type: "Promise Ledger"
title: "Transformers and Rectifiers (India) Ltd: what management promised, and what happened"
description: "29 statements by Transformers and Rectifiers (India) Ltd's management, each checked against the company's later filings: 2 kept, 3 slipped, 3 missed, 14 pending, 7 unverifiable."
resource: "https://eqdoc.com/stock/TARIL"
tags: ["promise ledger","management guidance","india","taril"]
sources: [{"resource":"https://nsearchives.nseindia.com/corporate/TRIL_25072026134625_TranscriptEarningCall21072026.pdf"},{"resource":"https://nsearchives.nseindia.com/corporate/TRIL_20072026193204_InvestorPresentationQ1202627.pdf"},{"resource":"https://nsearchives.nseindia.com/corporate/TRIL_16012026171422_IntimationTranscript08012026TARIL.pdf"},{"resource":"https://nsearchives.nseindia.com/corporate/TRIL_17112025150353_IntimationTranscriptH1202526TARIL.pdf"},{"resource":"https://nsearchives.nseindia.com/corporate/TRIL_04082025143306_SEIntimationTranscript.pdf"},{"resource":"https://nsearchives.nseindia.com/corporate/TRIL_29012024142814_TranscriptEarningConf22012024.pdf"}]
generated: {"by":"process:eqdoc-promise-audit","at":"2026-11-21"}
stale_after: "2027-03-01"
x-eqdoc-symbol: "TARIL"
x-eqdoc-counts: {"kept":2,"slipped":3,"missed":3,"pending":14,"unverifiable":7}
---

# How to read this

Each entry is something management said it would do, when it said it, and whether the company's later filings show it happened.
- **Kept**: a later filing shows it done. **Slipped**: done late or in part. **Missed**: the deadline passed without it.
- **Pending**: the deadline has not come, or no later filing yet speaks to it. **Unverifiable**: no filing could settle it.
- Evidence is either a sentence built from figures the company filed, or a quote from a later company document, as marked.

# Promises

## 2026-07-21 · Commissioning of CTC facility targeted by Q2 FY27.: Slipped

- Said: CTC facility 8,000 MTPA in Phase I and Phase II is 24,000 MTPA; targeted commissioning by Q2 FY27.
- By: Satyen Mamtora, Q1 FY27 earnings call
- Due: Q2 FY27
- Verdict: Slipped
- Evidence: The Q2 FY27 call, 21 Oct 2026 settles it: “In Q3, before Diwali the plant will be commissioned. Currently, the plant and machinery is being installed. By Diwali, the plant will be commissioned.”
- Filing: <https://nsearchives.nseindia.com/corporate/TRIL_25072026134625_TranscriptEarningCall21072026.pdf> (page 4)

## 2026-07-21 · Targeting 25% revenue growth in FY27 along with EBITDA margin of 16% and PAT margin of 9% to 10%.: Pending

- Said: At TARIL we remain confident of our growth trajectory and are targeting 25% revenue growth in FY27 along with EBITDA margin of 16% and PAT margin of 9% to 10%.
- By: Satyen Mamtora, Q1 FY27 earnings call
- Due: FY27
- Verdict: Pending
- Evidence: Not due until 31 Mar 2027, after the latest results; later ones will show.
- Filing: <https://nsearchives.nseindia.com/corporate/TRIL_25072026134625_TranscriptEarningCall21072026.pdf> (page 5)

## 2026-07-20 · The Changodar plant expansion is expected to be completed by August 2026.: Pending

- Said: Project Expansion is likely to be over by August-26 following which the plant is anticipated to operate at improved utilization levels.
- By: Company presentation, Investor presentation, 20 Jul 2026
- Due: 2026-08-31
- Verdict: Pending
- Evidence: Not due until 31 Aug 2026, after the latest results; later ones will show.

## 2026-07-20 · The company plans to launch the CTC facility with 8,000 MTPA (Phase I) capacity by Q2 FY27.: Pending

- Said: CTC 8,000 MTPA*; 24,000 MTPA** Q2FY27
- By: Company presentation, Investor presentation, 20 Jul 2026
- Due: 2026-09-30
- Verdict: Pending
- Evidence: Not due until 30 Sep 2026, after the latest results; later ones will show.

