title: "Navin Fluorine International Ltd: what management promised, and what happened"
description: "32 statements by Navin Fluorine International Ltd's management, each checked against the company's later filings: 7 kept, 3 slipped, 19 pending, 3 unverifiable."
resource: "https://eqdoc.com/stock/NAVINFLUOR"
tags: ["promise ledger","management guidance","india","navinfluor"]
sources: [{"resource":"https://eqdoc.com/pdf/ann/7460076.pdf"},{"resource":"https://nsearchives.nseindia.com/corporate/NAVINFLUOR_07092026125352_SEupload.pdf"},{"resource":"https://eqdoc.com/pdf/ann/7121666.pdf"},{"resource":"https://nsearchives.nseindia.com/corporate/NAVINFLUOR_13022026111844_Binder1.pdf"},{"resource":"https://nsearchives.nseindia.com/corporate/NAVINFLUOR_04112025154604_Binder1_uplaod.pdf"},{"resource":"https://nsearchives.nseindia.com/corporate/NAVINFLUOR_28082025143022_Stock_Exchange_Intimation_03-09-2025signed.pdf"}]
generated: {"by":"process:eqdoc-promise-audit","at":"2026-10-07"}
stale_after: "2027-01-15"
x-eqdoc-symbol: "NAVINFLUOR"
x-eqdoc-counts: {"kept":7,"slipped":3,"missed":0,"pending":19,"unverifiable":3}
---

# How to read this

Each entry is something management said it would do, when it said it, and whether the company's later filings show it happened.
- **Kept**: a later filing shows it done. **Slipped**: done late or in part. **Missed**: the deadline passed without it.
- **Pending**: the deadline has not come, or no later filing yet speaks to it. **Unverifiable**: no filing could settle it.
- Evidence is either a sentence built from figures the company filed, or a quote from a later company document, as marked.

# Promises

## 2026-10-30 · Achieve 25% gender diversity across the Board by 2030.: Pending

- Said: 25% gender diversity across the Board by 2030
- By: Company presentation, Investor presentation, 30 Oct 2026
- Due: 2030
- Verdict: Pending
- Evidence: Not due until 31 Dec 2030, after the latest results; later ones will show.
- Filing: <https://eqdoc.com/pdf/ann/7460076.pdf> (page 26)

## 2026-10-30 · Achieve 50% use of renewable electricity by 2030.: Pending

- Said: 50% use of renewable electricity by 2030
- By: Company presentation, Investor presentation, 30 Oct 2026
- Due: 2030
- Verdict: Pending
- Evidence: Not due until 31 Dec 2030, after the latest results; later ones will show.
- Filing: <https://eqdoc.com/pdf/ann/7460076.pdf> (page 26)

## 2026-10-30 · Complete Advanced Materials adoption capacity capex of Rs 90 crores by Q2 FY28.: Pending

- Said: Capex of Rs. 90 Crs • Completion by Q2 FY28
- By: Company presentation, Investor presentation, 30 Oct 2026
- Due: Q2 FY28
- Verdict: Pending
- Evidence: Not due until 30 Sep 2027, after the latest results; later ones will show.
- Filing: <https://eqdoc.com/pdf/ann/7460076.pdf> (page 11)

## 2026-10-30 · Target a 30% reduction in carbon emissions by 2030 from base year 2023.: Pending

- Said: 30% reduction in carbon emissions by 2030 from the base year 2023
- By: Company presentation, Investor presentation, 30 Oct 2026
- Due: 2030
- Verdict: Pending
- Evidence: Not due until 31 Dec 2030, after the latest results; later ones will show.
- Filing: <https://eqdoc.com/pdf/ann/7460076.pdf> (page 26)

## 2026-09-07 · Advanced Materials capex completion: Pending

- Said: • Capex of Rs. 90 Crs • Completion by Q2 FY28
- Due: Q2 FY28
- Verdict: Pending
- Filing: <https://nsearchives.nseindia.com/corporate/NAVINFLUOR_07092026125352_SEupload.pdf>

