type: "Promise Ledger"
title: "Torrent Power Ltd: what management promised, and what happened"
description: "16 statements by Torrent Power Ltd's management, each checked against the company's later filings: 12 pending, 4 unverifiable."
resource: "https://eqdoc.com/stock/TORNTPOWER"
tags: ["promise ledger","management guidance","india","torntpower"]
sources: [{"resource":"https://nsearchives.nseindia.com/corporate/TORNTPOWER_13022026180443_Intimation.pdf"},{"resource":"https://nsearchives.nseindia.com/corporate/TORNTPOWER_07082025124239_Transcript.pdf"}]
generated: {"by":"process:eqdoc-promise-audit","at":"2026-09-28"}
stale_after: "2027-01-06"
x-eqdoc-symbol: "TORNTPOWER"
x-eqdoc-counts: {"kept":0,"slipped":0,"missed":0,"pending":12,"unverifiable":4}
---

# How to read this

Each entry is something management said it would do, when it said it, and whether the company's later filings show it happened.
- **Kept**: a later filing shows it done. **Slipped**: done late or in part. **Missed**: the deadline passed without it.
- **Pending**: the deadline has not come, or no later filing yet speaks to it. **Unverifiable**: no filing could settle it.
- Evidence is either a sentence built from figures the company filed, or a quote from a later company document, as marked.

# Promises

## 2026-08-03 · The company aims to expand its renewable energy portfolio to approximately 6.25 GWp.: Pending

- Said: Target to Increase Renewable Portfolio to ~6.25 GWp
- By: Company presentation, Investor presentation, 3 Aug 2026
- Verdict: Pending
- Evidence: Not due yet, so it can't be checked.

## 2026-08-03 · The company expects to commission the SECI XII and SECI XVI projects partly in FY27 and the balance in FY28.: Pending

- Said: Partly in FY27 & balance in FY28
- By: Company presentation, Investor presentation, 3 Aug 2026
- Due: in FY27
- Verdict: Pending
- Evidence: Not due until 31 Mar 2027, after the latest results; later ones will show.

## 2026-08-03 · The company expects to commission the SECI XVIII project in FY28.: Pending

- Said: In FY28
- By: Company presentation, Investor presentation, 3 Aug 2026
- Due: in FY28
- Verdict: Pending
- Evidence: Not due until 31 Mar 2028, after the latest results; later ones will show.

## 2026-08-03 · The company expects to commission the TPL-D renewable project progressively from FY27 to FY29.: Pending

- Said: Progressively from FY27 to FY29
- By: Company presentation, Investor presentation, 3 Aug 2026
- Due: from FY27
- Verdict: Pending
- Evidence: Not due until 31 Mar 2027, after the latest results; later ones will show.

## 2026-08-03 · The company has a total planned capacity of 8.4 GW, which includes 3 GW currently under construction.: Pending

- Said: Total Planned Capacity: 8.4 GW (including 3 GW under construction)
- By: Company presentation, Investor presentation, 3 Aug 2026
- Verdict: Pending
- Evidence: Not due yet, so it can't be checked.

## 2026-08-03 · The company is developing a 3 GW pumped storage hydro project.: Pending

- Said: 3 GW Pumped Storage Hydro Project – Under Development
- By: Company presentation, Investor presentation, 3 Aug 2026
- Verdict: Pending
- Evidence: Not due yet, so it can't be checked.

## 2026-08-03 · The company plans to increase its operational capacity from approximately 6.6 GWp to 12.3 GWp.: Pending

- Said: Operational Capacity is estimated to Grow from ~6.6 GWp to ~12.3 GWp
- By: Company presentation, Investor presentation, 3 Aug 2026
- Verdict: Pending
- Evidence: Not due yet, so it can't be checked.

## 2026-08-03 · The scheduled commercial operation date for the TPL-D (FDRE) project is 24 months from the PPA date.: Pending

- Said: SCOD 24 months from PPA
- By: Company presentation, Investor presentation, 3 Aug 2026
- Verdict: Pending
- Evidence: Not due until 31 Aug 2028, after the latest results; later ones will show.

## 2026-08-03 · The scheduled commercial operation date for the pumped storage hydro project is October 2028.: Pending

- Said: SCOD: Oct’28
- By: Company presentation, Investor presentation, 3 Aug 2026
- Verdict: Pending
- Evidence: Not due until 31 Dec 2028, after the latest results; later ones will show.

## 2026-08-03 · The scheduled commercial operation dates for the Anuppur coal project units are 66 and 72 months from PPA execution.: Pending

- Said: Unit 1: 66 months & Unit 2: 72 Months from PPA Execution
- By: Company presentation, Investor presentation, 3 Aug 2026
- Verdict: Pending
- Evidence: Not due until 31 Aug 2032, after the latest results; later ones will show.

## 2025-12-31 · The company will make the transcript of the Q3 FY26 earnings call available on its website.: Unverifiable

- Said: Transcript of Earnings Conference call with Analysts / Investors on Unaudited Financial Results (Consolidated and Standalone) of the Company for the quarter and nine months ended December 31, 2025
- By: Rahul Shah, Q2 FY26 earnings call
- Verdict: Unverifiable
- Evidence: We could not match this promise to a figure, and no later call settles it.
- Filing: <https://nsearchives.nseindia.com/corporate/TORNTPOWER_13022026180443_Intimation.pdf> (page 1)

## 2025-11-11 · Khavda transmission project implementation timeline: Pending

- Said: Expected project cost ₹ 800 Crore Expected Implementation: FY26
- Due: FY26
- Verdict: Pending

## 2025-11-11 · Thermal power expansion project timeline: Pending

- Said: SCOD: Unit 1: 66 months & Unit 2: 72 Months from PPA Execution
- Verdict: Pending

## 2025-06-30 · The company will make the transcript of the Q1 FY26 earnings call available on its website.: Unverifiable

- Said: Transcript of Earnings Conference call with Analysts / Investors on Unaudited Financial Results (Consolidated and Standalone) of the Company for the quarter ended June 30, 2025, is available
- By: Rahul Shah, Q4 FY25 earnings call
- Verdict: Unverifiable
- Evidence: We could not match this promise to a figure, and no later call settles it.
- Filing: <https://nsearchives.nseindia.com/corporate/TORNTPOWER_07082025124239_Transcript.pdf> (page 1)

## 2025-03-31 · The company will make the transcript of the Q4 FY25 earnings call available on its website.: Unverifiable

- Said: Transcript of Earnings Conference call with Analysts / Investors on Audited Financial Results (Consolidated and Standalone) of the Company for the quarter and year ended March 31, 2025
- By: Rahul Shah, Q3 FY25 earnings call
- Verdict: Unverifiable
- Evidence: We could not match this promise to a figure, and no later call settles it.

## 2024-06-30 · The company will make the transcript of the Q1 FY25 earnings call available on its website.: Unverifiable

- Said: Transcript of Earnings Conference call with Analysts / Investors on Unaudited Financial Results (Consolidated and Standalone) of the Company for the quarter ended June 30, 2024, is available
- By: Rahul Shah, Q4 FY24 earnings call
- Verdict: Unverifiable
- Evidence: We could not match this promise to a figure, and no later call settles it.

Live record: https://eqdoc.com/stock/TORNTPOWER. Not investment advice.