title: "Solarworld Energy Solutions Ltd: what management promised, and what happened"
description: "8 statements by Solarworld Energy Solutions Ltd's management, each checked against the company's later filings: 2 slipped, 1 pending, 5 unverifiable."
resource: "https://eqdoc.com/stock/SOLARWORLD"
tags: ["promise ledger","management guidance","india","solarworld"]
sources: [{"resource":"https://nsearchives.nseindia.com/corporate/SUNSHINE123_02022026173443_transcript.pdf"},{"resource":"https://nsearchives.nseindia.com/corporate/SUNSHINE123_24102025145327_TranscriptSigned.pdf"}]
generated: {"by":"process:eqdoc-promise-audit"}
x-eqdoc-symbol: "SOLARWORLD"
x-eqdoc-counts: {"kept":0,"slipped":2,"missed":0,"pending":1,"unverifiable":5}
---

# How to read this

Each entry is something management said it would do, when it said it, and whether the company's later filings show it happened.
- **Kept**: a later filing shows it done. **Slipped**: done late or in part. **Missed**: the deadline passed without it.
- **Pending**: the deadline has not come, or no later filing yet speaks to it. **Unverifiable**: no filing could settle it.
- Evidence is either a sentence built from figures the company filed, or a quote from a later company document, as marked.

# Promises

## 2026-01-28 · Achieve monthly module manufacturing output of 70 MW in February 2026.: Unverifiable

- Said: So we are expecting -- in January, we are expecting about 50 megawatt. In Feb, it should go up to about 70.
- By: Kartik Teltia, Q3 FY26 earnings call
- Due: Feb
- Verdict: Unverifiable
- Evidence: We could not match this promise to a figure, and no later call settles it.
- Filing: <https://nsearchives.nseindia.com/corporate/SUNSHINE123_02022026173443_transcript.pdf> (page 8)

## 2026-01-28 · Commission 3.4 GW BESS manufacturing capacity by around the end of March 2026.: Unverifiable

- Said: BESS will get commissioned in the next couple of months, maybe end of March. So BESS capacity of 3.4 gigawatt will also be available for us to sell in
- By: Kartik Teltia, Q3 FY26 earnings call
- Due: end of March
- Verdict: Unverifiable
- Evidence: We could not match this promise to a figure, and no later call settles it.
- Filing: <https://nsearchives.nseindia.com/corporate/SUNSHINE123_02022026173443_transcript.pdf> (page 20)

## 2025-10-17 · Commission the 1.2 GW solar manufacturing facility at Pandhurna between December 2026 and March 2027.: Pending

- Said: The project is expected to be operational between December 2026 and March 2027.
- By: Kartik Teltia, Q2 FY26 earnings call
- Due: between December 2026 and March 2027
- Verdict: Pending
- Evidence: Not due until 31 Dec 2026, after the latest results; later ones will show.
- Filing: <https://nsearchives.nseindia.com/corporate/SUNSHINE123_24102025145327_TranscriptSigned.pdf> (page 4)

## 2025-10-17 · Commission the 3.4 GW BESS manufacturing line at Roorkee by January 2026.: Slipped

- Said: This line is expected to be operational by January 2026 which is in the next couple of months.
- By: Kartik Teltia, Q2 FY26 earnings call
- Due: by January 2026
- Verdict: Slipped
- Evidence: The Q3 FY26 call, 28 Jan 2026 settles it: “BESS will get commissioned in the next couple of months, maybe end of March. So BESS capacity of 3.4 gigawatt will also be available for us to sell in”
- Filing: <https://nsearchives.nseindia.com/corporate/SUNSHINE123_24102025145327_TranscriptSigned.pdf> (page 4)

## 2025-10-17 · Complete the NTPC green project around March-April 2026.: Slipped

- Said: Internally, we are targeting a timeline of close to March-April 2026 to execute this project.
- By: Kartik Teltia, Q2 FY26 earnings call
- Due: close to March-April 2026
- Verdict: Slipped
- Evidence: The Q3 FY26 call, 28 Jan 2026 settles it: “So both these projects are expected to get finished by May 2026. So that is when you will see the executed capacity going up significantly.”
- Filing: <https://nsearchives.nseindia.com/corporate/SUNSHINE123_24102025145327_TranscriptSigned.pdf> (page 13)

## 2025-10-17 · Execute approximately 60% of the Rs. 2,500 crore order book capacity within FY26.: Unverifiable

- Said: We expect to execute about 60% of this capacity in the current financial year.
- By: Kartik Teltia, Q2 FY26 earnings call
- Due: current financial year
- Verdict: Unverifiable
- Evidence: We could not match this promise to a figure, and no later call settles it.
- Filing: <https://nsearchives.nseindia.com/corporate/SUNSHINE123_24102025145327_TranscriptSigned.pdf> (page 7)

## 2025-10-17 · Have three manufacturing lines operational by the end of FY26.: Unverifiable

- Said: So, by the end of this financial year, three manufacturing lines should be operational.
- By: Kartik Teltia, Q2 FY26 earnings call
- Due: by the end of this financial year
- Verdict: Unverifiable
- Evidence: We could not match this promise to a figure, and no later call settles it.
- Filing: <https://nsearchives.nseindia.com/corporate/SUNSHINE123_24102025145327_TranscriptSigned.pdf> (page 8)

## 2025-10-17 · Operationalize the junction box manufacturing line before March 2026.: Unverifiable

- Said: We expect that also to come, become operational before March 2026.
- By: Kartik Teltia, Q2 FY26 earnings call
- Due: before March 2026
- Verdict: Unverifiable
- Evidence: We could not match this promise to a figure, and no later call settles it.
- Filing: <https://nsearchives.nseindia.com/corporate/SUNSHINE123_24102025145327_TranscriptSigned.pdf> (page 8)