type: "Promise Ledger"
title: "Max Healthcare Institute Ltd: what management promised, and what happened"
description: "10 statements by Max Healthcare Institute Ltd's management, each checked against the company's later filings: 6 slipped, 1 missed, 1 pending, 2 unverifiable."
resource: "https://eqdoc.com/stock/MAXHEALTH"
tags: ["promise ledger","management guidance","india","maxhealth"]
sources: [{"resource":"https://nsearchives.nseindia.com/corporate/MAXHEALTH_20082026222821_SE_Intimation_Earnings_Call_Transcript.pdf"},{"resource":"https://nsearchives.nseindia.com/corporate/MAXHEALTH_12022026222827_SE_Intimation_Earnings_Call_Transcript.pdf"},{"resource":"https://nsearchives.nseindia.com/corporate/MAXHEALTH_21112025221010_SE_Intimation_Earnings_Call_Transcript.pdf"},{"resource":"https://nsearchives.nseindia.com/corporate/MAXHEALTH_27052025221348_SE_Intimation_Earnings_Call_Transcript.pdf"},{"resource":"https://nsearchives.nseindia.com/corporate/MAXHEALTH_13112024203321_SE_Intimation_Earnings_call_Transcript.pdf"}]
generated: {"by":"process:eqdoc-promise-audit"}
x-eqdoc-symbol: "MAXHEALTH"
x-eqdoc-counts: {"kept":0,"slipped":6,"missed":1,"pending":1,"unverifiable":2}
---

# How to read this

Each entry is something management said it would do, when it said it, and whether the company's later filings show it happened.
- **Kept**: a later filing shows it done. **Slipped**: done late or in part. **Missed**: the deadline passed without it.
- **Pending**: the deadline has not come, or no later filing yet speaks to it. **Unverifiable**: no filing could settle it.
- Evidence is either a sentence built from figures the company filed, or a quote from a later company document, as marked.

# Promises

## 2026-08-14 · Hand over the remaining 50% beds of Max Smart brownfield tower to operations during Q2 FY27.: Pending

- Said: The remaining 50% beds are expected to be handed over to operations during the course of the current quarter.
- By: Abhay Soi, Q1 FY27 earnings call
- Due: current quarter
- Verdict: Pending
- Evidence: Not due until 30 Sep 2026, after the latest results; later ones will show.
- Filing: <https://nsearchives.nseindia.com/corporate/MAXHEALTH_20082026222821_SE_Intimation_Earnings_Call_Transcript.pdf> (page 2)

## 2026-02-06 · Increase Max Lucknow capacity to around 500 beds by the end of FY26.: Missed

- Said: Max Lucknow – The current capacity of the hospital stands at 413 beds, and we expect this to increase to around 500 beds by the end of this financial year.
- By: Abhay Soi, Q3 FY26 earnings call
- Due: end of this financial year
- Verdict: Missed
- Evidence: The Q1 FY27 call, 14 Aug 2026 settles it: “Additional 100 beds in the existing 468-bed facility will be commissioned over the next two quarters.”
- Filing: <https://nsearchives.nseindia.com/corporate/MAXHEALTH_12022026222827_SE_Intimation_Earnings_Call_Transcript.pdf> (page 5)

## 2025-11-17 · Commission the Patparganj expansion project by FY28.: Slipped

- Said: The project is expected to be completed by FY '28.
- By: Abhay Soi, Q2 FY26 earnings call
- Due: FY '28
- Verdict: Slipped
- Evidence: The Q3 FY26 call, 6 Feb 2026 settles it: “397 beds at Patparganj – All approvals have been received and barricading work is complete. New design for D-wall has been firmed up and the project is now expected to be completed by FY '29.”
- Filing: <https://nsearchives.nseindia.com/corporate/MAXHEALTH_21112025221010_SE_Intimation_Earnings_Call_Transcript.pdf> (page 5)

## 2025-11-17 · Launch the onco radiation program at Max Lucknow within two weeks.: Unverifiable

- Said: The onco radiation program, including PET-CT, will be launched in the next two weeks.
- By: Abhay Soi, Q2 FY26 earnings call
- Due: next two weeks
- Verdict: Unverifiable
- Evidence: We could not match this promise to a figure, and no later call settles it.
- Filing: <https://nsearchives.nseindia.com/corporate/MAXHEALTH_21112025221010_SE_Intimation_Earnings_Call_Transcript.pdf> (page 5)