## 2026-07-20 · The company plans to launch the Fabrication facility with 25,000 MTPA (Phase I) capacity by Q1 FY28.: Pending

- Said: Fabrication 25,000 MTPA*; 50,000 MTPA** Q1FY28
- By: Company presentation, Investor presentation, 20 Jul 2026
- Due: 2027-06-30
- Verdict: Pending
- Evidence: Not due until 30 Jun 2027, after the latest results; later ones will show.

## 2026-07-20 · The company plans to launch the Pressboard facility with 5,000 MTPA (Phase I) capacity by Q3 FY27.: Pending

- Said: Pressboard (Insulation) 5,000 MTPA*; 10,000 MTPA** Q3FY27
- By: Company presentation, Investor presentation, 20 Jul 2026
- Due: 2026-12-31
- Verdict: Pending
- Evidence: Not due until 31 Dec 2026, after the latest results; later ones will show.

## 2026-07-20 · The company plans to launch the RIP/OIP Bushings facility with 3,000 units (Phase I) capacity by Q4 FY27.: Pending

- Said: RIP/OIP Bushings 3,000 No. PA*; 6,000 No. PA** Q4FY27
- By: Company presentation, Investor presentation, 20 Jul 2026
- Due: 2027-03-31
- Verdict: Pending
- Evidence: Not due until 31 Mar 2027, after the latest results; later ones will show.

## 2026-07-20 · The company targets 16% EBITDA margin for FY27.: Pending

- Said: FY27 Outlook: Targeting 25% revenue growth with EBITDA margin of 16% and PAT margin 9%-10%.
- By: Company presentation, Investor presentation, 20 Jul 2026
- Due: 2027-03-31
- Verdict: Pending
- Evidence: Not due until 31 Mar 2027, after the latest results; later ones will show.

## 2026-07-20 · The company targets commercial commissioning of all backward integration facilities by Q1 FY28.: Pending

- Said: Commercial commissioning of all facilities put together targeted by Q1 FY28 (after considering delay of up to one quarter)
- By: Company presentation, Investor presentation, 20 Jul 2026
- Due: 2027-06-30
- Verdict: Pending
- Evidence: Not due until 30 Jun 2027, after the latest results; later ones will show.

## 2026-07-20 · Backward integration commissioning: Pending

- Said: Backward Integration: Commercial commissioning of all facilities put together targeted by Q1 FY28 (after considering delay of up to one quarter)
- Due: Q1FY28
- Verdict: Pending
- Filing: <https://nsearchives.nseindia.com/corporate/TRIL_20072026193204_InvestorPresentationQ1202627.pdf>

## 2026-01-08 · Changodar expansion completion in Q1 FY27.: Unverifiable

- Said: Our Changodar facility expansion is on track and completion on Q1 FY '26-27, while Moraiya is expected to be operational in Q2 FY '26-'27.
- By: Satyen Mamtora, Q3 FY26 earnings call
- Due: Q1 FY '26-27 and Q2 FY '26-'27
- Verdict: Unverifiable
- Evidence: We could not match this promise to a figure, and no later call settles it.
- Filing: <https://nsearchives.nseindia.com/corporate/TRIL_16012026171422_IntimationTranscript08012026TARIL.pdf> (page 4)

## 2026-01-08 · Full-year FY26 EBITDA margin targeted at around 16%.: Missed

- Said: We are targeting revenues of approximately INR2,600 crores along with EBITDA margin of around 16%.
- By: Satyen Mamtora, Q3 FY26 earnings call
- Due: FY '26
- Verdict: Missed
- Evidence: Operating margin for FY26 came to 15.3% — short of the 16% promised, with the window closed.
- Filing: <https://nsearchives.nseindia.com/corporate/TRIL_16012026171422_IntimationTranscript08012026TARIL.pdf> (page 4)

