type: "Promise Ledger"
title: "Petronet LNG Ltd: what management promised, and what happened"
description: "25 statements by Petronet LNG Ltd's management, each checked against the company's later filings: 2 kept, 6 slipped, 3 missed, 11 pending, 3 unverifiable."
resource: "https://eqdoc.com/stock/PETRONET"
tags: ["promise ledger","management guidance","india","petronet"]
sources: [{"resource":"https://nsearchives.nseindia.com/corporate/PETRONET_20022026110925_intimationtranscript2.pdf"},{"resource":"https://nsearchives.nseindia.com/corporate/PETRONET_04022025123513_intimationtranscriptsigned1.pdf"},{"resource":"https://nsearchives.nseindia.com/corporate/PETRONET_05022024174823_intimationtranscriptsigned.pdf"}]
generated: {"by":"process:eqdoc-promise-audit","at":"2026-10-07"}
stale_after: "2027-01-15"
x-eqdoc-symbol: "PETRONET"
x-eqdoc-counts: {"kept":2,"slipped":6,"missed":3,"pending":11,"unverifiable":3}
---

# How to read this

Each entry is something management said it would do, when it said it, and whether the company's later filings show it happened.
- **Kept**: a later filing shows it done. **Slipped**: done late or in part. **Missed**: the deadline passed without it.
- **Pending**: the deadline has not come, or no later filing yet speaks to it. **Unverifiable**: no filing could settle it.
- Evidence is either a sentence built from figures the company filed, or a quote from a later company document, as marked.

# Promises

## 2026-02-20 · Dahej expansion mechanical completion: Pending

- Said: So 31st March is our target to complete its -- mechanical completion.
- Due: 2026-03-31
- Verdict: Pending
- Filing: <https://nsearchives.nseindia.com/corporate/PETRONET_20022026110925_intimationtranscript2.pdf>

## 2026-02-20 · Dahej terminal capacity ramp-up: Kept

- Said: Dahej terminal, the present capacity is 17.5 MMTPA, and we are ramping it up to 22.5 MMTPA by the end of this financial year.
- Due: FY26
- Verdict: Kept
- Later filing says (2026-08-19): For the current quarter, the nameplate capacity of Dahej increased from 17.5 MMTPA to 22.5 MMTPA.
- Filing: <https://nsearchives.nseindia.com/corporate/PETRONET_20022026110925_intimationtranscript2.pdf>

## 2026-02-20 · FY26 and FY27 Capex targets: Pending

- Said: we will be restricting our capex during the year around INR3,000 crores. So next year, we are targeting to spend around INR9,000 crores.
- Due: FY27
- Verdict: Pending
- Filing: <https://nsearchives.nseindia.com/corporate/PETRONET_20022026110925_intimationtranscript2.pdf>

## 2026-02-20 · Kochi Bangalore pipeline connectivity: Missed

- Said: GAIL has been still maintaining March 2026, but we believe by June 2026, we should be connected to natural gas to Kochi, Kuttanad, Bangalore, Mangalore pipeline.
- Due: 2026-06-30
- Verdict: Missed
- Later filing says (2026-08-19): as far as the latest information that we have, it's still in the by the end of this quarter it should be mechanically completed.
- Filing: <https://nsearchives.nseindia.com/corporate/PETRONET_20022026110925_intimationtranscript2.pdf>

## 2026-02-20 · Petrochemical project capex outflow: Pending

- Said: Till March '26, which is current year ongoing, total petchem outflow will be approximate say, INR 2,300 crores. And next year -- budget year, which is March '26, till March '27, petchem we are expecting around INR7,500 crores.
- Due: FY27
- Verdict: Pending
- Filing: <https://nsearchives.nseindia.com/corporate/PETRONET_20022026110925_intimationtranscript2.pdf>

## 2026-02-20 · Third jetty construction completion: Pending

- Said: Balance is approximately INR800 crores budget for jetty, third jetty which is under construction. This will also be completing during this year.
- Due: FY27
- Verdict: Pending
- Filing: <https://nsearchives.nseindia.com/corporate/PETRONET_20022026110925_intimationtranscript2.pdf>

## 2026-02-13 · The company expects capital expenditure to reach approximately INR 3,000 crores by March 2026.: Pending

- Said: we are expecting to have the approximate capex of till -- by March around INR3,000 crores in this year.
- By: Rakesh Chawla, Q3 FY26 earnings call
- Verdict: Pending
- Evidence: Not due until 31 Dec 2026, after the latest results; later ones will show.

