type: "Promise Ledger"
title: "Shilchar Technologies Ltd: what management promised, and what happened"
description: "16 statements by Shilchar Technologies Ltd's management, each checked against the company's later filings: 14 pending, 2 unverifiable."
resource: "https://eqdoc.com/stock/SHILCTECH"
tags: ["promise ledger","management guidance","india","shilctech"]
sources: [{"resource":"https://eqdoc.com/pdf/ann/7451449.pdf"},{"resource":"https://nsearchives.nseindia.com/corporate/SHILCHARTECH_19082026153028_Shilchar_Transcript.pdf"},{"resource":"https://eqdoc.com/pdf/ann/7153258.pdf"},{"resource":"https://nsearchives.nseindia.com/corporate/SHILCHARTECH_11052026100211_Signed_Transcript.pdf"}]
generated: {"by":"process:eqdoc-promise-audit"}
x-eqdoc-symbol: "SHILCTECH"
x-eqdoc-counts: {"kept":0,"slipped":0,"missed":0,"pending":14,"unverifiable":2}
---

# How to read this

Each entry is something management said it would do, when it said it, and whether the company's later filings show it happened.
- **Kept**: a later filing shows it done. **Slipped**: done late or in part. **Missed**: the deadline passed without it.
- **Pending**: the deadline has not come, or no later filing yet speaks to it. **Unverifiable**: no filing could settle it.
- Evidence is either a sentence built from figures the company filed, or a quote from a later company document, as marked.

# Promises

## 2026-10-28 · Additional capacity of 6,500 MVA is expected to come online by April 2027.: Pending

- Said: Additional capacity (6,500 MVA) expected to come online by April 2027 to drive next leg of growth
- By: Company presentation, Investor presentation, 28 Oct 2026
- Due: by April 2027
- Verdict: Pending
- Evidence: Not due until 30 Apr 2027, after the latest results; later ones will show.
- Filing: <https://eqdoc.com/pdf/ann/7451449.pdf> (page 25)

## 2026-10-28 · An additional 1.1 lakh square feet of built-up area is scheduled to come online in 2027.: Pending

- Said: additional 1.1 Lakh Sq.Ft. coming online in 2027
- By: Company presentation, Investor presentation, 28 Oct 2026
- Due: in 2027
- Verdict: Pending
- Evidence: Not due until 31 Dec 2027, after the latest results; later ones will show.
- Filing: <https://eqdoc.com/pdf/ann/7451449.pdf> (page 11)

## 2026-10-28 · Annual capacity is expected to reach 14,000 MVA post-expansion by FY28.: Pending

- Said: 14,000 MVA Annual Capacity Post-Expansion (FY28)
- By: Company presentation, Investor presentation, 28 Oct 2026
- Due: FY28
- Verdict: Pending
- Evidence: Not due until 31 Mar 2028, after the latest results; later ones will show.
- Filing: <https://eqdoc.com/pdf/ann/7451449.pdf> (page 11)

## 2026-10-28 · Gavasad Expansion #3 is progressing as per plan towards commissioning in April 2027.: Pending

- Said: On the project front, Gavasad Expansion #3 is progressing as per plan, with commissioning expected in April 2027.
- By: Company presentation, Investor presentation, 28 Oct 2026
- Due: April 2027
- Verdict: Pending
- Evidence: Not due until 30 Apr 2027, after the latest results; later ones will show.
- Filing: <https://eqdoc.com/pdf/ann/7451449.pdf> (page 7)

## 2026-10-28 · The company expects an order pipeline of approximately ₹800 crore for FY27.: Pending

- Said: Order pipeline for FY27 ~₹800 Cr
- By: Company presentation, Investor presentation, 28 Oct 2026
- Due: FY27
- Verdict: Pending
- Evidence: Not due until 31 Mar 2027, after the latest results; later ones will show.
- Filing: <https://eqdoc.com/pdf/ann/7451449.pdf> (page 25)

## 2026-08-14 · Business momentum is expected to be notably better in Q2 FY27 compared to Q1 FY27.: Pending

- Said: Looking ahead, we expect overall business momentum to be notably better in Q2 compared to Q1
- By: Alay Shah, Q1 FY27 earnings call
- Due: Q2
- Verdict: Pending
- Evidence: Not due until 30 Sep 2026, after the latest results; later ones will show.
- Filing: <https://nsearchives.nseindia.com/corporate/SHILCHARTECH_19082026153028_Shilchar_Transcript.pdf> (page 4)

## 2026-08-14 · Phase-3 expansion adding about 6,500 MVA capacity remains on track for commissioning in April 2027.: Pending

- Said: Our CAPEX project, our expansion Phase-3, which will add about 6,500 MVA capacity, remains on track for commissioning in April 2027.
- By: Alay Shah, Q1 FY27 earnings call
- Due: April 2027
- Verdict: Pending
- Evidence: Not due until 30 Apr 2027, after the latest results; later ones will show.
- Filing: <https://nsearchives.nseindia.com/corporate/SHILCHARTECH_19082026153028_Shilchar_Transcript.pdf> (page 4)