## 2025-11-10 · Changodar expansion expected to be operational in the next quarter (Q3 FY26).: Slipped

- Said: while Changodar expansion is slightly delayed due to the monsoon and equipment delivery issues, is expected to be operational in the next quarter.
- By: Satyen Mamtora, Q2 FY26 earnings call
- Due: in the next quarter
- Verdict: Slipped
- Evidence: The Q3 FY26 call, 16 Jan 2026 settles it: “Our Changodar facility expansion is on track and completion on Q1 FY '26-27, while Moraiya is expected to be operational in Q2 FY '26-'27.”
- Filing: <https://nsearchives.nseindia.com/corporate/TRIL_17112025150353_IntimationTranscriptH1202526TARIL.pdf> (page 3)

## 2025-11-10 · Execution of around ₹1,600 crores to ₹1,700 crores over Q3 and Q4 FY26.: Missed

- Said: We are hoping that in this next 2 months -- 2 quarters' time, we will be somewhere around INR1,600 crores to INR1,700 crores of execution.
- By: Chanchal Rajora, Q2 FY26 earnings call
- Due: in this next 2 months -- 2 quarters' time
- Verdict: Missed
- Evidence: Sales for the Mar 2026 quarter came to ₹783 cr — short of the ₹1,600 cr promised, with the window closed.
- Filing: <https://nsearchives.nseindia.com/corporate/TRIL_17112025150353_IntimationTranscriptH1202526TARIL.pdf> (page 6)

## 2025-11-10 · Full-year FY26 revenue target of around ₹2,600 crores with approximately 16% EBITDA margin.: Missed

- Said: For the full year, we remain confident to achieving at least 25% revenue growth over FY '26, with target of around INR2,600 crores with EBITDA margin of approximately 16%.
- By: Satyen Mamtora, Q2 FY26 earnings call
- Due: full year
- Verdict: Missed
- Evidence: Sales for FY26 came to ₹2,509 cr — short of the ₹2,600 cr promised, with the window closed.
- Filing: <https://nsearchives.nseindia.com/corporate/TRIL_17112025150353_IntimationTranscriptH1202526TARIL.pdf> (page 3)

## 2025-08-01 · Moraiya plant expansion to be operational by the end of Q2 FY26.: Slipped

- Said: The expansion yes, yes. The expansion of Moraiya plant should be operational by end of quarter 2.
- By: Satyen Mamtora, Q1 FY26 earnings call
- Due: by end of quarter 2
- Verdict: Slipped
- Evidence: The Q3 FY26 call, 16 Jan 2026 settles it: “Our Changodar facility expansion is on track and completion on Q1 FY '26-27, while Moraiya is expected to be operational in Q2 FY '26-'27.”
- Filing: <https://nsearchives.nseindia.com/corporate/TRIL_04082025143306_SEIntimationTranscript.pdf> (page 8)

## 2025-08-04 · Reaching USD 1 billion in revenue over the next 3 financial years.: Unverifiable

- Said: I am pleased to share that we remain firmly in our track journey towards achieving USD1 billion in revenue over the next 3 financial years.
- By: Satyen Mamtora, Q1 FY26 earnings call
- Due: over the next 3 financial years
- Verdict: Unverifiable
- Evidence: We could not match this promise to a figure, and no later call settles it.
- Filing: <https://nsearchives.nseindia.com/corporate/TRIL_04082025143306_SEIntimationTranscript.pdf> (page 3)

## 2025-08-04 · Targeting around ₹3,500 crores of turnover for the current financial year (FY26).: Unverifiable

- Said: So on 1st April 2026, our unexecuted order book would be INR5,000 crores, and we are expecting around INR3,500 crores of turnover of this -- on this year.
- By: Satyen Mamtora, Q1 FY26 earnings call
- Due: on 1st April 2026
- Verdict: Unverifiable
- Evidence: We could not match this promise to a figure, and no later call settles it.
- Filing: <https://nsearchives.nseindia.com/corporate/TRIL_04082025143306_SEIntimationTranscript.pdf> (page 6)

## 2025-08-01 · Become a net debt-free company within 18 to 24 months.: Pending

- Said: progression towards becoming a net debt-free company next over 18 to 24 months.
- By: Chanchal Rajora, Q1 FY26 earnings call
- Due: next over 18 to 24 months
- Verdict: Pending
- Evidence: Not due until 31 Aug 2027, after the latest results; later ones will show.
- Filing: <https://nsearchives.nseindia.com/corporate/TRIL_04082025143306_SEIntimationTranscript.pdf> (page 4)

## 2025-04-08 · The company expects exports to account for 10% of its total turnover next year.: Unverifiable

- Said: So we are - we would be doing around 10% of our total turnover next year in exports.
- By: Satyen Mamtora, Q4 FY25 earnings call
- Verdict: Unverifiable
- Evidence: We could not match this promise to a figure, and no later call settles it.

