type: "Promise Ledger"
title: "Vardhman Textiles Ltd: what management promised, and what happened"
description: "28 statements by Vardhman Textiles Ltd's management, each checked against the company's later filings: 5 kept, 4 slipped, 1 missed, 13 pending, 5 unverifiable."
resource: "https://eqdoc.com/stock/VTL"
tags: ["promise ledger","management guidance","india","vtl"]
sources: [{"resource":"https://nsearchives.nseindia.com/corporate/VTL_28072025174154_VTL.pdf"},{"resource":"https://nsearchives.nseindia.com/corporate/VTL_27012024175236_vtxl.pdf"}]
generated: {"by":"process:eqdoc-promise-audit","at":"2026-10-25"}
stale_after: "2027-02-02"
x-eqdoc-symbol: "VTL"
x-eqdoc-counts: {"kept":5,"slipped":4,"missed":1,"pending":13,"unverifiable":5}
---

# How to read this

Each entry is something management said it would do, when it said it, and whether the company's later filings show it happened.
- **Kept**: a later filing shows it done. **Slipped**: done late or in part. **Missed**: the deadline passed without it.
- **Pending**: the deadline has not come, or no later filing yet speaks to it. **Unverifiable**: no filing could settle it.
- Evidence is either a sentence built from figures the company filed, or a quote from a later company document, as marked.

# Promises

## 2026-07-30 · The company aims for 100% compliance with ZHDC MRSL standards by FY 2030.: Pending

- Said: 100% ZHDC MRSL Compliance by FY 2030
- By: Company presentation, Investor presentation, 30 Jul 2026
- Due: by FY 2030
- Verdict: Pending
- Evidence: Not due until 31 Mar 2030, after the latest results; later ones will show.

## 2026-07-30 · The company aims to reduce waste sent to landfills by 50% by 2030.: Pending

- Said: 50% Reduction in waste sent to landfill by 2030
- By: Company presentation, Investor presentation, 30 Jul 2026
- Due: by 2030
- Verdict: Pending
- Evidence: Not due until 31 Dec 2030, after the latest results; later ones will show.

## 2026-07-30 · The company commits to achieving net zero emissions by 2045.: Pending

- Said: Achieve Net Zero Emissions 2045
- By: Company presentation, Investor presentation, 30 Jul 2026
- Due: by 2045
- Verdict: Pending
- Evidence: Not due until 31 Dec 2045, after the latest results; later ones will show.

## 2026-07-30 · The company commits to using 100% sustainable packaging by FY 2030.: Pending

- Said: 100% Sustainable packaging by FY 2030
- By: Company presentation, Investor presentation, 30 Jul 2026
- Due: by FY 2030
- Verdict: Pending
- Evidence: Not due until 31 Mar 2030, after the latest results; later ones will show.

## 2026-07-30 · The company expects to complete its open-end project by FY 2027-28.: Pending

- Said: Open-end project to be completed by FY 2027 - 28
- By: Company presentation, Investor presentation, 30 Jul 2026
- Due: by FY 2027-28
- Verdict: Pending
- Evidence: Not due until 31 Mar 2027, after the latest results; later ones will show.

## 2026-07-30 · The company plans to reduce freshwater consumption by 30% by 2030.: Pending

- Said: 30% Reduction in freshwater consumption by 2030
- By: Company presentation, Investor presentation, 30 Jul 2026
- Due: by 2030
- Verdict: Pending
- Evidence: Not due until 31 Dec 2030, after the latest results; later ones will show.

## 2026-07-30 · The company targets generating 60% of its power from green sources by FY 2027-28.: Pending

- Said: Achieve 60% green power generation by FY 2027-28
- By: Company presentation, Investor presentation, 30 Jul 2026
- Due: by FY 2027-28
- Verdict: Pending
- Evidence: Not due until 31 Mar 2027, after the latest results; later ones will show.

## 2026-07-30 · The garment capacity expansion is expected to be completed by the end of FY 2026-27.: Unverifiable

- Said: Expected to be completed by end of FY2026-27
- By: Company presentation, Investor presentation, 30 Jul 2026
- Due: by the end of FY 2026-27
- Verdict: Unverifiable
- Evidence: We could not match this promise to a figure, and no later call settles it.

