type: "Promise Ledger"
title: "Shakti Pumps India Ltd: what management promised, and what happened"
description: "21 statements by Shakti Pumps India Ltd's management, each checked against the company's later filings: 1 kept, 4 slipped, 1 missed, 13 pending, 2 unverifiable."
resource: "https://eqdoc.com/stock/SHAKTIPUMP"
tags: ["promise ledger","management guidance","india","shaktipump"]
sources: [{"resource":"https://eqdoc.com/pdf/ann/7435410.pdf"},{"resource":"https://nsearchives.nseindia.com/corporate/SHAKTIPUMP_01082026102948_SubmissionofEarningTranscript.pdf"},{"resource":"https://nsearchives.nseindia.com/corporate/SHAKTIPUMP_25072026153057_LetterInvestorPresentationQ1FY27.pdf"},{"resource":"https://eqdoc.com/pdf/ann/7079315.pdf"},{"resource":"https://eqdoc.com/pdf/ann/6796979.pdf"},{"resource":"https://nsearchives.nseindia.com/corporate/SHAKTIPUMP_19022026163933_SubmissionofEarningTranscript14022026.pdf"}]
generated: {"by":"process:eqdoc-promise-audit","at":"2026-09-16"}
stale_after: "2026-12-25"
x-eqdoc-symbol: "SHAKTIPUMP"
x-eqdoc-counts: {"kept":1,"slipped":4,"missed":1,"pending":13,"unverifiable":2}
---

# How to read this

Each entry is something management said it would do, when it said it, and whether the company's later filings show it happened.
- **Kept**: a later filing shows it done. **Slipped**: done late or in part. **Missed**: the deadline passed without it.
- **Pending**: the deadline has not come, or no later filing yet speaks to it. **Unverifiable**: no filing could settle it.
- Evidence is either a sentence built from figures the company filed, or a quote from a later company document, as marked.

# Promises

## 2026-10-23 · Bring new capacities for pumps, motors, VFDs, and solar structures online starting Q3 FY27.: Pending

- Said: Pumps, Motors, VFDs & Solar Structures — New capacities expected to come online from Q3 FY27
- By: Company presentation, Investor presentation, 23 Oct 2026
- Due: Q3 FY27
- Verdict: Pending
- Evidence: Not due until 31 Dec 2026, after the latest results; later ones will show.
- Filing: <https://eqdoc.com/pdf/ann/7435410.pdf> (page 20)

## 2026-10-23 · Commission the 2.2 GW DCR solar cell facility by FY28.: Pending

- Said: with the 2.2 GW DCR solar cell facility to be commissioned by FY28.
- By: Company presentation, Investor presentation, 23 Oct 2026
- Due: FY28
- Verdict: Pending
- Evidence: Not due until 31 Mar 2028, after the latest results; later ones will show.
- Filing: <https://eqdoc.com/pdf/ann/7435410.pdf> (page 7)

## 2026-10-23 · Double existing pump and motor manufacturing capacity.: Pending

- Said: Capacity Expansion in Progress to Double existing Pump & Motor capacities
- By: Company presentation, Investor presentation, 23 Oct 2026
- Verdict: Pending
- Evidence: Not due yet, so it can't be checked.
- Filing: <https://eqdoc.com/pdf/ann/7435410.pdf> (page 26)

## 2026-07-27 · Operating margins are projected to improve quarter-on-quarter following Q1 FY27.: Missed

- Said: Going forward, with KUSUM 2.0 expected to come in and raw material prices likely to ease as the geopolitical situation stabilizes, we expect margins to improve gradually on a quarter-on-quarter basis.
- By: Dinesh Patel, Q1 FY27 earnings call
- Due: quarter-on-quarter
- Verdict: Missed
- Evidence: Operating margin went from 9.6% in the Jun 2026 quarter to 8.6% in the Sep 2026 quarter.
- Filing: <https://nsearchives.nseindia.com/corporate/SHAKTIPUMP_01082026102948_SubmissionofEarningTranscript.pdf> (page 9)

