type: "Promise Ledger"
title: "Modis Navnirman Ltd: what management promised, and what happened"
description: "21 statements by Modis Navnirman Ltd's management, each checked against the company's later filings: 1 slipped, 1 missed, 15 pending, 4 unverifiable."
resource: "https://eqdoc.com/stock/MODIS"
tags: ["promise ledger","management guidance","india","modis"]
sources: [{"resource":"https://eqdoc.com/pdf/ann/7452758.pdf"},{"resource":"https://eqdoc.com/pdf/ann/7437245.pdf"},{"resource":"https://eqdoc.com/pdf/ann/7162502.pdf"},{"resource":"https://eqdoc.com/pdf/ann/7136035.pdf"},{"resource":"https://nsearchives.nseindia.com/corporate/MODIS_21052026115356_Transcript_Q4FY26sd.pdf"},{"resource":"https://nsearchives.nseindia.com/corporate/MODIS_20022026200349_MNL_2025_26_Q3_9Months_Conference_Transript-WCL-Outcome-output.pdf"}]
generated: {"by":"process:eqdoc-promise-audit"}
x-eqdoc-symbol: "MODIS"
x-eqdoc-counts: {"kept":0,"slipped":1,"missed":1,"pending":15,"unverifiable":4}
---

# How to read this

Each entry is something management said it would do, when it said it, and whether the company's later filings show it happened.
- **Kept**: a later filing shows it done. **Slipped**: done late or in part. **Missed**: the deadline passed without it.
- **Pending**: the deadline has not come, or no later filing yet speaks to it. **Unverifiable**: no filing could settle it.
- Evidence is either a sentence built from figures the company filed, or a quote from a later company document, as marked.

# Promises

## 2026-10-26 · Rashmi Paradise project is scheduled to launch on October 30th.: Unverifiable

- Said: Probably 30th of October is our planned date for launch. So, the project will be launched on that day.
- By: Mahek Modi, Q2 FY27 earnings call
- Due: 30th of October
- Verdict: Unverifiable
- Evidence: We could not match this promise to a figure, and no later call settles it.
- Filing: <https://eqdoc.com/pdf/ann/7452758.pdf> (page 10)

## 2026-10-24 · Complete the Rashmi Avenue project by 2027.: Pending

- Said: Rashmi Avenue Contemporary Living, Connected for More 18 Storey Building with 2 Wings Premium Residences Retail Spaces Project Year – Dec 2024 To be Completed – 2027
- By: Company presentation, Investor presentation, 24 Oct 2026
- Due: 2027
- Verdict: Pending
- Evidence: Not due until 31 Dec 2027, after the latest results; later ones will show.
- Filing: <https://eqdoc.com/pdf/ann/7437245.pdf> (page 30)

## 2026-10-24 · Complete the Rashmi Icon project by 2027.: Pending

- Said: Rashmi Icon A Landmark Address in the Heart of the City 22 Storey Building with 2 Wings Premium Residences Retail Spaces Project Year – Dec 2023 To be Completed – 2027
- By: Company presentation, Investor presentation, 24 Oct 2026
- Due: 2027
- Verdict: Pending
- Evidence: Not due until 31 Dec 2027, after the latest results; later ones will show.
- Filing: <https://eqdoc.com/pdf/ann/7437245.pdf> (page 29)

## 2026-10-24 · Complete the Rashmi Manorath project featuring 87 flats by 2027.: Pending

- Said: Rashmi Manorath 19 Storey Building with 87 Flats & 2 Podium Project Year – Jan 24 To be Completed – 2027
- By: Company presentation, Investor presentation, 24 Oct 2026
- Due: 2027
- Verdict: Pending
- Evidence: Not due until 31 Dec 2027, after the latest results; later ones will show.
- Filing: <https://eqdoc.com/pdf/ann/7437245.pdf> (page 27)

## 2026-10-24 · Deliver the 22-storey Rashmi Signature redevelopment project by 2027.: Pending

- Said: Rashmi Signature Redefine Luxury Living, Malad (W) 22 Storey Building with 3 Wings 208 Flats, 2 Podium Project Year – May 2024 To be Completed – 2027
- By: Company presentation, Investor presentation, 24 Oct 2026
- Due: 2027
- Verdict: Pending
- Evidence: Not due until 31 Dec 2027, after the latest results; later ones will show.
- Filing: <https://eqdoc.com/pdf/ann/7437245.pdf> (page 25)