## 2026-07-30 · The green capex project is being implemented in phases with completion expected by FY27.: Pending

- Said: Being implemented in phases and expected completion by FY27
- By: Company presentation, Investor presentation, 30 Jul 2026
- Due: by FY27
- Verdict: Pending
- Evidence: Not due until 31 Mar 2027, after the latest results; later ones will show.

## 2025-07-28 · Biomass boiler project completion: Kept

- Said: we are going in for the biomass-based boilers where the cost of steam and the cost of power should come down. Those things will be applicable only once we complete the project, which will be close to about a year from today.
- Due: 2026-07-22
- Verdict: Kept
- Later filing says (2026-08-03): So we have started our boiler -- biomass boiler in Baddi last week only. And the another one in Madhya Pradesh is expected to start maybe in a month or so.
- Filing: <https://nsearchives.nseindia.com/corporate/VTL_28072025174154_VTL.pdf>

## 2025-07-28 · Energy conservation initiatives completion: Pending

- Said: initiatives within -- for our energy conservation within the operation both spinning and on the fabric side. So we've taken lots of initiatives on their side also, which I think we'll complete in next 6 months' time.
- Due: 2026-01-22
- Verdict: Pending
- Filing: <https://nsearchives.nseindia.com/corporate/VTL_28072025174154_VTL.pdf>

## 2025-07-28 · Fabric expansion revenue and margin contribution: Pending

- Said: Our fabric expansion is progressing as per schedule and we can expect it to begin contributing meaningfully to our top line and bottom line from quarter three onwards.
- Due: Q3 FY26
- Verdict: Pending
- Filing: <https://nsearchives.nseindia.com/corporate/VTL_28072025174154_VTL.pdf>

## 2025-07-28 · Fabric processing capacity expansion: Pending

- Said: On the fabric side, we are currently at 145 lakh meters per month process capacity. And in the next 3 to 4 years, this will go up to about 210 lakh meters per month.
- Due: FY29-FY30
- Verdict: Pending
- Filing: <https://nsearchives.nseindia.com/corporate/VTL_28072025174154_VTL.pdf>

## 2025-07-28 · New synthetic line launch: Slipped

- Said: And we also are excited and enthusiastic for our new synthetic line, which will be upcoming in quarter three.
- Due: Q3 FY26
- Verdict: Slipped
- Later filing says (2026-05-08): Commercial Production Started of 18 million meters annually in March FY26
- Filing: <https://nsearchives.nseindia.com/corporate/VTL_28072025174154_VTL.pdf>

## 2025-07-28 · Spinning production growth target: Kept

- Said: overall production, which used to be about 710, 720 tonnes would increase to about 750 tonnes or so. So that means a total of about 6% to 7% growth on the production side on the sales side.
- Verdict: Kept
- Later filing says (2026-05-08): Production (MT) 2,77,072 2,67,552 4%
- Filing: <https://nsearchives.nseindia.com/corporate/VTL_28072025174154_VTL.pdf>

## 2025-07-22 · The ReNova recycling plant and 14,000 spindles for Melange yarn are now operational.: Kept

- Said: Additionally, our capacity expansion in our mechanical recycling plant, ReNova, has successfully begun operations in July. And also the expanded capacity of 14,000 spindles in Melange yarn is now operational.
- By: management, Q1 FY26 earnings call
- Verdict: Kept
- Evidence: The Q3 FY26 call, 21 Jan 2026 settles it: “the fabric expansion at Budhni on our existing cotton blend lines has also been commissioned, and it is expected to gain momentum from Quarter 1 next year.”
- Filing: <https://nsearchives.nseindia.com/corporate/VTL_28072025174154_VTL.pdf> (page 4)

## 2025-05-05 · The company expects a 10% revenue increase in FY26.: Unverifiable

- Said: we can expect the revenue increase in FY26 by 10% and the year after that we can expect about 30%.
- By: Sagrika Jain, Q4 FY25 earnings call
- Due: in FY26
- Verdict: Unverifiable
- Evidence: We could not match this promise to a figure, and no later call settles it.