## 2026-07-27 · The 0.5 GW facility will be completed by September 2026.: Unverifiable

- Said: One is for 0.5 GW which will be completed in September '26. The second is for 2.2 GW, for which we are aiming at September '27.
- By: Dinesh Patel, Q1 FY27 earnings call
- Due: September '26 and September '27
- Verdict: Unverifiable
- Evidence: We could not match this promise to a figure, and no later call settles it.
- Filing: <https://nsearchives.nseindia.com/corporate/SHAKTIPUMP_01082026102948_SubmissionofEarningTranscript.pdf> (page 7)

## 2026-07-25 · Commission 0.5 GW DCR module facility by September 2026.: Unverifiable

- Said: 0.5 GW DCR Module Expected commissioning by September 2026 - a direct near-term lever for margin improvement via reduced module dependency
- By: Company presentation, Investor presentation, 25 Jul 2026
- Due: September 2026
- Verdict: Unverifiable (a second reading found it pending)
- Evidence: We could not match this promise to a figure, and no later call settles it.
- Filing: <https://nsearchives.nseindia.com/corporate/SHAKTIPUMP_25072026153057_LetterInvestorPresentationQ1FY27.pdf> (page 12)

## 2026-07-25 · Commission 2.2 GW solar DCR cell and module greenfield capacity expansion at Pithampur by FY28.: Pending

- Said: 2.2 GW Solar DCR Cell & Module Greenfield capacity expansion at Pithampur, expected to commission by FY28
- By: Company presentation, Investor presentation, 25 Jul 2026
- Due: by FY28
- Verdict: Pending
- Evidence: Not due until 31 Mar 2028, after the latest results; later ones will show.
- Filing: <https://nsearchives.nseindia.com/corporate/SHAKTIPUMP_25072026153057_LetterInvestorPresentationQ1FY27.pdf> (page 12)

## 2026-07-25 · Deploy planned capex of ₹1,140 million in EV subsidiary Shakti EV Mobility.: Pending

- Said: Cumulative investment of ₹ 700 Mn till July 2026, out of a planned ₹1,140 Mn capex
- By: Company presentation, Investor presentation, 25 Jul 2026
- Verdict: Pending
- Evidence: Not due yet, so it can't be checked.
- Filing: <https://nsearchives.nseindia.com/corporate/SHAKTIPUMP_25072026153057_LetterInvestorPresentationQ1FY27.pdf> (page 11)

## 2026-07-25 · Execute phased capex programme of approximately ₹17,000 million to double core capacity and enter solar cell/module manu: Pending

- Said: A ~ ₹ 17,000 Mn phased capex programme positions Shakti Pumps to double core capacity and enter solar cell/module manufacturing
- By: Company presentation, Investor presentation, 25 Jul 2026
- Verdict: Pending
- Evidence: Not due yet, so it can't be checked.
- Filing: <https://eqdoc.com/pdf/ann/7079315.pdf> (page 12)

## 2026-07-25 · core capacity expansion timeline: Pending

- Said: Pumps, Motors, VFDs & Solar Structures — New capacities expected to come online from Q3 FY27
- Due: FY27-Q3
- Verdict: Pending

## 2026-05-11 · The 0.5 GW module facility will be commissioned by the end of Q1 FY27.: Slipped

- Said: We feel that the facility will be commissioned by the end of Q1FY27 and will start contributing to margin improvement.
- By: Dinesh Patel, Q4 FY26 earnings call
- Due: by the end of Q1FY27
- Verdict: Slipped
- Evidence: The Q1 FY27 call, 27 Jul 2026 settles it: “One is for 0.5 GW which will be completed in September '26. The second is for 2.2 GW, for which we are aiming at September '27.”
- Filing: <https://eqdoc.com/pdf/ann/6796979.pdf> (page 16)

## 2026-02-14 · The 2.2 GW cell plus module capacity is expected to be operational by April 2027.: Pending

- Said: Second, the cell plus module capacity of 2.2 gigawatts we are talking about, the remaining capacity is expected to be operational by April 2027.
- By: Dinesh Patel, Q3 FY26 earnings call
- Due: April 2027
- Verdict: Pending
- Evidence: Not due until 30 Apr 2027, after the latest results; later ones will show.
- Filing: <https://nsearchives.nseindia.com/corporate/SHAKTIPUMP_19022026163933_SubmissionofEarningTranscript14022026.pdf> (page 6)

