type: "Promise Ledger"
title: "Tembo Global Industries Limited: what management promised, and what happened"
description: "18 statements by Tembo Global Industries Limited's management, each checked against the company's later filings: 3 slipped, 13 pending, 2 unverifiable."
resource: "https://eqdoc.com/stock/TEMBO"
tags: ["promise ledger","management guidance","india","tembo"]
sources: [{"resource":"https://nsearchives.nseindia.com/corporate/TEMBO_25082026171822_Transcriptfinal_sd.pdf"},{"resource":"https://nsearchives.nseindia.com/corporate/TEMBO_18082026105620_Tembo_global_presentation_Q1_FY27_SD.pdf"},{"resource":"https://nsearchives.nseindia.com/corporate/TEMBO_11022026150819_Announucement_transcript_sd.pdf"},{"resource":"https://nsearchives.nseindia.com/corporate/TEMBO_20082025164421_concallscript.pdf"}]
generated: {"by":"process:eqdoc-promise-audit"}
x-eqdoc-symbol: "TEMBO"
x-eqdoc-counts: {"kept":0,"slipped":3,"missed":0,"pending":13,"unverifiable":2}
---

# How to read this

Each entry is something management said it would do, when it said it, and whether the company's later filings show it happened.
- **Kept**: a later filing shows it done. **Slipped**: done late or in part. **Missed**: the deadline passed without it.
- **Pending**: the deadline has not come, or no later filing yet speaks to it. **Unverifiable**: no filing could settle it.
- Evidence is either a sentence built from figures the company filed, or a quote from a later company document, as marked.

# Promises

## 2026-08-19 · Commence UAV component manufacturing from Vasai facility in Q3 FY27.: Pending

- Said: We also expect to commence UAV component manufacturing from our Vasai facility in Q3 FY27.
- By: Shabbir Merchant, Q1 FY27 earnings call
- Due: Q3 FY27
- Verdict: Pending
- Evidence: Not due until 31 Dec 2026, after the latest results; later ones will show.
- Filing: <https://nsearchives.nseindia.com/corporate/TEMBO_25082026171822_Transcriptfinal_sd.pdf> (page 4)

## 2026-08-19 · Commission remaining solar project sites in Q2 FY27.: Pending

- Said: the remaining sites are on track for commissioning in Q2 FY27.
- By: Shabbir Merchant, Q1 FY27 earnings call
- Due: Q2 FY27
- Verdict: Pending
- Evidence: Not due until 30 Sep 2026, after the latest results; later ones will show.
- Filing: <https://nsearchives.nseindia.com/corporate/TEMBO_25082026171822_Transcriptfinal_sd.pdf> (page 3)

## 2026-08-18 · Commercial operations for the solar portfolio are scheduled to start in the third quarter of FY27.: Pending

- Said: Commercial operations are scheduled to commence from Q3FY27
- By: Company presentation, Investor presentation, 18 Aug 2026
- Due: 2026-12-31
- Verdict: Pending
- Evidence: Not due until 31 Dec 2026, after the latest results; later ones will show.
- Filing: <https://nsearchives.nseindia.com/corporate/TEMBO_18082026105620_Tembo_global_presentation_Q1_FY27_SD.pdf> (page 5)

## 2026-08-18 · Construction of the defence facility is expected to start by August 2026, with commercial production targeted for Q1FY28: Pending

- Said: construction expected to begin by August 2026 and commercial production targeted from Q1FY28.
- By: Company presentation, Investor presentation, 18 Aug 2026
- Due: 2027-06-30
- Verdict: Pending
- Evidence: Not due until 30 Jun 2027, after the latest results; later ones will show.
- Filing: <https://nsearchives.nseindia.com/corporate/TEMBO_18082026105620_Tembo_global_presentation_Q1_FY27_SD.pdf> (page 5)

## 2026-08-18 · The UAV joint venture aims to generate approximately INR 100 Crores in revenue during its first year.: Pending