## 2026-10-24 · Deliver the Rashmi Delight project by 2027.: Pending

- Said: Rashmi Delight 22 Storey Building with 63 Flats & 3 Shops with 4 Podium Project Year – Jan 25 To be Completed – 2027
- By: Company presentation, Investor presentation, 24 Oct 2026
- Due: 2027
- Verdict: Pending
- Evidence: Not due until 31 Dec 2027, after the latest results; later ones will show.
- Filing: <https://eqdoc.com/pdf/ann/7437245.pdf> (page 28)

## 2026-10-24 · Deliver the Rashmi Square development by 2027.: Pending

- Said: Rashmi Square Elegant Living, Borivali (W) 22 Storey Building with 2 Wings 133 Flats, 10 Shops, 3 Office, 2 Podium Project Year – Dec 23 To be Completed – 2027
- By: Company presentation, Investor presentation, 24 Oct 2026
- Due: 2027
- Verdict: Pending
- Evidence: Not due until 31 Dec 2027, after the latest results; later ones will show.
- Filing: <https://eqdoc.com/pdf/ann/7437245.pdf> (page 26)

## 2026-10-24 · Develop approximately 10.50 lakh square feet of upcoming projects.: Pending

- Said: 10.50 lakh sq. ft. upcoming
- By: Company presentation, Investor presentation, 24 Oct 2026
- Verdict: Pending
- Evidence: Not due yet, so it can't be checked.
- Filing: <https://eqdoc.com/pdf/ann/7437245.pdf> (page 7)

## 2026-08-10 · Rashmi Signature handover with OC pushed to the third quarter of FY27.: Pending

- Said: In FY -- in the third quarter, we'll be probably handing over with OC.
- By: Mahek Modi, Q1 FY27 earnings call
- Due: third quarter
- Verdict: Pending
- Evidence: Not due until 31 Mar 2027, after the latest results; later ones will show.
- Filing: <https://eqdoc.com/pdf/ann/7162502.pdf> (page 6)

## 2026-08-07 · Complete the Rashmi Delight project by 2027.: Pending

- Said: To be Completed : 2027
- By: Company presentation, Investor presentation, 7 Aug 2026
- Due: 2027
- Verdict: Pending
- Evidence: Not due until 31 Dec 2027, after the latest results; later ones will show.
- Filing: <https://eqdoc.com/pdf/ann/7136035.pdf> (page 24)

## 2026-08-07 · Complete the Rashmi Icon project by 2028.: Pending

- Said: To be Completed - 2028
- By: Company presentation, Investor presentation, 7 Aug 2026
- Due: 2028
- Verdict: Pending
- Evidence: Not due until 31 Dec 2028, after the latest results; later ones will show.
- Filing: <https://eqdoc.com/pdf/ann/7136035.pdf> (page 25)

## 2026-08-07 · Complete the Rashmi Manorath project by 2027.: Pending

- Said: To be Completed : 2027
- By: Company presentation, Investor presentation, 7 Aug 2026
- Due: 2027
- Verdict: Pending
- Evidence: Not due until 31 Dec 2027, after the latest results; later ones will show.
- Filing: <https://eqdoc.com/pdf/ann/7136035.pdf> (page 24)

## 2026-08-07 · Complete the Rashmi Signature project by 2027.: Pending

- Said: To be Completed : 2027
- By: Company presentation, Investor presentation, 7 Aug 2026
- Due: 2027
- Verdict: Pending
- Evidence: Not due until 31 Dec 2027, after the latest results; later ones will show.
- Filing: <https://eqdoc.com/pdf/ann/7136035.pdf> (page 24)

## 2026-08-07 · Complete the Rashmi Square project by 2027.: Pending

- Said: To be Completed : 2027
- By: Company presentation, Investor presentation, 7 Aug 2026
- Due: 2027
- Verdict: Pending
- Evidence: Not due until 31 Dec 2027, after the latest results; later ones will show.
- Filing: <https://eqdoc.com/pdf/ann/7136035.pdf> (page 24)