## 2025-05-05 · The company expects to achieve at least a 15% EBITDA margin on its expenditures.: Unverifiable

- Said: our expectation is always at least 15% EBITDA margin should come over and above the existing costs.
- By: Neeraj Jain, Q4 FY25 earnings call
- Verdict: Unverifiable
- Evidence: We could not match this promise to a figure, and no later call settles it.

## 2025-05-05 · The company expects to complete most of its modernization projects by September.: Unverifiable

- Said: I expect most of the modernization will be completed by September.
- By: Neeraj Jain, Q4 FY25 earnings call
- Verdict: Unverifiable
- Evidence: We could not match this promise to a figure, and no later call settles it.

## 2025-01-22 · The company expects its annual maintenance or replacement capital expenditure to be between 150 and 200 crores.: Pending

- Said: going forward the normal CAPEX or the replacement for CAPEX to my mind should not be more than 150, 200 crores per year.
- By: Neeraj Jain, Q3 FY25 earnings call
- Verdict: Pending
- Evidence: Not due yet, so it can't be checked.

## 2025-01-22 · The company expects to complete its capital expenditure for green power within the current calendar year.: Slipped

- Said: All that CAPEX is also likely to be completed within this calendar year.
- By: Neeraj Jain, Q3 FY25 earnings call
- Verdict: Slipped
- Evidence: The Q1 FY27 call, 31 Jul 2026 settles it: “all the power projects will be completed in the next 3 months' time.”

## 2024-08-01 · The company expects its fabric capacity to reach 200 million meters.: Unverifiable

- Said: About 200 millimeters.
- By: Neeraj Jain, Q1 FY25 earnings call
- Verdict: Unverifiable
- Evidence: We could not match this promise to a figure, and no later call settles it.

## 2024-08-01 · The company sees a possibility of reaching INR 10,000 crores in sales for the current financial year.: Missed

- Said: we feel there could be a possibility to go up to INR10,000 crores.
- By: Neeraj Jain, Q1 FY25 earnings call
- Verdict: Missed
- Evidence: Sales for FY25 came to ₹9,785 cr — short of the ₹10,000 cr promised, with the window closed.

## 2024-01-27 · Capex allocation for expansion: Kept

- Said: We have announced INR220 crores of capex, specifically for an expansion.
- Due: 2024-12-31
- Verdict: Kept
- Later filing says (2024-05-13): Awanish Chandra: Sir, first thing, last time we have talked about 200 crores small CAPEX. That is separate than what we have announced today. Management: Yes, that was CAPEX.
- Filing: <https://nsearchives.nseindia.com/corporate/VTL_27012024175236_vtxl.pdf>

## 2024-01-27 · FY25 maintenance capex continuation: Pending

- Said: And sir, this maintenance capex of like INR350 crores what we are having in FY '24, that will be continued even in the next year. Neeraj Jain: That's true, that's true.
- Due: FY25
- Verdict: Pending
- Filing: <https://nsearchives.nseindia.com/corporate/VTL_27012024175236_vtxl.pdf>

## 2024-01-27 · Melange business capacity expansion: Kept

- Said: So total capital outlays in the range of about INR200-plus crores, which will take -- which will give us additional production of 8, 9 tons per day
- Due: 2024-12-31
- Verdict: Kept
- Later filing says (2025-07-28): And also the expanded capacity of 14,000 spindles in Melange yarn is now operational.
- Filing: <https://nsearchives.nseindia.com/corporate/VTL_27012024175236_vtxl.pdf>

## 2024-01-27 · Melange capex completion timeline: Slipped

- Said: No, we will be completing it within, I think, calendar year '24.
- Due: 2024-12-31
- Verdict: Slipped
- Later filing says (2025-07-28): And also the expanded capacity of 14,000 spindles in Melange yarn is now operational.
- Filing: <https://nsearchives.nseindia.com/corporate/VTL_27012024175236_vtxl.pdf>

## 2024-01-27 · Spindle capacity addition: Slipped

- Said: Adding about 15,000 spindles.
- Due: 2024-12-31
- Verdict: Slipped
- Later filing says (2026-05-08): Expansion of about 15,600 spindles completed in H1 FY26
- Filing: <https://nsearchives.nseindia.com/corporate/VTL_27012024175236_vtxl.pdf>

Live record: https://eqdoc.com/stock/VTL. Not investment advice.