- Said: Tembo Global UAV JV targets revenue of ~ INR 100 Crores in its first year of operations
- By: Company presentation, Investor presentation, 18 Aug 2026
- Verdict: Pending
- Evidence: Not due yet, so it can't be checked.
- Filing: <https://nsearchives.nseindia.com/corporate/TEMBO_18082026105620_Tembo_global_presentation_Q1_FY27_SD.pdf> (page 35)

## 2026-08-18 · The Vasai facility has a potential revenue capacity of INR 700 Crores at peak utilization.: Unverifiable

- Said: Vasai Capacity’s Revenue Potential at Peak Utilization: INR 700 Crores
- By: Company presentation, Investor presentation, 18 Aug 2026
- Verdict: Unverifiable
- Evidence: We could not match this promise to a figure, and no later call settles it.
- Filing: <https://nsearchives.nseindia.com/corporate/TEMBO_18082026105620_Tembo_global_presentation_Q1_FY27_SD.pdf> (page 30)

## 2026-08-18 · The company expects to reach a revenue of INR 1,600 Crores in FY27.: Pending

- Said: the Company remains confident of achieving its FY27 revenue guidance of INR 1,600 Crores.
- By: Company presentation, Investor presentation, 18 Aug 2026
- Due: 2027-03-31
- Verdict: Pending
- Evidence: Not due until 31 Mar 2027, after the latest results; later ones will show.
- Filing: <https://nsearchives.nseindia.com/corporate/TEMBO_18082026105620_Tembo_global_presentation_Q1_FY27_SD.pdf> (page 5)

## 2026-08-18 · The company has a long-term vision to achieve over INR 5,000 Crores in revenue by FY31.: Pending

- Said: Vision INR 5,000+ Crore by FY31
- By: Company presentation, Investor presentation, 18 Aug 2026
- Due: 2031-03-31
- Verdict: Pending
- Evidence: Not due until 31 Mar 2031, after the latest results; later ones will show.
- Filing: <https://nsearchives.nseindia.com/corporate/TEMBO_18082026105620_Tembo_global_presentation_Q1_FY27_SD.pdf> (page 37)

## 2026-08-18 · The company plans to start UAV component manufacturing at its Vasai facility in the third quarter of FY27.: Pending

- Said: UAV component manufacturing at the Vasai facility is scheduled to commence in Q3FY27
- By: Company presentation, Investor presentation, 18 Aug 2026
- Due: 2026-12-31
- Verdict: Pending
- Evidence: Not due until 31 Dec 2026, after the latest results; later ones will show.
- Filing: <https://nsearchives.nseindia.com/corporate/TEMBO_18082026105620_Tembo_global_presentation_Q1_FY27_SD.pdf> (page 5)

## 2026-08-18 · The remaining solar project sites are expected to be commissioned in the second quarter of FY27.: Pending

- Said: remaining sites expected to be commissioned in Q2FY27.
- By: Company presentation, Investor presentation, 18 Aug 2026
- Due: 2026-09-30
- Verdict: Pending
- Evidence: Not due until 30 Sep 2026, after the latest results; later ones will show.
- Filing: <https://nsearchives.nseindia.com/corporate/TEMBO_18082026105620_Tembo_global_presentation_Q1_FY27_SD.pdf> (page 5)

## 2026-08-18 · The solar project portfolio has a revenue potential of approximately INR 80 Crores in FY27.: Pending

- Said: Revenue Potential of ~ INR 80 Crores in FY27
- By: Company presentation, Investor presentation, 18 Aug 2026
- Due: 2027-03-31
- Verdict: Pending
- Evidence: Not due until 31 Mar 2027, after the latest results; later ones will show.
- Filing: <https://nsearchives.nseindia.com/corporate/TEMBO_18082026105620_Tembo_global_presentation_Q1_FY27_SD.pdf> (page 31)