## 2026-08-14 · The company expects to achieve higher margins and EBITDA in upcoming quarters compared to Q1 FY27.: Unverifiable

- Said: Yes, it will be higher. I mean, we hope to achieve more EBITDA.
- By: Alay Shah, Q1 FY27 earnings call
- Due: Q2, Q3
- Verdict: Unverifiable
- Evidence: We could not match this promise to a figure, and no later call settles it.
- Filing: <https://nsearchives.nseindia.com/corporate/SHILCHARTECH_19082026153028_Shilchar_Transcript.pdf> (page 12)

## 2026-08-12 · Commissioning of Gavasad Expansion #3 is expected in April 2027.: Pending

- Said: On the project front, we remain on track with our Gavasad Expansion #3, with commissioning expected in April 2027.
- By: Company presentation, Investor presentation, 12 Aug 2026
- Due: April 2027
- Verdict: Pending
- Evidence: Not due until 30 Apr 2027, after the latest results; later ones will show.
- Filing: <https://eqdoc.com/pdf/ann/7153258.pdf> (page 7)

## 2026-08-12 · Overall business momentum is expected to be notably better in Q2FY27.: Unverifiable

- Said: We expect overall business momentum to be notably better in Q2FY27.
- By: Company presentation, Investor presentation, 12 Aug 2026
- Due: Q2FY27
- Verdict: Unverifiable
- Evidence: The promise is not about sales, the figure we hold that comes nearest; none of our figures settles it, and no later call does.
- Filing: <https://eqdoc.com/pdf/ann/7153258.pdf> (page 7)

## 2026-08-12 · The company remains on track with its revenue ambition for the year despite potential changes in geographic mix.: Pending

- Said: We also remain on track with our revenue ambition for the year, although the geographic mix may change given the ongoing situation in West Asia.
- By: Company presentation, Investor presentation, 12 Aug 2026
- Due: FY27
- Verdict: Pending
- Evidence: Not due until 31 Mar 2027, after the latest results; later ones will show.
- Filing: <https://eqdoc.com/pdf/ann/7153258.pdf> (page 7)

## 2026-05-05 · Existing 7,500 MVA capacity will be operated at almost full utilization during FY27.: Pending

- Said: For financial year '27, we expect to run our existing 7,500 MVA capacity at almost full utilization
- By: Alay Shah, Q4 FY26 earnings call
- Due: financial year '27
- Verdict: Pending
- Evidence: Not due until 31 Mar 2027, after the latest results; later ones will show.
- Filing: <https://nsearchives.nseindia.com/corporate/SHILCHARTECH_11052026100211_Signed_Transcript.pdf> (page 4)

## 2026-05-05 · The Gavasad expansion Phase-3 will add 6,500 MVA capacity and is on track for commissioning in April 2027.: Pending

- Said: our Gavasad expansion number three, which will add 6,500 MVA and take our total installed capacity to 14,000 MVA, remains on track for commissioning in April '27.
- By: Alay Shah, Q4 FY26 earnings call
- Due: April '27
- Verdict: Pending
- Evidence: Not due until 30 Apr 2027, after the latest results; later ones will show.
- Filing: <https://nsearchives.nseindia.com/corporate/SHILCHARTECH_11052026100211_Signed_Transcript.pdf> (page 4)

## 2026-05-05 · The company aims to maintain or increase EBITDA margins in FY27.: Pending

- Said: Yes, we'll do our best to maintain the same margin or even increase the margin.
- By: Alay Shah, Q4 FY26 earnings call
- Due: FY27
- Verdict: Pending
- Evidence: Not due until 31 Mar 2027, after the latest results; later ones will show.
- Filing: <https://nsearchives.nseindia.com/corporate/SHILCHARTECH_11052026100211_Signed_Transcript.pdf> (page 7)

## 2026-05-05 · The company targets delivering around 7,000 MVA in volume for FY27.: Pending

- Said: Around 7,000 MVA.
- By: Alay Shah, Q4 FY26 earnings call
- Due: FY'27
- Verdict: Pending
- Evidence: Not due until 31 Mar 2027, after the latest results; later ones will show.
- Filing: <https://nsearchives.nseindia.com/corporate/SHILCHARTECH_11052026100211_Signed_Transcript.pdf> (page 15)

## 2026-05-05 · The company targets reaching INR 800 crores in revenue for the entire year FY27.: Pending

- Said: Now, so our target for the entire year is INR800 crores and that we are very confident to achieve.
- By: Alay Shah, Q4 FY26 earnings call
- Due: entire year
- Verdict: Pending
- Evidence: Not due until 31 Mar 2027, after the latest results; later ones will show.
- Filing: <https://nsearchives.nseindia.com/corporate/SHILCHARTECH_11052026100211_Signed_Transcript.pdf> (page 5)

Live record: https://eqdoc.com/stock/SHILCTECH. Not investment advice.