## 2026-05-21 · Complete Rashmi Square in four to six months.: Unverifiable

- Said: Now currently the project is at a completion stage where we are looking to complete it in the next four to five probably in the six months.
- By: Mahek Modi, Q4 FY26 earnings call
- Due: in the next four to five probably in the six months
- Verdict: Unverifiable
- Evidence: We could not match this promise to a figure, and no later call settles it.
- Filing: <https://nsearchives.nseindia.com/corporate/MODIS_21052026115356_Transcript_Q4FY26sd.pdf> (page 6)

## 2026-05-21 · Rashmi Paradise execution will start in Q1 or Q2 FY27.: Slipped

- Said: Rashmi Paradies in the quarter, in this quarter or the second quarter of this financial year we'll be starting execution.
- By: Mahek Modi, Q4 FY26 earnings call
- Due: this quarter or the second quarter of this financial year
- Verdict: Slipped
- Evidence: The Q2 FY27 call, 26 Oct 2026 settles it: “Probably 30th of October is our planned date for launch. So, the project will be launched on that day.”
- Filing: <https://nsearchives.nseindia.com/corporate/MODIS_21052026115356_Transcript_Q4FY26sd.pdf> (page 5)

## 2026-05-21 · Rashmi Signature is targeted to be handed over to the society in Q1 FY27.: Unverifiable

- Said: So we are targeting this project Rashmi Signature to be handed over to the society in the first quarter of '27
- By: Mahek Modi, Q4 FY26 earnings call
- Due: first quarter of '27
- Verdict: Unverifiable
- Evidence: We could not match this promise to a figure, and no later call settles it.
- Filing: <https://nsearchives.nseindia.com/corporate/MODIS_21052026115356_Transcript_Q4FY26sd.pdf> (page 4)

## 2026-05-21 · Target completing Rashmi Delight and Rashmi Manorath next year (FY27).: Pending

- Said: Rashmi Delight and Rashmi Manorath both are on the verge of half of completion, both the towers are getting completed and this we'll be targeting completion next year.
- By: Mahek Modi, Q4 FY26 earnings call
- Due: next year
- Verdict: Pending
- Evidence: Not due until 31 Mar 2027, after the latest results; later ones will show.
- Filing: <https://nsearchives.nseindia.com/corporate/MODIS_21052026115356_Transcript_Q4FY26sd.pdf> (page 4)

## 2026-02-17 · Full-year FY26 revenue will be around ₹180 crores.: Missed

- Said: See, so probably nine months our revenue has been INR137 crores so for 12 months we are targeting around INR180 crores of revenue.
- By: Mahek Modi, Q3 FY26 earnings call
- Due: for 12 months
- Verdict: Missed
- Evidence: Sales for the Mar 2026 quarter came to ₹51 cr — short of the ₹180 cr promised, with the window closed.
- Filing: <https://nsearchives.nseindia.com/corporate/MODIS_20022026200349_MNL_2025_26_Q3_9Months_Conference_Transript-WCL-Outcome-output.pdf> (page 11)

## 2026-02-17 · Maintain EBITDA margins in the bracket of 22% to 25%.: Unverifiable

- Said: Yes. More or less it is going to be the same. You can keep a bracket of 22% to 25%.
- By: Mahek Modi, Q3 FY26 earnings call
- Verdict: Unverifiable
- Evidence: We could not match this promise to a figure, and no later call settles it.
- Filing: <https://nsearchives.nseindia.com/corporate/MODIS_20022026200349_MNL_2025_26_Q3_9Months_Conference_Transript-WCL-Outcome-output.pdf> (page 14)

## 2026-02-17 · Targeting around ₹200 crores to ₹230 crores of revenue recognition in FY27.: Pending

- Said: FY '27 we are targeting around INR200 crores to INR225 crores, INRINR 230 crores of revenue recognition in the next year.
- By: Mahek Modi, Q3 FY26 earnings call
- Due: FY '27
- Verdict: Pending
- Evidence: Not due until 31 Mar 2027, after the latest results; later ones will show.
- Filing: <https://nsearchives.nseindia.com/corporate/MODIS_20022026200349_MNL_2025_26_Q3_9Months_Conference_Transript-WCL-Outcome-output.pdf> (page 11)

Live record: https://eqdoc.com/stock/MODIS. Not investment advice.