closed.

## 2024-11-13 · The company forecasts interest costs to be in the range of Rs. 70 to 80 crores for the full year FY25.: Unverifiable

- Said: Yes, Viraj, I think, as you mentioned, it is in the range of Rs. 70 crores, Rs. 80 crores. That's where we forecast.
- By: Atul Bohra, Q2 FY25 earnings call
- Verdict: Unverifiable
- Evidence: We could not match this promise to a figure, and no later call settles it.

## 2024-08-09 · The company expects to launch projects with a total GDV of Rs. 8,000 crore in FY25.: Slipped

- Said: The launch pipeline is largely on track and we are confident of launching project with the total GDV of Rs. 8,000 crore during the current financial year.
- By: Atul Bohra, Q1 FY25 earnings call
- Verdict: Slipped
- Evidence: The Q3 FY25 call, 12 Feb 2025 settles it: “We are hopeful of launching projects with the GDV of ~Rs. 5,000 crore in FY25.”

## 2024-08-09 · The company forecasts full-year revenue between Rs. 1,800 crore and Rs. 1,900 crore for FY25.: Missed

- Said: For the full financial year, we foresee at Rs. 1,800 crores to Rs. 1,900 crores, and EBITDA margin in the early teens.
- By: Atul Bohra, Q1 FY25 earnings call
- Verdict: Missed
- Evidence: Sales for FY25 came to ₹1,717 cr — short of the ₹1,800 cr promised, with the window closed.

Live record: https://eqdoc.com/stock/KOLTEPATIL. Not investment advice.