## 2026-09-07 · Carbon emissions reduction target: Pending

- Said: 30% reduction in carbon emissions by 2030 from the base year 2023
- Due: 2030
- Verdict: Pending
- Filing: <https://nsearchives.nseindia.com/corporate/NAVINFLUOR_07092026125352_SEupload.pdf>

## 2026-09-07 · Chemours project completion: Pending

- Said: Chemours project is targeted for completion by end of Q2 FY27
- Due: Q2 FY27
- Verdict: Pending
- Filing: <https://nsearchives.nseindia.com/corporate/NAVINFLUOR_07092026125352_SEupload.pdf>

## 2026-09-07 · HFC capacity expansion commissioning: Pending

- Said: Capex for additional HFC capacity equivalent upto 15,000 MTPA of R32 is on track to be commissioned in Q3FY27
- Due: Q3 FY27
- Verdict: Pending
- Filing: <https://nsearchives.nseindia.com/corporate/NAVINFLUOR_07092026125352_SEupload.pdf>

## 2026-09-07 · MPP capacity debottlenecking commissioning: Pending

- Said: De-bottlenecking MPP capacity at Dahej is on track for commissioning in Q3 FY27
- Due: Q3 FY27
- Verdict: Pending
- Filing: <https://nsearchives.nseindia.com/corporate/NAVINFLUOR_07092026125352_SEupload.pdf>

## 2026-09-07 · Phase II cGMP4 capex operationalization: Pending

- Said: Phase II - cGMP4 capex of Rs. 125 Crs is expected to operationalize by Q4 FY27
- Due: Q4 FY27
- Verdict: Pending
- Filing: <https://nsearchives.nseindia.com/corporate/NAVINFLUOR_07092026125352_SEupload.pdf>

## 2026-08-05 · Chemours project targeted for completion by end of Q2 FY27.: Slipped

- Said: Chemours project is targeted for completion by end of Q2 FY27
- By: Company presentation, Investor presentation, 5 Aug 2026
- Due: end of Q2 FY27
- Verdict: Slipped
- Evidence: The Investor presentation, 30 Oct 2026 settles it: “Chemours project is targeted for completion by end of Q3 FY27; purchase orders are in place for delivery during Q4 FY27”
- Filing: <https://eqdoc.com/pdf/ann/7121666.pdf> (page 7)

## 2026-08-05 · Commission capex for additional HFC capacity up to 15,000 MTPA of R32 in Q3 FY27.: Pending

- Said: Capex for additional HFC capacity equivalent upto 15,000 MTPA of R32 is on track to be commissioned in Q3FY27
- By: Company presentation, Investor presentation, 5 Aug 2026
- Due: Q3FY27
- Verdict: Pending
- Evidence: Not due until 31 Dec 2026, after the latest results; later ones will show.
- Filing: <https://eqdoc.com/pdf/ann/7121666.pdf> (page 6)

## 2026-08-05 · Commission de-bottlenecking of MPP capacity at Dahej in Q3 FY27.: Pending

- Said: De-bottlenecking MPP capacity at Dahej is on track for commissioning in Q3 FY27
- By: Company presentation, Investor presentation, 5 Aug 2026
- Due: Q3 FY27
- Verdict: Pending
- Evidence: Not due until 31 Dec 2026, after the latest results; later ones will show.
- Filing: <https://eqdoc.com/pdf/ann/7121666.pdf> (page 7)

## 2026-08-05 · Operationalize Phase II cGMP4 capex of Rs 125 crores by Q4 FY27.: Pending

- Said: Initiated today, Phase II - cGMP4 capex of Rs. 125 Crs is expected to operationalize by Q4 FY27
- By: Company presentation, Investor presentation, 5 Aug 2026
- Due: Q4 FY27
- Verdict: Pending
- Evidence: Not due until 31 Mar 2027, after the latest results; later ones will show.
- Filing: <https://eqdoc.com/pdf/ann/7121666.pdf> (page 8)

