type: "Promise Ledger"
title: "PTC India Ltd: what management promised, and what happened"
description: "14 statements by PTC India Ltd's management, each checked against the company's later filings: 1 missed, 8 pending, 5 unverifiable."
resource: "https://eqdoc.com/stock/PTC"
tags: ["promise ledger","management guidance","india","ptc"]
sources: [{"resource":"https://nsearchives.nseindia.com/corporate/PTC_02112026182003_Investorpresentationsigned.pdf"},{"resource":"https://eqdoc.com/pdf/ann/7118267.pdf"},{"resource":"https://nsearchives.nseindia.com/corporate/PTC_20022026183157_letterfortranscriptdecresults.pdf"}]
generated: {"by":"process:eqdoc-promise-audit"}
x-eqdoc-symbol: "PTC"
x-eqdoc-counts: {"kept":0,"slipped":0,"missed":1,"pending":8,"unverifiable":5}
---

# How to read this

Each entry is something management said it would do, when it said it, and whether the company's later filings show it happened.
- **Kept**: a later filing shows it done. **Slipped**: done late or in part. **Missed**: the deadline passed without it.
- **Pending**: the deadline has not come, or no later filing yet speaks to it. **Unverifiable**: no filing could settle it.
- Evidence is either a sentence built from figures the company filed, or a quote from a later company document, as marked.

# Promises

## 2026-11-02 · Execute long-term 25-year power purchase agreement for 1,200 MW solar power with NTPC Renewable Energy.: Pending

- Said: Power purchase Agreement of 1200 MW solar power with NTPC Renewable Energy on long- term for 25 years
- By: Company presentation, Investor presentation, 2 Nov 2026
- Due: 25 years
- Verdict: Pending
- Evidence: Not due until 2 Nov 2051, after the latest results; later ones will show.
- Filing: <https://nsearchives.nseindia.com/corporate/PTC_02112026182003_Investorpresentationsigned.pdf> (page 16)

## 2026-11-02 · Extend the medium-term 204 MW power supply contract to Nepal up to 2028.: Pending

- Said: Extending contract of 204 MW supply of power to Nepal for medium term up to 2028.
- By: Company presentation, Investor presentation, 2 Nov 2026
- Due: up to 2028
- Verdict: Pending
- Evidence: Not due until 31 Dec 2028, after the latest results; later ones will show.
- Filing: <https://nsearchives.nseindia.com/corporate/PTC_02112026182003_Investorpresentationsigned.pdf> (page 16)

## 2026-11-02 · Procure 500 MW / 2,000 MWh BESS on a long-term basis through an Expression of Interest.: Pending

- Said: Expression of Interest for procurement of power 500 MW/2000 MWh BESS on long term basis.
- By: Company presentation, Investor presentation, 2 Nov 2026
- Verdict: Pending
- Evidence: Not due yet, so it can't be checked.
- Filing: <https://nsearchives.nseindia.com/corporate/PTC_02112026182003_Investorpresentationsigned.pdf> (page 16)

## 2026-11-02 · Supply and export up to 1,200 MW cross-border power to Bhutan during the winter season.: Pending

- Said: Cross Border supply (export) of power of up to 1200 MW in winter for the short term to Bhutan
- By: Company presentation, Investor presentation, 2 Nov 2026
- Due: in winter
- Verdict: Pending
- Evidence: Not due yet, so it can't be checked.
- Filing: <https://nsearchives.nseindia.com/corporate/PTC_02112026182003_Investorpresentationsigned.pdf> (page 16)

## 2026-08-04 · Align green power trading with India's national goal of 500 GW non-fossil capacity by 2030.: Pending

- Said: Markets like GTAM and RECs support green power trading, aligned with India’s 500 GW non-fossil goal by 2030.
- By: Company presentation, Investor presentation, 4 Aug 2026
- Due: 2030
- Verdict: Pending
- Evidence: Not due until 31 Dec 2030, after the latest results; later ones will show.
- Filing: <https://eqdoc.com/pdf/ann/7118267.pdf> (page 17)