## 2025-05-21 · Commission the 500-bed facility at Sector 56 Gurgaon by end of calendar year 2025.: Slipped

- Said: 500 beds at Sector 56 Gurgaon: Structural work is in progress. We expect to commission the facility by end of this calendar year.
- By: Abhay Soi, Q4 FY25 earnings call
- Due: end of this calendar year
- Verdict: Slipped
- Evidence: The Q3 FY26 call, 6 Feb 2026 settles it: “500 beds at Sector-56, Gurgaon – The pace of work at site has picked up post GRAP-related disruptions. We now expect to commission the first phase by end of H1 FY '27.”
- Filing: <https://nsearchives.nseindia.com/corporate/MAXHEALTH_27052025221348_SE_Intimation_Earnings_Call_Transcript.pdf> (page 5)

## 2025-05-21 · Complete 155 beds at Mohali within 90 days of late May 2025.: Slipped

- Said: 155 beds at Mohali: Finishing work is underway and we expect to commission this facility within 90 days as well.
- By: Abhay Soi, Q4 FY25 earnings call
- Due: 90 days
- Verdict: Slipped
- Evidence: The Q3 FY26 call, 6 Feb 2026 settles it: “The remaining beds at both hospitals are expected to be commissioned during the Q4 FY '26.”
- Filing: <https://nsearchives.nseindia.com/corporate/MAXHEALTH_27052025221348_SE_Intimation_Earnings_Call_Transcript.pdf> (page 4)

## 2024-11-07 · Complete 268 beds at Nanavati Phase 1 by the end of FY25.: Unverifiable

- Said: For 268 beds at Nanavati in Phase 1, we have completed most of the structural work. The project continues to be on schedule and we expect completion by end of the financial year
- By: Abhay Soi, Q2 FY25 earnings call
- Due: end of the financial year
- Verdict: Unverifiable
- Evidence: We could not match this promise to a figure, and no later call settles it.
- Filing: <https://nsearchives.nseindia.com/corporate/MAXHEALTH_13112024203321_SE_Intimation_Earnings_call_Transcript.pdf> (page 4)

## 2024-11-07 · Complete 400 beds at Max Smart within Q1 FY26.: Slipped

- Said: For 400 beds at Max Smart, this project is on track. We expect its completion within Q1 FY26.
- By: Abhay Soi, Q2 FY25 earnings call
- Due: Q1 FY26
- Verdict: Slipped
- Evidence: The Q4 FY25 call, 21 May 2025 settles it: “400 beds at Max Smart (Saket Complex): Interior and MEP-fit-out works are ongoing. We expect to commission this facility latest by Q2 FY '26.”
- Filing: <https://nsearchives.nseindia.com/corporate/MAXHEALTH_13112024203321_SE_Intimation_Earnings_call_Transcript.pdf> (page 4)

## 2024-11-07 · Complete the first phase of 300 beds at Sector 56 Gurgaon by end of Q3 FY26.: Slipped

- Said: We expect completion of the first phase of 300 beds by end of Q3 FY26.
- By: Abhay Soi, Q2 FY25 earnings call
- Due: Q3 FY26
- Verdict: Slipped
- Evidence: The Q3 FY26 call, 6 Feb 2026 settles it: “500 beds at Sector-56, Gurgaon – The pace of work at site has picked up post GRAP-related disruptions. We now expect to commission the first phase by end of H1 FY '27.”
- Filing: <https://nsearchives.nseindia.com/corporate/MAXHEALTH_13112024203321_SE_Intimation_Earnings_call_Transcript.pdf> (page 4)

## 2024-11-07 · Finish additional 140 beds at Max Lucknow by December 2024.: Slipped

- Said: For capacity augmentation at Max Lucknow, finishing work for additional 140 beds is in progress and will be completed by December 2024
- By: Abhay Soi, Q2 FY25 earnings call
- Due: December 2024
- Verdict: Slipped
- Evidence: The Q3 FY25 call, 31 Jan 2025 settles it: “128 beds at Max Lucknow – 64 beds have been commissioned in January 2025, and the balance 64 beds will be added in February 2025.”
- Filing: <https://nsearchives.nseindia.com/corporate/MAXHEALTH_13112024203321_SE_Intimation_Earnings_call_Transcript.pdf> (page 4)

Live record: https://eqdoc.com/stock/MAXHEALTH. Not investment advice.