## 2026-02-13 · Annualized EBITDA margin target: Pending

- Said: So it will be an annualized number that we are looking at 30% give or take plus/minus 200 basis points.
- Verdict: Pending
- Filing: <https://nsearchives.nseindia.com/corporate/NAVINFLUOR_13022026111844_Binder1.pdf>

## 2026-02-13 · Chemours Project completion timeline: Slipped

- Said: On the Project front, the Chemours Project is progressing well and is on track for completion in Q1 FY27.
- Due: 2026-06-30
- Verdict: Slipped
- Later filing says (2026-08-11): Chemours project, which also form a part of this vertical is targeted for completion by end of Q2 FY '27.
- Filing: <https://nsearchives.nseindia.com/corporate/NAVINFLUOR_13022026111844_Binder1.pdf>

## 2026-02-13 · MPP capacity debottlenecking commissioning: Pending

- Said: Further, the de-bottlenecking of MPP capacity at our Dahej facility is expected to be commissioned in Q3 FY27, which will further enhance our capabilities.
- Due: 2026-12-31
- Verdict: Pending
- Filing: <https://nsearchives.nseindia.com/corporate/NAVINFLUOR_13022026111844_Binder1.pdf>

## 2026-02-13 · R32 HFC capacity commissioning timeline: Pending

- Said: Additionally, the CAPEX for incremental HFC capacity equivalent up to 15,000 MTPA of R32 is progressing as planned and is expected to be commissioned in Q3 FY27.
- Due: 2026-12-31
- Verdict: Pending
- Filing: <https://nsearchives.nseindia.com/corporate/NAVINFLUOR_13022026111844_Binder1.pdf>

## 2026-02-13 · cGMP-4 Phase-1 plant full utilization: Pending

- Said: Within the year…in FY27, you will see full optimum utilization.
- Due: FY27
- Verdict: Pending
- Filing: <https://nsearchives.nseindia.com/corporate/NAVINFLUOR_13022026111844_Binder1.pdf>

## 2026-02-09 · The company targets an annual EBITDA margin of 30%.: Kept

- Said: On the margin, I think, we have always said 25%. I think it is now safe to think of Navin as a 30% annual number.
- By: Anish Ganatra, Q3 FY26 earnings call
- Verdict: Kept
- Evidence: Operating margin for FY26 came to 32.6% — past the 30% promised.

## 2025-10-30 · The company expects EBITDA margins to be between 28% and 30% for the full fiscal year FY26.: Kept

- Said: we are well on track to be between 28% to 30% for the year.
- By: Anish Ganatra, Q2 FY26 earnings call
- Due: 2026-03-31
- Verdict: Kept
- Evidence: Operating margin for FY26 came to 32.6% — beat the top of the 28% to 30% promised, by 2.6 points.
- Filing: <https://nsearchives.nseindia.com/corporate/NAVINFLUOR_04112025154604_Binder1_uplaod.pdf> (page 7)

## 2025-10-30 · The company expects total cash outflow for capex to be between INR 600 and 700 crores for the year FY26.: Unverifiable

- Said: It will be within the range of that INR700 crores -- INR600 crores, INR700 crores for the year in terms of cash outflow
- By: Anish Ganatra, Q2 FY26 earnings call
- Verdict: Unverifiable
- Evidence: We could not match this promise to a figure, and no later call settles it.
- Filing: <https://nsearchives.nseindia.com/corporate/NAVINFLUOR_04112025154604_Binder1_uplaod.pdf> (page 7)

## 2025-08-28 · AHF Dahej capex commissioning: Slipped

- Said: AHF capex for Rs. 450 crore at Dahej is expected to commission by end Q2 FY26
- Due: Q2 FY26
- Verdict: Slipped
- Later filing says (2026-08-17): AHF facility commenced operations in Q4 FY26 and continues to be ramped up
- Filing: <https://nsearchives.nseindia.com/corporate/NAVINFLUOR_28082025143022_Stock_Exchange_Intimation_03-09-2025signed.pdf>

