type: "Promise Ledger"
title: "Pace Digitek Ltd: what management promised, and what happened"
description: "10 statements by Pace Digitek Ltd's management, each checked against the company's later filings: 1 slipped, 6 pending, 3 unverifiable."
resource: "https://eqdoc.com/stock/PACEDIGITK"
tags: ["promise ledger","management guidance","india","pacedigitk"]
sources: [{"resource":"https://eqdoc.com/pdf/ann/7466711.pdf"},{"resource":"https://eqdoc.com/pdf/ann/7197692.pdf"}]
generated: {"by":"process:eqdoc-promise-audit"}
x-eqdoc-symbol: "PACEDIGITK"
x-eqdoc-counts: {"kept":0,"slipped":1,"missed":0,"pending":6,"unverifiable":3}
---

# How to read this

Each entry is something management said it would do, when it said it, and whether the company's later filings show it happened.
- **Kept**: a later filing shows it done. **Slipped**: done late or in part. **Missed**: the deadline passed without it.
- **Pending**: the deadline has not come, or no later filing yet speaks to it. **Unverifiable**: no filing could settle it.
- Evidence is either a sentence built from figures the company filed, or a quote from a later company document, as marked.

# Promises

## 2026-10-31 · Achieve revised FY27 revenue guidance of Rs. 3,300 crore to Rs. 3,500 crore.: Pending

- Said: FY27E Rs. 3,300 – 3,500 Cr (Revised from Rs. 3,200 - 3,400 Cr)
- By: Company presentation, Investor presentation, 31 Oct 2026
- Due: FY27
- Verdict: Pending
- Evidence: Not due until 31 Mar 2027, after the latest results; later ones will show.
- Filing: <https://eqdoc.com/pdf/ann/7466711.pdf> (page 15)

## 2026-10-31 · Commence trial production of in-house BESS containers in November 2026, scaling to full production by January 2027.: Pending

- Said: Trial production is scheduled to commence in November 2026, with full-scale production targeted from January 2027.
- By: Company presentation, Investor presentation, 31 Oct 2026
- Due: January 2027
- Verdict: Pending
- Evidence: Not due until 30 Nov 2026, after the latest results; later ones will show.
- Filing: <https://eqdoc.com/pdf/ann/7466711.pdf> (page 10)

## 2026-10-31 · Commission Line 3 (5 GWh) by December 2026.: Pending

- Said: Line 3 (5 GWh) is under implementation, with commissioning targeted by December 2026.
- By: Company presentation, Investor presentation, 31 Oct 2026
- Due: December 2026
- Verdict: Pending
- Evidence: Not due until 31 Dec 2026, after the latest results; later ones will show.
- Filing: <https://eqdoc.com/pdf/ann/7466711.pdf> (page 10)

## 2026-08-19 · Commercialize C&I energy storage prototype solutions starting from Q2 FY27.: Unverifiable

- Said: Developed C&I energy storage prototype solutions with commercialization planned from Q2 FY27
- By: Company presentation, Investor presentation, 19 Aug 2026
- Due: Q2 FY27
- Verdict: Unverifiable
- Evidence: We could not match this promise to a figure, and no later call settles it.
- Filing: <https://eqdoc.com/pdf/ann/7197692.pdf> (page 11)

## 2026-08-19 · Commission the in-house container fabrication facility in August 2026.: Slipped

- Said: In-house container fabrication facility ready for commissioning in August 2026
- By: Company presentation, Investor presentation, 19 Aug 2026
- Due: August 2026
- Verdict: Slipped
- Evidence: The Investor presentation, 31 Oct 2026 settles it: “Trial production is scheduled to commence in November 2026, with full-scale production targeted from January 2027.”
- Filing: <https://eqdoc.com/pdf/ann/7197692.pdf> (page 15)

## 2026-08-19 · Deliver FY27 revenue of ₹32,000 to ₹34,000 million (₹3,200 to ₹3,400 crore).: Pending

- Said: FY27E ₹32,000 – 34,000 mn
- By: Company presentation, Investor presentation, 19 Aug 2026
- Due: FY27
- Verdict: Pending
- Evidence: Not due until 31 Mar 2027, after the latest results; later ones will show.
- Filing: <https://eqdoc.com/pdf/ann/7197692.pdf> (page 27)

## 2026-08-19 · Deliver FY28 revenue of ₹40,000 to ₹42,000 million.: Pending

- Said: FY28E ₹40,000 – 42,000 mn
- By: Company presentation, Investor presentation, 19 Aug 2026
- Due: FY28
- Verdict: Pending
- Evidence: Not due until 31 Mar 2028, after the latest results; later ones will show.
- Filing: <https://eqdoc.com/pdf/ann/7197692.pdf> (page 27)

## 2026-08-19 · Operationalize an additional 2.5 GWh manufacturing line in August 2026.: Unverifiable

- Said: Additional 2.5 GWh manufacturing line operational in August 2026
- By: Company presentation, Investor presentation, 19 Aug 2026
- Due: August 2026
- Verdict: Unverifiable
- Evidence: We could not match this promise to a figure, and no later call settles it.
- Filing: <https://eqdoc.com/pdf/ann/7197692.pdf> (page 15)

## 2026-08-19 · Operationalize the new 5 GWh facility by Q3 FY27.: Pending

- Said: Expected to be operational by Q3 FY27
- By: Company presentation, Investor presentation, 19 Aug 2026
- Due: Q3 FY27
- Verdict: Pending
- Evidence: Not due until 31 Dec 2026, after the latest results; later ones will show.
- Filing: <https://eqdoc.com/pdf/ann/7197692.pdf> (page 15)

## 2026-08-19 · Receive machines for the new 5 GWh facility by October 2026.: Unverifiable

- Said: Machines expected to receive by October 2026
- By: Company presentation, Investor presentation, 19 Aug 2026
- Due: October 2026
- Verdict: Unverifiable
- Evidence: We could not match this promise to a figure, and no later call settles it.
- Filing: <https://eqdoc.com/pdf/ann/7197692.pdf> (page 15)

Live record: https://eqdoc.com/stock/PACEDIGITK. Not investment advice.