type: "Promise Ledger"
title: "Rossell Techsys Ltd: what management promised, and what happened"
description: "11 statements by Rossell Techsys Ltd's management, each checked against the company's later filings: 1 kept, 1 missed, 6 pending, 3 unverifiable."
resource: "https://eqdoc.com/stock/ROSSTECH"
tags: ["promise ledger","management guidance","india","rosstech"]
sources: [{"resource":"https://nsearchives.nseindia.com/corporate/9886945009_06022026111028_upload.pdf"}]
generated: {"by":"process:eqdoc-promise-audit"}
x-eqdoc-symbol: "ROSSTECH"
x-eqdoc-counts: {"kept":1,"slipped":0,"missed":1,"pending":6,"unverifiable":3}
---

# How to read this

Each entry is something management said it would do, when it said it, and whether the company's later filings show it happened.
- **Kept**: a later filing shows it done. **Slipped**: done late or in part. **Missed**: the deadline passed without it.
- **Pending**: the deadline has not come, or no later filing yet speaks to it. **Unverifiable**: no filing could settle it.
- Evidence is either a sentence built from figures the company filed, or a quote from a later company document, as marked.

# Promises

## 2026-07-28 · The company expects to begin generating revenue from its new semiconductor customer starting in the second quarter of fi: Pending

- Said: new high-growth revenue stream with execution from Q2 FY27.
- By: Company presentation, Investor presentation, 28 Jul 2026
- Due: starting in the second quarter of fiscal year 2027
- Verdict: Pending
- Evidence: Not due until 30 Sep 2026, after the latest results; later ones will show.

## 2026-07-28 · The company plans to raise up to 300 crore rupees through a Qualified Institutional Placement to fund expansion and capa: Pending

- Said: The proposed QIP of up to ₹300 Cr will provide the capital required to support strategic expansion, capacity creation, and long-term value creation.
- By: Company presentation, Investor presentation, 28 Jul 2026
- Verdict: Pending
- Evidence: Not due yet, so it can't be checked.

## 2026-07-28 · The company projects its workforce will grow to 2,500 employees by 2029.: Pending

- Said: Number of employees 2025 2026 2027>* 2029>* 600 1196 2000 2500
- By: Company presentation, Investor presentation, 28 Jul 2026
- Due: by 2029
- Verdict: Pending
- Evidence: Not due until 31 Dec 2029, after the latest results; later ones will show.

## 2026-07-28 · The company targets increasing its aircraft build contribution to 25% over the long term.: Pending

- Said: Value chain target: 2% → 15% → 25% aircraft build contribution.
- By: Company presentation, Investor presentation, 28 Jul 2026
- Verdict: Pending
- Evidence: Not due yet, so it can't be checked.

## 2026-07-28 · The company will open a new manufacturing facility in Bengaluru during the second half of fiscal year 2027.: Pending

- Said: secured an additional manufacturing facility within Aerospace Park, Bengaluru, expected to become operational during H2 FY27
- By: Company presentation, Investor presentation, 28 Jul 2026
- Due: during the second half of fiscal year 2027
- Verdict: Pending
- Evidence: Not due until 31 Mar 2027, after the latest results; later ones will show.

## 2026-02-04 · The company plans to lease a new 210,000 square foot facility to support growth.: Pending

- Said: we are planning to take a building on lease from the first of April of the year 2026-2027 of around 210,000 square feet to fuel our growth
- By: Rishab Gupta, Q3 FY26 earnings call
- Verdict: Pending
- Evidence: Not due until 31 Dec 2026, after the latest results; later ones will show.
- Filing: <https://nsearchives.nseindia.com/corporate/9886945009_06022026111028_upload.pdf> (page 6)

## 2025-11-11 · The company expects to receive its AS9110 MRO license within 30 days.: Unverifiable

- Said: the company has already applied for an AS9110 license, which is the MRO license. We should be able to secure that within the next 30 days.
- By: Senthil B., Q2 FY26 earnings call
- Verdict: Unverifiable
- Evidence: We could not match this promise to a figure, and no later call settles it.

## 2025-11-11 · The company intends to complete the QIP process by the end of December.: Unverifiable

- Said: So another, I would say 45 days, the QIP should be closed. So that's the intent of the company by end of December, that the QIP process is completed.
- By: Rishab Gupta, Q2 FY26 earnings call
- Verdict: Unverifiable
- Evidence: We could not match this promise to a figure, and no later call settles it.

## 2025-08-14 · The company expects EBITDA margins of 18-22% starting this year.: Missed

- Said: Going forward we should expect an 18% to 22% EBITDA margin moving forward and that we will achieved starting this year and that should continue moving forward.
- By: Rishab Gupta, Q1 FY26 earnings call
- Due: 2026-03-31
- Verdict: Missed
- Evidence: Operating margin for FY26 came to 12.2% — short of the 18% to 22% promised, with the window closed.

## 2025-08-14 · The company expects to execute INR 150 crores of its current confirmed POs within the current financial year.: Kept

- Said: So out of INR700 crores I think probably we have INR150 crores which is executable in this financial year.
- By: Zeena Philip, Q1 FY26 earnings call
- Due: 2026-03-31
- Verdict: Kept
- Evidence: Sales for FY26 came to ₹484 cr — past the ₹150 cr promised.

## 2025-08-14 · The company targets reaching a three-month inventory level.: Unverifiable

- Said: The end goal for the company is a four-term inventory, that means a three-month inventory. We have a three-month inventory in the company moving forward.
- By: Rishab Gupta, Q1 FY26 earnings call
- Verdict: Unverifiable
- Evidence: We could not match this promise to a figure, and no later call settles it.

Live record: https://eqdoc.com/stock/ROSSTECH. Not investment advice.