## 2025-08-28 · CDMO EU order delivery: Kept

- Said: EU Major – Material order received for supply in Q2FY26
- Due: Q2 FY26
- Verdict: Kept
- Later filing says (2026-02-03): EU Major – Supplies concluded for the material order in Q2 FY26 and in discussion for the future supplies
- Filing: <https://nsearchives.nseindia.com/corporate/NAVINFLUOR_28082025143022_Stock_Exchange_Intimation_03-09-2025signed.pdf>

## 2025-08-28 · CDMO commercial order delivery: Pending

- Said: US Major – Commercial order expected for delivery in FY26
- Due: FY26
- Verdict: Pending
- Filing: <https://nsearchives.nseindia.com/corporate/NAVINFLUOR_28082025143022_Stock_Exchange_Intimation_03-09-2025signed.pdf>

## 2025-08-28 · CDMO scale up order: Kept

- Said: Another EU Major – Scale up order expected in Q2FY26
- Due: Q2 FY26
- Verdict: Kept
- Later filing says (2026-02-03): Another EU Major – Scale up order received for supplies in Q3 & Q4 FY26
- Filing: <https://nsearchives.nseindia.com/corporate/NAVINFLUOR_28082025143022_Stock_Exchange_Intimation_03-09-2025signed.pdf>

## 2025-08-28 · Molecules supply launch: Pending

- Said: Supplies for 3 new molecules to start in Q2FY26; Orders are in place
- Due: Q2 FY26
- Verdict: Pending
- Filing: <https://nsearchives.nseindia.com/corporate/NAVINFLUOR_28082025143022_Stock_Exchange_Intimation_03-09-2025signed.pdf>

## 2025-08-28 · cGMP4 Phase 1 capex commissioning: Kept

- Said: cGMP4 capex for Rs. 288 crore – Phase 1 capex of Rs. 160 crore on track to commission by end of Q3FY26
- Due: Q3 FY26
- Verdict: Kept
- Later filing says (2026-08-17): Phase I capex operationalized in Q3 FY26. Initiated today, Phase II - cGMP4 capex of Rs. 125 Crs is expected to operationalize by Q4 FY27
- Filing: <https://nsearchives.nseindia.com/corporate/NAVINFLUOR_28082025143022_Stock_Exchange_Intimation_03-09-2025signed.pdf>

## 2025-01-30 · The company expects to exit FY '25 with an EBITDA margin of approximately 25%.: Kept

- Said: we've indicated that we would exit FY '25 near 25% or at 25%.
- By: Anish Ganatra, Q3 FY25 earnings call
- Due: 2025-03-31
- Verdict: Kept
- Evidence: Operating margin for the Mar 2025 quarter came to 25.5% — past the 25% promised.

## 2024-07-30 · The R32 capacity expansion is scheduled for completion by February 2025.: Unverifiable

- Said: Additional R32 CAPEX of Rs. 84 crores to boost capacity by 4,500 tonnes is on track for completion by February 2025.
- By: Vishad Mafatlal, Q1 FY25 earnings call
- Due: 2025-02-28
- Verdict: Unverifiable
- Evidence: We could not match this promise to a figure, and no later call settles it.

## 2024-07-30 · The agro-specialty project is scheduled to begin commercial production by September.: Unverifiable

- Said: Our agro-specialty project with a CAPEX of Rs. 540 crores is targeted to commence commercial production by September.
- By: Vishad Mafatlal, Q1 FY25 earnings call
- Verdict: Unverifiable
- Evidence: We could not match this promise to a figure, and no later call settles it.

## 2024-07-30 · The new capability in Surat is planned to be commissioned during the second quarter of Financial Year 2025.: Kept

- Said: The Rs. 30 crores CAPEX for development of new capability in Surat, which is progressing as planned to be commissioned during quarter 2 Financial Year 2025.
- By: Vishad Mafatlal, Q1 FY25 earnings call
- Due: during the second quarter of Financial Year 2025
- Verdict: Kept
- Evidence: The Q2 FY25 call, 23 Oct 2024 settles it: “Simultaneously, our Surat project with an outlay of INR30 crores is commissioned, and the first dispatch will be in November 2024.”

Live record: https://eqdoc.com/stock/NAVINFLUOR. Not investment advice.