type: "Promise Ledger"
title: "NHPC Ltd: what management promised, and what happened"
description: "7 statements by NHPC Ltd's management, each checked against the company's later filings: 2 slipped, 1 missed, 4 pending."
resource: "https://eqdoc.com/stock/NHPC"
tags: ["promise ledger","management guidance","india","nhpc"]
sources: [{"resource":"https://nsearchives.nseindia.com/corporate/NHPC_12022026183633_STX_Transcript_Concall_12022026.pdf"}]
generated: {"by":"process:eqdoc-promise-audit"}
x-eqdoc-symbol: "NHPC"
x-eqdoc-counts: {"kept":0,"slipped":2,"missed":1,"pending":4,"unverifiable":0}
---

# How to read this

Each entry is something management said it would do, when it said it, and whether the company's later filings show it happened.
- **Kept**: a later filing shows it done. **Slipped**: done late or in part. **Missed**: the deadline passed without it.
- **Pending**: the deadline has not come, or no later filing yet speaks to it. **Unverifiable**: no filing could settle it.
- Evidence is either a sentence built from figures the company filed, or a quote from a later company document, as marked.

# Promises

## 2026-08-05 · The company will report its unaudited financial results for the quarter ending June 30, 2026.: Pending

- Said: The Board of Directors in its meeting held on Tuesday, August 04, 2026 had inter-alia approved the unaudited financial results (Standalone and Consolidated) of the Company for the quarter ended on 30th June, 2026.
- By: Company presentation, Investor presentation, 5 Aug 2026
- Verdict: Pending
- Evidence: Not due until 30 Jun 2030, after the latest results; later ones will show.

## 2026-02-06 · The company expects to add 2,744 MW of hydro capacity next year.: Pending

- Said: Next year, our capacity addition will be 2744 MW from hydro.
- By: Saroj Kumar Roy, Q3 FY26 earnings call
- Verdict: Pending
- Evidence: Not due yet, so it can't be checked.
- Filing: <https://nsearchives.nseindia.com/corporate/NHPC_12022026183633_STX_Transcript_Concall_12022026.pdf> (page 10)

## 2026-02-06 · The company plans to commission the remaining four units of the Subansiri Lower Project by December 2026.: Pending

- Said: We are targeting to commission all the remaining four units by December'26.
- By: Bhupender Gupta, Q3 FY26 earnings call
- Due: by December 2026
- Verdict: Pending
- Evidence: Not due until 31 Dec 2026, after the latest results; later ones will show.
- Filing: <https://nsearchives.nseindia.com/corporate/NHPC_12022026183633_STX_Transcript_Concall_12022026.pdf> (page 4)

## 2026-02-06 · The company plans to spend Rs. 15,000 Crore on capital expenditure in the next fiscal year.: Pending

- Said: The CAPEX plan for the current fiscal year is Rs. 13,300 Crore and next year, we are planning to spend Rs. 15,000 Crore.
- By: Saroj Kumar Roy, Q3 FY26 earnings call
- Verdict: Pending
- Evidence: Not due yet, so it can't be checked.
- Filing: <https://nsearchives.nseindia.com/corporate/NHPC_12022026183633_STX_Transcript_Concall_12022026.pdf> (page 9)

## 2024-11-08 · The 200 MW Grid Connected Solar Power Project at Khavda is expected to be commissioned by August 2025.: Slipped

- Said: The project is expected to be commissioned by August'25.
- By: R.K. Chaudhary, Q2 FY25 earnings call
- Due: by August 2025
- Verdict: Slipped
- Evidence: The Q4 FY25 call, 21 May 2025 settles it: “The project is expected to be commissioned by March’26.”

## 2024-11-08 · The company aims to complete the Parbati-II project and commission it by February 2025.: Missed

- Said: We are trying our best to complete the remaining overt lining and invert lining of HRT and commission the project by February'25.
- By: R.K. Chaudhary, Q2 FY25 earnings call
- Due: by February 2025
- Verdict: Missed
- Evidence: The Q4 FY25 call, 21 May 2025 settles it: “the project is scheduled to be commissioned by December’27.”

## 2024-11-08 · The company expects to commission three units of the Subansiri Lower project by March 2025.: Slipped

- Said: We are very hopeful that we can commission three units of the project by March'25 and rest of the units one by one by May'26.
- By: R.K. Chaudhary, Q2 FY25 earnings call
- Due: by March 2025
- Verdict: Slipped
- Evidence: The Q4 FY25 call, 21 May 2025 settles it: “We are very hopeful of commissioning 5 units of the project in the current financial year and rest of the units by May’26.”

Live record: https://eqdoc.com/stock/NHPC. Not investment advice.