type: "Promise Ledger"
title: "Sarda Energy & Minerals Ltd: what management promised, and what happened"
description: "26 statements by Sarda Energy & Minerals Ltd's management, each checked against the company's later filings: 3 slipped, 2 missed, 17 pending, 4 unverifiable."
resource: "https://eqdoc.com/stock/SARDAEN"
tags: ["promise ledger","management guidance","india","sardaen"]
sources: [{"resource":"https://nsearchives.nseindia.com/corporate/SARDAEN_02112026142551_SEML.pdf"},{"resource":"https://eqdoc.com/pdf/ann/7110191.pdf"},{"resource":"https://nsearchives.nseindia.com/corporate/SARDAEN_16022026113448_SEML.pdf"},{"resource":"https://nsearchives.nseindia.com/corporate/SARDAEN_11082025151101_SEML_Concall_Transcript_04082025.pdf"},{"resource":"https://nsearchives.nseindia.com/corporate/SARDAEN_13022024101641_SEML_Concall_Transcript_06022024.pdf"}]
generated: {"by":"process:eqdoc-promise-audit","at":"2026-10-18"}
stale_after: "2027-01-26"
x-eqdoc-symbol: "SARDAEN"
x-eqdoc-counts: {"kept":0,"slipped":3,"missed":2,"pending":17,"unverifiable":4}
---

# How to read this

Each entry is something management said it would do, when it said it, and whether the company's later filings show it happened.
- **Kept**: a later filing shows it done. **Slipped**: done late or in part. **Missed**: the deadline passed without it.
- **Pending**: the deadline has not come, or no later filing yet speaks to it. **Unverifiable**: no filing could settle it.
- Evidence is either a sentence built from figures the company filed, or a quote from a later company document, as marked.

# Promises

## 2026-11-02 · Achieve operational status for the 50 MW solar power project during FY27.: Pending

- Said: The solar power project is expected to become operational during FY27.
- By: Company presentation, Investor presentation, 2 Nov 2026
- Due: FY27
- Verdict: Pending
- Evidence: Not due until 31 Mar 2027, after the latest results; later ones will show.
- Filing: <https://nsearchives.nseindia.com/corporate/SARDAEN_02112026142551_SEML.pdf> (page 21)

## 2026-11-02 · Double EBITDA over the medium term based on FY26 levels.: Unverifiable

- Said: Target to double EBITDA* over the medium term through disciplined execution, operational excellence and a diversified, future-ready portfolio
- By: Company presentation, Investor presentation, 2 Nov 2026
- Due: over the medium term
- Verdict: Unverifiable
- Evidence: We could not match this promise to a figure, and no later call settles it.
- Filing: <https://nsearchives.nseindia.com/corporate/SARDAEN_02112026142551_SEML.pdf> (page 17)

## 2026-11-02 · Double energy capacity and quadruple mining capacity by FY30.: Pending

- Said: Plans to double energy capacity and quadruple mining capacity by FY30
- By: Company presentation, Investor presentation, 2 Nov 2026
- Due: FY30
- Verdict: Pending
- Evidence: Not due until 31 Mar 2030, after the latest results; later ones will show.
- Filing: <https://nsearchives.nseindia.com/corporate/SARDAEN_02112026142551_SEML.pdf> (page 16)

## 2026-11-02 · Execute over Rs. 10,000 crore in growth capex focused on energy and mining assets.: Pending

- Said: Execute Rs. 10,000+ Cr growth capex focused on high-return energy and mining assets.
- By: Company presentation, Investor presentation, 2 Nov 2026
- Verdict: Pending
- Evidence: Not due yet, so it can't be checked.
- Filing: <https://nsearchives.nseindia.com/corporate/SARDAEN_02112026142551_SEML.pdf> (page 17)

## 2026-11-02 · Increase coal production capacity to over 7 MTPA via new mine development.: Pending

- Said: Increase coal production capacity to 7+ MTPA through new mine development.
- By: Company presentation, Investor presentation, 2 Nov 2026
- Verdict: Pending
- Evidence: Not due yet, so it can't be checked.
- Filing: <https://nsearchives.nseindia.com/corporate/SARDAEN_02112026142551_SEML.pdf> (page 17)

## 2026-11-02 · Increase renewable energy portfolio to 400 MW by FY30.: Pending

- Said: Increase renewable energy portfolio to 400 MW by FY30.
- By: Company presentation, Investor presentation, 2 Nov 2026
- Due: by FY30
- Verdict: Pending
- Evidence: Not due until 31 Mar 2030, after the latest results; later ones will show.
- Filing: <https://nsearchives.nseindia.com/corporate/SARDAEN_02112026142551_SEML.pdf> (page 17)

