type: "Promise Ledger"
title: "Mazagon Dock Shipbuilders Ltd: what management promised, and what happened"
description: "14 statements by Mazagon Dock Shipbuilders Ltd's management, each checked against the company's later filings: 1 kept, 2 slipped, 9 pending, 2 unverifiable."
resource: "https://eqdoc.com/stock/MAZDOCK"
tags: ["promise ledger","management guidance","india","mazdock"]
sources: [{"resource":"https://eqdoc.com/pdf/ann/7443952.pdf"},{"resource":"https://eqdoc.com/pdf/ann/7293841.pdf"}]
generated: {"by":"process:eqdoc-promise-audit"}
x-eqdoc-symbol: "MAZDOCK"
x-eqdoc-counts: {"kept":1,"slipped":2,"missed":0,"pending":9,"unverifiable":2}
---

# How to read this

Each entry is something management said it would do, when it said it, and whether the company's later filings show it happened.
- **Kept**: a later filing shows it done. **Slipped**: done late or in part. **Missed**: the deadline passed without it.
- **Pending**: the deadline has not come, or no later filing yet speaks to it. **Unverifiable**: no filing could settle it.
- Evidence is either a sentence built from figures the company filed, or a quote from a later company document, as marked.

# Promises

## 2026-10-27 · Act as Anchor Shipyard for the proposed greenfield shipbuilding cluster at Dugarajapatnam in Andhra Pradesh.: Pending

- Said: MDL has signed an MoU with National Shipbuilding and Heavy Industries Park Andhra Pradesh to be the Anchor Shipyard for the proposed greenfield shipbuilding cluster at Dugarajapatnam
- By: Company presentation, Investor presentation, 27 Oct 2026
- Verdict: Pending
- Evidence: Not due yet, so it can't be checked.
- Filing: <https://eqdoc.com/pdf/ann/7443952.pdf> (page 14)

## 2026-10-27 · Anchor the development of a shipbuilding cluster with an envisaged investment of ~₹15,000 crore and 1.2 million GT annua: Pending

- Said: With an envisaged investment of ~₹15,000 crore and capacity of 1.2 million GT per annum, MDL will anchor the development of a globally competitive shipbuilding and marine ecosystem.
- By: Company presentation, Investor presentation, 27 Oct 2026
- Verdict: Pending
- Evidence: Not due yet, so it can't be checked.
- Filing: <https://eqdoc.com/pdf/ann/7443952.pdf> (page 14)

## 2026-10-27 · Participate as the Anchor Shipyard in the proposed greenfield shipbuilding cluster at Dighi, Maharashtra.: Pending

- Said: MDL has signed an MoU with National Shipbuilding & Heavy Industries Park Maharashtra Limited to participate as the Anchor Shipyard in the proposed Greenfield Shipbuilding Industrial Cluster at Dighi Maharashtra.
- By: Company presentation, Investor presentation, 27 Oct 2026
- Verdict: Pending
- Evidence: Not due yet, so it can't be checked.
- Filing: <https://eqdoc.com/pdf/ann/7443952.pdf> (page 15)

## 2026-09-23 · Develop a 37-acre greenfield shipyard facility at Nhava for larger ships and offshore platforms.: Pending

- Said: Nhava Greenfield Shipyard: 37-acre facility for larger ships/offshore platforms
- By: Company presentation, Investor presentation, 23 Sep 2026
- Verdict: Pending
- Evidence: Not due yet, so it can't be checked.
- Filing: <https://eqdoc.com/pdf/ann/7293841.pdf> (page 16)

## 2026-09-23 · Develop the 15-acre MbPA land at South Yard Annex to nearly double shipbuilding and refit capacity.: Pending

- Said: South Yard Annex: 15-acre MbPA land under development to nearly double shipbuilding and refit capacity
- By: Company presentation, Investor presentation, 23 Sep 2026
- Verdict: Pending
- Evidence: Not due yet, so it can't be checked.
- Filing: <https://eqdoc.com/pdf/ann/7293841.pdf> (page 16)

