type: "Promise Ledger"
title: "Timken India Ltd: what management promised, and what happened"
description: "13 statements by Timken India Ltd's management, each checked against the company's later filings: 2 kept, 2 slipped, 3 missed, 4 pending, 2 unverifiable."
resource: "https://eqdoc.com/stock/TIMKEN"
tags: ["promise ledger","management guidance","india","timken"]
sources: [{"resource":"https://nsearchives.nseindia.com/corporate/TIMKEN_13022026173234_SE_Transcript_InvestorsMeet.pdf"},{"resource":"https://nsearchives.nseindia.com/corporate/TIMKEN_14022025171955_SEIntimation_Transcript.pdf"},{"resource":"https://nsearchives.nseindia.com/corporate/TIMKEN_27022024162358_SEIntimation_Transcript.pdf"}]
generated: {"by":"process:eqdoc-promise-audit","at":"2026-10-07"}
stale_after: "2027-01-15"
x-eqdoc-symbol: "TIMKEN"
x-eqdoc-counts: {"kept":2,"slipped":2,"missed":3,"pending":4,"unverifiable":2}
---

# How to read this

Each entry is something management said it would do, when it said it, and whether the company's later filings show it happened.
- **Kept**: a later filing shows it done. **Slipped**: done late or in part. **Missed**: the deadline passed without it.
- **Pending**: the deadline has not come, or no later filing yet speaks to it. **Unverifiable**: no filing could settle it.
- Evidence is either a sentence built from figures the company filed, or a quote from a later company document, as marked.

# Promises

## 2026-02-09 · The company expects margins to return to the 17%-18% range.: Unverifiable

- Said: And once these 3 things happen, so we will definitely see the margin at a very close to what the numbers you are referring to.
- By: Sujit Pattanaik, Q3 FY26 earnings call
- Verdict: Unverifiable
- Evidence: We could not match this promise to a figure, and no later call settles it.
- Filing: <https://nsearchives.nseindia.com/corporate/TIMKEN_13022026173234_SE_Transcript_InvestorsMeet.pdf> (page 8)

## 2025-02-14 · Bharuch plant FY26 capacity utilization: Pending

- Said: the intent is that we should at least fill up the plant in the first year to 50% to 60% of the capacity.
- Due: FY26
- Verdict: Pending
- Filing: <https://nsearchives.nseindia.com/corporate/TIMKEN_14022025171955_SEIntimation_Transcript.pdf>

## 2025-02-14 · Bharuch plant multi-year capacity utilization: Pending

- Said: 70% to 75% next year. And by third year, we are fully capacity utilized. That would be the target.
- Due: FY28
- Verdict: Pending
- Filing: <https://nsearchives.nseindia.com/corporate/TIMKEN_14022025171955_SEIntimation_Transcript.pdf>

## 2025-02-14 · Capacity utilization roadmap Bharuch: Pending

- Said: I would say that 50%, 60% by the end of next year, 70-ish percent 1 year down the line after that and 85% by the end of 3 years would be a great achievement
- Due: FY28
- Verdict: Pending
- Filing: <https://nsearchives.nseindia.com/corporate/TIMKEN_14022025171955_SEIntimation_Transcript.pdf>

## 2025-02-14 · Initial PPAPs at Bharuch plant: Kept

- Said: We should be able to start doing some kind of initial PPAPs by the end of the March, hopefully. That is the target.
- Due: 2025-03-31
- Verdict: Kept
- Later filing says (2025-06-02): PPAPs are happening. In fact, today, we shipped the first (inaudible) to the customer.
- Filing: <https://nsearchives.nseindia.com/corporate/TIMKEN_14022025171955_SEIntimation_Transcript.pdf>

## 2025-02-10 · The company expects to begin initial Production Part Approval Process (PPAP) for the new plant by the end of March.: Slipped

- Said: We should be able to start doing some kind of initial PPAPs by the end of the March, hopefully.
- By: Sanjay Koul, Q3 FY25 earnings call
- Verdict: Slipped
- Evidence: The Q4 FY25 call, 27 May 2025 settles it: “So by the end of June, we'll start really producing.”

## 2025-02-10 · The company expects to reach 50% capacity utilization at the new plant by the end of the year.: Pending

- Said: I hope that we hit 50% capacity utilization by the end of the year.
- By: Sanjay Koul, Q3 FY25 earnings call
- Verdict: Pending
- Evidence: Not due yet, so it can't be checked.

## 2024-11-06 · The company aims to commission the Bharuch plant by the first quarter.: Unverifiable

- Said: we are working towards as fast as possible, some months here and there, but endeavour is first quarter-ish, somewhere like that.
- By: Sanjay Koul, Q2 FY25 earnings call
- Verdict: Unverifiable
- Evidence: We could not match this promise to a figure, and no later call settles it.

## 2024-08-09 · The company expects to start production at the new Bharuch facility in early January next year.: Slipped

- Said: And hopefully, by the end of this year, we'll start the PPAPs and things like that and then, next year, early January, we'll start producing.
- By: Sanjay Koul, Q1 FY25 earnings call
- Verdict: Slipped
- Evidence: The Q4 FY25 call, 27 May 2025 settles it: “So by the end of June, we'll start really producing.”

## 2024-02-27 · Bharuch plant PPAP commencement: Missed

- Said: And hopefully by end of this year, we should be starting to move the PPAP.
- Due: 2024-12-31
- Verdict: Missed
- Later filing says (2025-02-14): We should be able to start doing some kind of initial PPAPs by the end of the March, hopefully. That is the target.
- Filing: <https://nsearchives.nseindia.com/corporate/TIMKEN_27022024162358_SEIntimation_Transcript.pdf>

## 2024-02-27 · Bharuch plant building completion: Kept

- Said: The building should be completed by July. That means that when I say completed means that we can move the assets in position.
- Due: 2024-07-31
- Verdict: Kept
- Later filing says (2024-08-14): As we speak, our main shop flooring is complete; PEB, which is the building and the roof sheeting is complete.
- Filing: <https://nsearchives.nseindia.com/corporate/TIMKEN_27022024162358_SEIntimation_Transcript.pdf>

## 2024-02-27 · Bharuch plant customer supplies: Missed

- Said: Hopefully next year by this time we will be supplying to the Indian customers out of that plant, supplying to experts as well out of this plant.
- Due: 2025-02-28
- Verdict: Missed
- Later filing says (2025-08-07): Bharuch plant continues to stabilize well. We have successfully capitalized 1 CRB line, and we have commenced the commercial production in late June there. And obviously, we have started invoicing from July.
- Filing: <https://nsearchives.nseindia.com/corporate/TIMKEN_27022024162358_SEIntimation_Transcript.pdf>

## 2024-02-27 · Bharuch plant equipment delivery: Missed

- Said: Between now and the next two or three months all the assets will be there.
- Due: 2024-05-31
- Verdict: Missed
- Later filing says (2024-11-11): The machines are already -the box machines we received from Italy, Switzerland, Japan, etcetera. So -- and more machines are coming in.
- Filing: <https://nsearchives.nseindia.com/corporate/TIMKEN_27022024162358_SEIntimation_Transcript.pdf>

Live record: https://eqdoc.com/stock/TIMKEN. Not investment advice.