## 2026-02-13 · The company expects to maintain its dividend payout in the range of 40% to 50%.: Pending

- Said: We have a healthy cash balance carrying in our books. So we expect to maintain the similar range of dividends.
- By: Saurav Mitra, Q3 FY26 earnings call
- Verdict: Pending
- Evidence: Not due yet, so it can't be checked.

## 2025-11-10 · The company expects the share of natural gas in India's energy basket to increase from 7% to 10% or 11%.: Pending

- Said: So, if not 15%, we are very hopeful that it will increase from current 7% level to 10%, 11% level.
- By: Vivek Mittal, Q2 FY26 earnings call
- Verdict: Pending
- Evidence: Not due yet, so it can't be checked.

## 2025-05-20 · The company has planned a capital expenditure program of 4,500 to 5,000 crore rupees for the current financial year.: Unverifiable

- Said: we have scheduled capex program of around INR5,000 crores -- INR4,500 crores to INR5,000 crores in the current financial year
- By: Saurav Mitra, Q4 FY25 earnings call
- Due: 2026-03-31
- Verdict: Unverifiable
- Evidence: We could not match this promise to a figure, and no later call settles it.

## 2025-02-04 · Dahej 5 MTPA expansion timeline: Slipped

- Said: just wait for some time because this capacity will be in place, maybe, by June, I think it should be in place.
- Due: 2025-06-30
- Verdict: Slipped
- Later filing says (2026-08-19): So the capacity utilization for Dahej was 65.6% but please do take note that this is for the expanded capacity which got expanded on 31st of March 2026.
- Filing: <https://nsearchives.nseindia.com/corporate/PETRONET_04022025123513_intimationtranscriptsigned1.pdf>

## 2025-02-04 · Kochi-Bangalore pipeline section connectivity: Slipped

- Said: from Coimbatore to Bangalore connectivity is still pending, maybe by June '25, it should be ready.
- Due: 2025-06-30
- Verdict: Slipped
- Later filing says (2026-02-20): GAIL has been still maintaining March 2026, but we believe by June 2026, we should be connected to natural gas to Kochi, Kuttanad, Bangalore, Mangalore pipeline.
- Filing: <https://nsearchives.nseindia.com/corporate/PETRONET_04022025123513_intimationtranscriptsigned1.pdf>

## 2025-02-04 · Petrochemical complex FY26 capex guidance: Pending

- Said: Next year we are planning to spend around INR 3,000 crore to INR 3,500 crores of Capex for petrochemical complex.
- Due: FY26
- Verdict: Pending
- Filing: <https://nsearchives.nseindia.com/corporate/PETRONET_04022025123513_intimationtranscriptsigned1.pdf>

## 2025-02-04 · Petrochemical project commissioning timeline: Pending

- Said: And as you said when it is likely to come up our schedule date is November 2027.
- Due: 2027-11-30
- Verdict: Pending
- Filing: <https://nsearchives.nseindia.com/corporate/PETRONET_04022025123513_intimationtranscriptsigned1.pdf>

## 2025-02-04 · Recovery of CY21 UoP dues: Kept

- Said: we will send the letters that we are going to invoke the bank guarantee. But at the same time, they have sought some time till 31st March because the bank guarantees are valid till 31st March.
- Due: 2025-03-31
- Verdict: Kept
- Later filing says (2025-05-27): We have received INR360.94 crores of Use or Pay dues pertaining to Calendar Year 2021, thanks to the Board approved mechanism in place
- Filing: <https://nsearchives.nseindia.com/corporate/PETRONET_04022025123513_intimationtranscriptsigned1.pdf>

## 2025-02-04 · Total FY26 capex guidance: Pending

- Said: INR 4,000 crores to INR 4,500 crores, including petchem.
- Due: FY26
- Verdict: Pending
- Filing: <https://nsearchives.nseindia.com/corporate/PETRONET_04022025123513_intimationtranscriptsigned1.pdf>

## 2025-01-28 · The company expects capital expenditure for the next fiscal year to be between INR 3000 and 3500 crores.: Missed

- Said: We expect at least 10%-15% of the Capex maybe to INR 3000 crores – INR 3500 crores. This is the expectation for the next year, actually at FY'25-'26.
- By: management, Q3 FY25 earnings call
- Verdict: Missed
- Evidence: The Q2 FY26 call, 10 Nov 2025 settles it: “So FY '26, I think we have already announced in our earlier conference calls that the total capex will be around INR5,000 crores.”