## 2026-08-04 · Execute a renewable energy advisory assignment to drive C&I adoption.: Unverifiable

- Said: Renewable energy advisory assignment focused on accelerating renewable energy adoption in the Commercial & Industrial (C&I) sector through regulatory, financial, and implementation
- By: Company presentation, Investor presentation, 4 Aug 2026
- Verdict: Unverifiable
- Evidence: We could not match this promise to a figure, and no later call settles it.
- Filing: <https://eqdoc.com/pdf/ann/7118267.pdf> (page 16)

## 2026-08-04 · Prepare a business plan for setting up EV charging parks on highways.: Unverifiable

- Said: Preparation of Business Plan for Charging Parks on Highways.
- By: Company presentation, Investor presentation, 4 Aug 2026
- Verdict: Unverifiable
- Evidence: We could not match this promise to a figure, and no later call settles it.
- Filing: <https://eqdoc.com/pdf/ann/7118267.pdf> (page 16)

## 2026-08-04 · Procure power for Indian Railways under a 3-year work order from REMCL.: Pending

- Said: 3 Year Work Order from Railway Energy Management Company Ltd. (REMCL) for the procurement of power for Indian Railways
- By: Company presentation, Investor presentation, 4 Aug 2026
- Due: 2029-08-04
- Verdict: Pending
- Evidence: Not due until 4 Aug 2029, after the latest results; later ones will show.
- Filing: <https://eqdoc.com/pdf/ann/7118267.pdf> (page 16)

## 2026-02-16 · The Teesta Urja plant expects to start power generation within 6 months.: Pending

- Said: I think maybe within a period of next 6 months, so the coffer dam will be constructed and the power will be started generating from that.
- By: Pankaj Goel, Q3 FY26 earnings call
- Verdict: Pending
- Evidence: Not due until 31 Aug 2026, after the latest results; later ones will show.
- Filing: <https://nsearchives.nseindia.com/corporate/PTC_20022026183157_letterfortranscriptdecresults.pdf> (page 14)

## 2025-11-12 · A 100 MW solar plant is expected to be operational by Q1 FY 2027.: Unverifiable

- Said: I am happy to inform that in this quarter, we have executed PPA of 100 MW and the plant is expected to get operational by the first quarter of the financial year 2027.
- By: Manoj Kumar Jhawar, Q2 FY26 earnings call
- Due: by Q1 FY 2027
- Verdict: Unverifiable
- Evidence: We could not match this promise to a figure, and no later call settles it.

## 2025-02-13 · The company expects power demand to grow at a rate of 6% to 8% per annum.: Unverifiable

- Said: The business outlook, I expect power demand to remain firm and grow at 6% to 8% per annum.
- By: Dr. Manoj Kumar Jhawar, Q3 FY25 earnings call
- Verdict: Unverifiable
- Evidence: We could not match this promise to a figure, and no later call settles it.

## 2025-02-13 · The transaction for the sale of PTC Energy Limited is expected to close by February 28, 2025.: Pending

- Said: We expect this to close very shortly, and the timeline for completion of the transaction has been extended to 28th February 25 on mutual agreement.
- By: Dr. Manoj Kumar Jhawar, Q3 FY25 earnings call
- Due: by February 28, 2025
- Verdict: Pending
- Evidence: Not due until 29 Feb 2028, after the latest results; later ones will show.

## 2024-11-13 · The company estimates it may take about a quarter to resolve accounting issues and seek shareholder approval.: Unverifiable

- Said: It may take a quarter or so.
- By: management, Q2 FY25 earnings call
- Verdict: Unverifiable
- Evidence: We could not match this promise to a figure, and no later call settles it.

## 2024-11-13 · The company expects to close the PTC Energy Limited divestment transaction by mid-December.: Missed

- Said: We expect to close this transaction by mid of the next month.
- By: management, Q2 FY25 earnings call
- Verdict: Missed
- Evidence: The Q3 FY25 call, 13 Feb 2025 settles it: “We expect this to close very shortly, and the timeline for completion of the transaction has been extended to 28th February 25 on mutual agreement.”

Live record: https://eqdoc.com/stock/PTC. Not investment advice.