## 2026-11-02 · Invest Rs. 300 crore in sustainability initiatives including a WHR power plant at Vizianagaram.: Pending

- Said: Announced a Rs. 300 crore investment for sustainability initiatives including Waste Heat Recovery power plant at Vizianagaram.
- By: Company presentation, Investor presentation, 2 Nov 2026
- Verdict: Pending
- Evidence: Not due yet, so it can't be checked.
- Filing: <https://nsearchives.nseindia.com/corporate/SARDAEN_02112026142551_SEML.pdf> (page 22)

## 2026-11-02 · Start operations at the Avagudem manganese ore mine within 12 to 14 months.: Pending

- Said: Indicative start of operations 12-14 months, subject to approvals and mine development
- By: Company presentation, Investor presentation, 2 Nov 2026
- Due: 12-14 months
- Verdict: Pending
- Evidence: Not due until 31 Jan 2028, after the latest results; later ones will show.
- Filing: <https://nsearchives.nseindia.com/corporate/SARDAEN_02112026142551_SEML.pdf> (page 7)

## 2026-08-03 · Double capacity at SKS Power (IPP Binjkot) to 4x300 MW.: Pending

- Said: Plans to double capacity at SKS Power (IPP Binjkot) to 4x300 MW ; approval process underway
- By: Company presentation, Investor presentation, 3 Aug 2026
- Verdict: Pending
- Evidence: Not due yet, so it can't be checked.
- Filing: <https://eqdoc.com/pdf/ann/7110191.pdf> (page 22)

## 2026-02-09 · The company expects to achieve a total capex of approximately INR550 to INR600 crores for FY26.: Unverifiable

- Said: we should be able to comfortably achieve somewhere in the range of INR550 crores to INR600 crores approximately.
- By: Padam Kumar Jain, Q3 FY26 earnings call
- Due: for FY26
- Verdict: Unverifiable
- Evidence: We could not match this promise to a figure, and no later call settles it.
- Filing: <https://nsearchives.nseindia.com/corporate/SARDAEN_16022026113448_SEML.pdf> (page 11)

## 2025-08-11 · 30MW TG set replacement operations: Pending

- Said: Work is on schedule with operations expected to begin by mid-FY '27.
- Due: FY27
- Verdict: Pending
- Filing: <https://nsearchives.nseindia.com/corporate/SARDAEN_11082025151101_SEML_Concall_Transcript_04082025.pdf>

## 2025-08-11 · 50MW Captive solar commissioning: Slipped

- Said: Project commissioning is expected in current financial year.
- Due: FY26
- Verdict: Slipped
- Later filing says (2026-08-10): Commissioning of our 50-megawatt captive solar project has been delayed due to right-of-way issues of the transmission line. We now expect commissioning before the end of the next quarter.
- Filing: <https://nsearchives.nseindia.com/corporate/SARDAEN_11082025151101_SEML_Concall_Transcript_04082025.pdf>

## 2025-08-11 · Annual expansion capex spending: Pending

- Said: We are spending about INR500 crores to INR1,000 crores a year on the expansion projects in different segments, whether it is coal mines, hydropower project and other projects.
- Due: FY28
- Verdict: Pending
- Filing: <https://nsearchives.nseindia.com/corporate/SARDAEN_11082025151101_SEML_Concall_Transcript_04082025.pdf>

## 2025-08-11 · Coal mining capacity approval: Missed

- Said: Final approval for increasing coal mining capacity from 1.68 million tons is expected this quarter.
- Due: Q2 FY26
- Verdict: Missed
- Later filing says (2026-02-16): Approval to enhance the capacity of the Gare Palma IV/7 Coal Mine from 1.68 million tons to 1.8 million tons is at the final stage and is expected shortly.
- Filing: <https://nsearchives.nseindia.com/corporate/SARDAEN_11082025151101_SEML_Concall_Transcript_04082025.pdf>

## 2025-08-11 · Kotaiveera Hydropower project start: Pending

- Said: The project is in approval stage with work expected to begin in next quarter.
- Due: Q3 FY26
- Verdict: Pending
- Filing: <https://nsearchives.nseindia.com/corporate/SARDAEN_11082025151101_SEML_Concall_Transcript_04082025.pdf>

## 2025-08-11 · Shahpur West mine production: Pending

- Said: Shahpur West mine development work is progressing as per schedule and production is expected before the end of the next financial year.
- Due: FY27
- Verdict: Pending
- Filing: <https://nsearchives.nseindia.com/corporate/SARDAEN_11082025151101_SEML_Concall_Transcript_04082025.pdf>

## 2024-11-18 · The 30-megawatt TG set replacement project will be operational by mid-financial year 2026-27.: Pending

- Said: The plant will be operational in mid of financial year 2026-'27.
- By: P K Jain, Q2 FY25 earnings call
- Verdict: Pending
- Evidence: Not due until 31 Dec 2026, after the latest results; later ones will show.