## 2026-09-23 · Execute phased replacement of eight vintage cranes.: Pending

- Said: 8 vintage cranes under phased replacement
- By: Company presentation, Investor presentation, 23 Sep 2026
- Verdict: Pending
- Evidence: Not due yet, so it can't be checked.
- Filing: <https://eqdoc.com/pdf/ann/7293841.pdf> (page 16)

## 2026-09-23 · Target completing construction of the 12,000T Floating Dry Dock by July 2026.: Unverifiable

- Said: 12,000T Floating Dry Dock under construction; target completion Jul’26
- By: Company presentation, Investor presentation, 23 Sep 2026
- Due: Jul’26
- Verdict: Unverifiable
- Evidence: We could not match this promise to a figure, and no later call settles it.
- Filing: <https://eqdoc.com/pdf/ann/7293841.pdf> (page 16)

## 2026-09-23 · Undertake capex for Submarine and Heavy Engineering division to construct a submarine launch facility and blasting paint: Pending

- Said: Undertaking capex for Submarine and Heavy Engineering division – construction of Submarine launch facility and blasting painting chamber
- By: Company presentation, Investor presentation, 23 Sep 2026
- Verdict: Pending
- Evidence: Not due yet, so it can't be checked.
- Filing: <https://eqdoc.com/pdf/ann/7293841.pdf> (page 24)

## 2025-10-28 · The company expects to maintain average margins of 15% or more.: Unverifiable

- Said: But on an average, we can anticipate around 15% plus margins.
- By: Capt. Jagmohan, Q2 FY26 earnings call
- Verdict: Unverifiable
- Evidence: We could not match this promise to a figure, and no later call settles it.

## 2025-10-28 · The company expects to sign the contract for three additional Scorpene submarines in the coming months.: Pending

- Said: We are still hopeful that in the coming months, we should be able to sign the contract for the three additional Scorpene Submarines.
- By: Capt. Jagmohan, Q2 FY26 earnings call
- Verdict: Pending
- Evidence: Not due yet, so it can't be checked.

## 2025-10-28 · The company projects revenue of approximately INR 12,500 crores for the current year (FY26).: Kept

- Said: We anticipate that this year, we will have revenue of approximately INR 12,500 crores or so. And the coming year also, we should have may be another 5% growth
- By: Capt. Jagmohan, Q2 FY26 earnings call
- Due: FY26
- Verdict: Kept
- Evidence: Sales for FY26 came to ₹13,006 cr — past the ₹12,500 cr promised.

## 2025-05-30 · The company expects to invoice approximately Rs. 24,000 crore of its order book over the next two years.: Pending

- Said: Out of the 32,000 crores, may be almost 24,000 across the next two years.
- By: Capt. Jagmohan, Q4 FY25 earnings call
- Verdict: Pending
- Evidence: Not due yet, so it can't be checked.

## 2024-11-05 · The company expects to deliver the sixth submarine before December 31st, 2024.: Slipped

- Said: We expect the delivery any time before 31st December.
- By: Sanjeev Singhal, Q2 FY25 earnings call
- Verdict: Slipped
- Evidence: The Q4 FY25 call, 30 May 2025 settles it: “The 4th ship will be the only one pending in the next financial year, that also we expect to deliver by April '26.”

## 2024-08-14 · The company is targeting three deliveries in FY25.: Slipped

- Said: we are targeting three deliveries. One for destroyer, which we plan before the contractual delivery schedule.
- By: Sanjeev Singhal, Q1 FY25 earnings call
- Due: in FY25
- Verdict: Slipped
- Evidence: The Q4 FY25 call, 30 May 2025 settles it: “The 4th ship will be the only one pending in the next financial year, that also we expect to deliver by April '26.”

Live record: https://eqdoc.com/stock/MAZDOCK. Not investment advice.