## 2026-02-05 · Commence commercial production for the Defence segment by September end or October 2026.: Slipped

- Said: So maximum to maximum, September end or October we should start commercial production for Defence.
- By: Sanjay Patel, Q3 FY26 earnings call
- Due: September end or October
- Verdict: Slipped
- Evidence: The Q1 FY27 call, 19 Aug 2026 settles it: “So, we are planning to manufacture the first batch to come out on the Q4 FY27.”
- Filing: <https://nsearchives.nseindia.com/corporate/TEMBO_11022026150819_Announucement_transcript_sd.pdf> (page 4)

## 2026-02-05 · Generate FY27 defense segment revenue of Rs. 125 to Rs. 150 crore.: Slipped

- Said: FY27, you can expect Rs. 125 to Rs. 150 crore.
- By: Sanjay Patel, Q3 FY26 earnings call
- Due: FY27
- Verdict: Slipped
- Evidence: The Q1 FY27 call, 19 Aug 2026 settles it: “we look at around, in a range of around INR 70 crores to INR 100 crores of revenue in this particular quarter.”
- Filing: <https://nsearchives.nseindia.com/corporate/TEMBO_11022026150819_Announucement_transcript_sd.pdf> (page 5)

## 2026-02-05 · Separate the legacy textile business segment by 2027.: Pending

- Said: So we are planning to get it separated by 2027.
- By: Sanjay Patel, Q3 FY26 earnings call
- Due: 2027
- Verdict: Pending
- Evidence: Not due until 31 Dec 2027, after the latest results; later ones will show.
- Filing: <https://nsearchives.nseindia.com/corporate/TEMBO_11022026150819_Announucement_transcript_sd.pdf> (page 15)

## 2025-08-18 · Achieve consolidated revenue of Rs. 1,400 crore to Rs. 1,500 crore in FY27.: Pending

- Said: So, you can see in a range of around Rs. 1400 crore to Rs. 1500 crore, I rather let the Street be surprised.
- By: Shabbir Merchant, Q1 FY26 earnings call
- Due: FY ‘26-27
- Verdict: Pending
- Evidence: Not due until 31 Mar 2027, after the latest results; later ones will show.
- Filing: <https://nsearchives.nseindia.com/corporate/TEMBO_20082025164421_concallscript.pdf> (page 6)

## 2025-08-18 · Commission solar project by the end of FY26 alongside a 25-year PPA.: Slipped

- Said: This commissioning is expected by the end of FY ‘26 alongside a 25-year PPA from the completion date.
- By: Shabbir Merchant, Q1 FY26 earnings call
- Due: end of FY ‘26
- Verdict: Slipped
- Evidence: The Q1 FY27 call, 19 Aug 2026 settles it: “the remaining sites are on track for commissioning in Q2 FY27.”
- Filing: <https://nsearchives.nseindia.com/corporate/TEMBO_20082025164421_concallscript.pdf> (page 4)

## 2025-08-18 · Deliver PAT of Rs. 200 crore plus in FY27.: Pending

- Said: And we are looking at a PAT of around Rs. 200 crore plus.
- By: Shabbir Merchant, Q1 FY26 earnings call
- Due: FY ‘26-27
- Verdict: Pending
- Evidence: Not due until 31 Mar 2027, after the latest results; later ones will show.
- Filing: <https://nsearchives.nseindia.com/corporate/TEMBO_20082025164421_concallscript.pdf> (page 6)

## 2025-08-18 · Expand production capacity six-fold to 90,000 metric tonnes per annum by end of Q2 FY26.: Unverifiable

- Said: Currently, we are undertaking a capital expenditure initiative aimed at expanding our capacity six-fold, targeting an impressive 90,000 metric tonnes per annum, which we expect to commission by the end of Q2 FY ‘26
- By: Shabbir Merchant, Q1 FY26 earnings call
- Due: Q2 FY ‘26
- Verdict: Unverifiable
- Evidence: We could not match this promise to a figure, and no later call settles it.
- Filing: <https://nsearchives.nseindia.com/corporate/TEMBO_20082025164421_concallscript.pdf> (page 3)

Live record: https://eqdoc.com/stock/TEMBO. Not investment advice.