## 2024-11-18 · The company expects to increase coal mining capacity to 1.8 million tons by the end of the current financial year (FY25): Unverifiable

- Said: In the first stage, we are increasing it further from 1.68 million to 1.8 million tons. We expect to get maybe by end of the current financial year
- By: P K Jain, Q2 FY25 earnings call
- Due: FY25
- Verdict: Unverifiable
- Evidence: We could not match this promise to a figure, and no later call settles it.

## 2024-08-05 · The 50-megawatt captive solar power project is expected to be operational by the end of the current financial year (FY25: Unverifiable

- Said: The plant is scheduled to be operational by end of the current financial year.
- By: Pankaj Sarda, Q1 FY25 earnings call
- Due: FY25
- Verdict: Unverifiable
- Evidence: We could not match this promise to a figure, and no later call settles it.

## 2024-08-05 · The company projects a total capital expenditure of approximately INR700 crores for the financial year FY25.: Slipped

- Said: It should be -- total capex should be somewhere in the range of INR700 crores
- By: Padam Jain, Q1 FY25 earnings call
- Verdict: Slipped
- Evidence: The Q3 FY26 call, 9 Feb 2026 settles it: “we should be able to comfortably achieve somewhere in the range of INR550 crores to INR600 crores approximately.”

## 2024-02-13 · 50 MW solar power project operationalization: Slipped

- Said: The project is estimated to cost Rs. 200 crores. Orders have been placed and the plant will be operational before the end of next financial year.
- Due: FY25
- Verdict: Slipped
- Later filing says (2026-08-10): Commissioning of our 50-megawatt captive solar project has been delayed due to right-of-way issues of the transmission line. We now expect commissioning before the end of the next quarter.
- Filing: <https://nsearchives.nseindia.com/corporate/SARDAEN_13022024101641_SEML_Concall_Transcript_06022024.pdf>

## 2024-02-13 · Annual ongoing CAPEX outlay guidance: Pending

- Said: For the next 2 years at least, we will have CAPEX of about 700 crores to 800 crores and put together in all the ongoing projects.
- Due: FY26
- Verdict: Pending
- Filing: <https://nsearchives.nseindia.com/corporate/SARDAEN_13022024101641_SEML_Concall_Transcript_06022024.pdf>

## 2024-02-13 · Captive coal requirement coverage target: Pending

- Said: FY25-26 we should be able to meet 100% of our coal requirement from captive sources after commissioning of the Shahpur Coal Mine.
- Due: FY26
- Verdict: Pending
- Filing: <https://nsearchives.nseindia.com/corporate/SARDAEN_13022024101641_SEML_Concall_Transcript_06022024.pdf>

## 2024-02-13 · Indonesian JV coal production target: Pending

- Said: We expect to produce 1 million metric tonne of coal from the mine in FY25.
- Due: FY25
- Verdict: Pending
- Filing: <https://nsearchives.nseindia.com/corporate/SARDAEN_13022024101641_SEML_Concall_Transcript_06022024.pdf>

## 2024-02-13 · Kalyani coal mine restart timeline: Pending

- Said: We have to restart mining within 18 months after obtaining all required approvals etc.
- Verdict: Pending
- Filing: <https://nsearchives.nseindia.com/corporate/SARDAEN_13022024101641_SEML_Concall_Transcript_06022024.pdf>

## 2024-02-13 · Rehar Hydro Project commissioning timeline: Missed

- Said: Construction work at 25 megawatt Rehar Hydro Project is progressing ahead of schedule and the plant is expected to be operational well before scheduled completion date of March 2025.
- Due: 2025-03-31
- Verdict: Missed
- Later filing says (2025-08-11): 25-megawatt Rehar hydropower plant, which commissioned in July 2025
- Filing: <https://nsearchives.nseindia.com/corporate/SARDAEN_13022024101641_SEML_Concall_Transcript_06022024.pdf>

Live record: https://eqdoc.com/stock/SARDAEN. Not investment advice.