## 2026-02-14 · The company targets reaching ₹5,000 crores in revenue in FY28.: Slipped

- Said: In FY28, we will see ourselves doing a revenue of INR5,000 crores.
- By: Dinesh Patel, Q3 FY26 earnings call
- Due: FY28
- Verdict: Slipped (a second reading found it pending)
- Evidence: The Q1 FY27 call, 27 Jul 2026 settles it: “So, together these products create an integrated portfolio and with this complete package, our target is to reach INR5,000 crores by FY29.”
- Filing: <https://nsearchives.nseindia.com/corporate/SHAKTIPUMP_19022026163933_SubmissionofEarningTranscript14022026.pdf> (page 14)

## 2026-02-19 · Retail export growth target: Pending

- Said: the retail export will grow by 25% every year.
- Verdict: Pending

## 2026-02-19 · Solar plant investment and debt plan: Pending

- Said: Because the INR1200 crores investment to be made to install the solar plant, in that we are planning a minimum debt of around INR400 crores to INR500 crores.
- Verdict: Pending

## 2026-02-14 · Management expects execution momentum to improve meaningfully in Q4 FY26 to deliver the company's highest revenue quarte: Kept

- Said: Looking ahead, we expect execution momentum to improve meaningfully in Q4 FY '26, which we anticipate being our highest revenue quarter ever
- By: Ramesh Patidar, Q3 FY26 earnings call
- Due: Q4 FY '26
- Verdict: Kept
- Evidence: Sales went from ₹551 cr in the Dec 2025 quarter to ₹858 cr in the Mar 2026 quarter.
- Filing: <https://nsearchives.nseindia.com/corporate/SHAKTIPUMP_19022026163933_SubmissionofEarningTranscript14022026.pdf> (page 4)

## 2026-02-14 · Management expects to commission its 500 MW DCR module capacity in Q1 FY27.: Slipped

- Said: Our solar rooftop business is steadily expanding its dealer network, positioning it to become a meaningful contributor post commissioning of our DCR module capacity of 500 megawatts in Q1 FY '27.
- By: Ramesh Patidar, Q3 FY26 earnings call
- Due: Q1 FY '27
- Verdict: Slipped
- Evidence: The Q1 FY27 call, 27 Jul 2026 settles it: “One is for 0.5 GW which will be completed in September '26. The second is for 2.2 GW, for which we are aiming at September '27.”
- Filing: <https://nsearchives.nseindia.com/corporate/SHAKTIPUMP_19022026163933_SubmissionofEarningTranscript14022026.pdf> (page 4)

## 2026-02-14 · Pump expansion trial runs and full-fledged production are scheduled to commence around August 2026.: Slipped

- Said: Most probably, in August ‘26 we will be able to start trial runs and then full-fledged production.
- By: Dinesh Patel, Q3 FY26 earnings call
- Due: August ‘26
- Verdict: Slipped
- Evidence: The Q1 FY27 call, 27 Jul 2026 settles it: “In November '26, our pump plant will come. This is our capacity; everything is well-planned, it's all coming.”
- Filing: <https://nsearchives.nseindia.com/corporate/SHAKTIPUMP_19022026163933_SubmissionofEarningTranscript14022026.pdf> (page 6)

## 2025-11-09 · Capacity expansion capex: Pending

- Said: Company is executing a capex plan of Rs. 17,000 Mn, which includes: Doubling capacity for pumps, motors, VFDs, and solar structures (Rs. 2,500 Mn)
- Verdict: Pending

## 2025-11-09 · EV subsidiary investment commitment: Pending

- Said: SPIL Board has approved investments of ₹ 114.3 crores in Shakti EV Mobility, in one or more tranches over 5 years
- Verdict: Pending

## 2025-11-09 · Solar cell plant capex: Pending

- Said: Setting up a 2.2 GW solar DCR cell and PV module plant in Pithampur, Madhya Pradesh (Rs. 12,000 Mn)
- Verdict: Pending

Live record: https://eqdoc.com/stock/SHAKTIPUMP. Not investment advice.