## 2025-04-08 · The company expects to reach 80% capacity utilization next year.: Unverifiable

- Said: Next year, we should reach about 80% utilization.
- By: Satyen Mamtora, Q4 FY25 earnings call
- Verdict: Unverifiable
- Evidence: We could not match this promise to a figure, and no later call settles it.

## 2025-01-08 · The company targets an order book exceeding INR 4,000 crores by the end of the current financial year.: Unverifiable

- Said: we will be having an order book of INR4,000 crores plus by the end of this financial year.
- By: Chanchal Rajora, Q3 FY25 earnings call
- Verdict: Unverifiable
- Evidence: We could not match this promise to a figure, and no later call settles it.

## 2024-10-08 · The company will begin commercial production for its new 15,000 MVA capacity in January 2025.: Unverifiable

- Said: The first phase of new capacity addition of 15,000 MVA will start for commercial production from January 2025.
- By: Jitendra Mamtora, Q2 FY25 earnings call
- Due: in January 2025
- Verdict: Unverifiable
- Evidence: We could not match this promise to a figure, and no later call settles it.

## 2024-01-29 · Capex expansion initiation: Kept

- Said: And as I explained to you, for the additional new revenues, next year will be coming up a capex expansion.
- Due: FY25
- Verdict: Kept
- Later filing says (2025-04-15): Launched two major capacity expansions. 15,000 MVA capacity expansion started in April 2024, the Phase 1 operation by May 2025.
- Filing: <https://nsearchives.nseindia.com/corporate/TRIL_29012024142814_TranscriptEarningConf22012024.pdf>

## 2024-01-29 · EBITDA margin guidance: Pending

- Said: 13%-14%, what we had said, we have said it from the financial year of 2026-27 and Financial Year 27-28. So that we still foresee that it will be on that level only.
- Due: FY27
- Verdict: Pending
- Filing: <https://nsearchives.nseindia.com/corporate/TRIL_29012024142814_TranscriptEarningConf22012024.pdf>

## 2024-01-29 · Export network and maintenance team expansion: Pending

- Said: And shortly, maybe in another six months' time, we will have proper people at proper places for the supply and also for looking after the maintenance of the transformers.
- Due: 2024-07-31
- Verdict: Pending
- Filing: <https://nsearchives.nseindia.com/corporate/TRIL_29012024142814_TranscriptEarningConf22012024.pdf>

## 2024-01-29 · Industry average EBITDA margin: Kept

- Said: The 10%-12% what I just mentioned to Subhadip is the industry average which we will achieve in coming financial year. That is what I explained.
- Due: FY25
- Verdict: Kept
- Later filing says (2025-04-15): EBITDA margin improved to 16.12% for the entire year as compared to 10.03% in FY '24, indicating better operating leverage and cost efficiency measures taken by the organization.
- Filing: <https://nsearchives.nseindia.com/corporate/TRIL_29012024142814_TranscriptEarningConf22012024.pdf>

## 2024-01-29 · Order book execution timeline: Pending

- Said: the order book we have right now is for the next 15 months to 18 months delivery period. And we expect that we will be able to deliver these orders into the prescribed time.
- Due: FY25
- Verdict: Pending
- Filing: <https://nsearchives.nseindia.com/corporate/TRIL_29012024142814_TranscriptEarningConf22012024.pdf>

## 2024-01-29 · Working capital days reduction: Pending

- Said: In terms of the absolute numbers, number of days, if you see that we are working on the direction to bring down the working capital days up to 120 days.
- Verdict: Pending
- Filing: <https://nsearchives.nseindia.com/corporate/TRIL_29012024142814_TranscriptEarningConf22012024.pdf>

Live record: https://eqdoc.com/stock/TARIL. Not investment advice.