## 2025-01-28 · The company expects terminal utilization to remain between 95% and 100%.: Unverifiable

- Said: this quarter it has been 93%, but we expect this to remain in the range of 95-100%.
- By: management, Q3 FY25 earnings call
- Verdict: Unverifiable
- Evidence: We could not match this promise to a figure, and no later call settles it.

## 2024-10-24 · The Dahej terminal capacity expansion of 5 MMTPA is expected to be completed by March 2025.: Slipped

- Said: this expansion of our capacity by 5 MMTPA and this is likely to be completed by March 2025 as per the scheduled completion time.
- By: Vinod Kumar Mishra, Q2 FY25 earnings call
- Verdict: Slipped
- Evidence: The Q3 FY26 call, 13 Feb 2026 settles it: “we will be mechanically completing the construction by end of this financial year. So 31st March is our target to complete its -- mechanical completion.”

## 2024-10-24 · The company expects to recover the 2021 short volume receivables by December 2024.: Unverifiable

- Said: For 2021, it should be recovered by December 2024.
- By: Vinod Kumar Mishra, Q2 FY25 earnings call
- Verdict: Unverifiable
- Evidence: We could not match this promise to a figure, and no later call settles it.

## 2024-02-05 · Dahej 5 MMTPA expansion completion: Slipped

- Said: Expansion will be completed by March 2025 of 5 MMTPA at Dahej.
- Due: 2025-03-31
- Verdict: Slipped
- Later filing says (2026-08-19): So the capacity utilization for Dahej was 65.6% but please do take note that this is for the expanded capacity which got expanded on 31st of March 2026.
- Filing: <https://nsearchives.nseindia.com/corporate/PETRONET_05022024174823_intimationtranscriptsigned.pdf>

## 2024-02-05 · Dahej jetty completion: Pending

- Said: we hope that after it is awarded, it would take another 36-month period to complete that jetty.
- Verdict: Pending
- Filing: <https://nsearchives.nseindia.com/corporate/PETRONET_05022024174823_intimationtranscriptsigned.pdf>

## 2024-02-05 · Dahej tanks commissioning: Slipped

- Said: another -- tanks are also coming up. So tanks will be commissioned by June 2024.
- Due: 2024-06-30
- Verdict: Slipped
- Later filing says (2024-10-30): we have commissioned two tanks in Dahej on 1st of October.
- Filing: <https://nsearchives.nseindia.com/corporate/PETRONET_05022024174823_intimationtranscriptsigned.pdf>

## 2024-02-05 · Dahej terminal capacity expansion: Slipped

- Said: our expansion of Dahej terminal from 17.5 MMTPA to 22.5 MMTPA will be completed by March 2025.
- Due: 2025-03-31
- Verdict: Slipped
- Later filing says (2026-08-19): For the current quarter, the nameplate capacity of Dahej increased from 17.5 MMTPA to 22.5 MMTPA.
- Filing: <https://nsearchives.nseindia.com/corporate/PETRONET_05022024174823_intimationtranscriptsigned.pdf>

## 2024-02-05 · Kochi connectivity pipeline completion: Missed

- Said: section of Coimbatore to Krishnagiri is pending 250 kilometers. And as GAIL has committed, this will be completed by this year-end
- Due: 2024-12-31
- Verdict: Missed
- Later filing says (2026-02-20): And as far as pipeline connectivity is concerned, GAIL has been still maintaining March 2026, but we believe by June 2026, we should be connected to natural gas
- Filing: <https://nsearchives.nseindia.com/corporate/PETRONET_05022024174823_intimationtranscriptsigned.pdf>

Live record: https://eqdoc.com/stock/PETRONET. Not investment advice.