## Business model
A capital goods company sells the machine, not the output: transformers, switchgear, boilers, gears, cables, pumps, material-handling plant. Revenue is earned by **converting an order into a delivered, commissioned asset**, and a rupee of revenue arrives only when a contractual milestone is met — so the P&L is a lagged, smoothed picture of an order book won months or years earlier. CRISIL (Feb 2024) names the sector's defining features as "multi-year order books, long product cycles, replacement demand, and large working capital requirement", and says revenue "tends to be bunched up depending on the order book and delivery schedule". Two consequences follow. First, **demand is derived**: it is the capex budget of somebody else — power utilities, steel, cement, railways, refineries — so the cycle is the customer's investment cycle, partially cushioned by replacement and spares demand (CRISIL). Second, **price is fixed before cost is known**: the order is priced at tender, the steel and copper are bought over the following quarters, and whoever bears that gap earns or loses the margin. It is the largest industrial sector in India — 27% of all factories, 1.9% of GDP, capital goods production of Rs 5,69,900 crore in FY25 of which heavy electrical equipment is Rs 3,72,200 crore, and engineering exports of Rs 10,82,729 crore in FY26 (IBEF, Sep 2026).

## First segmentation: cycle length decides whether any ratio means anything
Before reading a single number, decide **how long the company's order takes to execute**. The ratios do not merely differ between a catalogue-product maker and a project contractor — they invert.

| Axis | Short-cycle product | Long-cycle engineered-to-order / project |
|---|---|---|
| What is sold | Catalogue or lightly-configured equipment, shipped from stock or a short build slot | A designed, site-erected plant or system, executed over 1–3+ years |
| Order book vs revenue | Small; a book below one year's sales is normal, not weak. Elecon's open order was Rs 1,226 cr at 30 Sep 2025 against FY26 revenue guidance of Rs 2,650 cr — roughly 0.5x | Large by necessity; ICRA compares the order-book-to-operating-income (OB/OI) ratio against the **weighted-average residual execution time** of the book |
| Working capital | Inventory-led. CRISIL: average raw-material inventory holding is "over three months" | Receivable- and claim-led: retention money, milestone billing, mobilisation advances (ICRA: "generally 10% of the total project value"), bank guarantees |
| Input-price risk | Repriced each order or each list revision; short exposure window | Locked for years. ICRA: an entity on a fixed-price contract "has to absorb this increase in prices, which in turn would drive down its profit margins" |
| Reads as a red flag when | Order book swells far beyond capacity to build | OB/OI is very high — ICRA warns a large ratio "could be the result of aggressive bidding" and bring "enhanced execution risks" |

A high order book is therefore **not** a quality signal on its own; it is a quality signal only against execution capacity and bid discipline. **[reasoning]** Our financials carry no order book at all, so this axis must be set from disclosures before the computed ratios are interpreted.

## Key success factors
1. **Bid discipline, not bid volume.** ICRA assesses the bid success ratio and, for large orders, "the difference between the top two bids (lowest bid or L1, and second lowest or L2)" to detect aggressive bidding, "in which case the profitability could be lower". Winning cheap converts an order book into a loss-making backlog that cannot be repriced.
2. **Contractual pass-through of steel and copper — partial by construction.** The Indian electrical industry's standard answer is the IEEMA Price Variation Clause, which settles "variation in the basic price of raw materials from the period of tendering till the date of delivery" and "give[s] variations on both sides, either upwards or downwards", with formulae published for transformers, cables, conductors, switchgear, motors and towers (IEEMA). Crucially, such clauses index only a **slice** of the price: ABB's own escalation instruction sets price as `P1 = P0 × {x% + [y%×(LME Cu ratio) + z%×(CRU HR-coil ratio)]}`, where `x` is "fixed proportion of the contract price (not subject to price escalation)" — and `x` is 81% for MV switchgear up to 24kV, 63% for LV switchgear, but only 20% for a copper-heavy busway. The residual is management's risk, and ABB's clause triggers only when the deviation exceeds "+/- 2%". So pass-through is real, product-specific, and incomplete.
3. **Raw material is the dominant cost block and it is mostly metal.** CRISIL: "Raw materials, mainly equipment components and steel sheets, account for 55-60% of operating income." CARE adds the pricing-power test that decides who absorbs a metal spike: where prices "are driven by market forces like the landed cost of imports, etc., ... even a large player may not be in a position to pass on the increase in the input costs", and it checks whether gross margin is sufficient "to absorb the other operating costs and fixed costs".
4. **Working capital is the sector's real balance-sheet risk.** CRISIL calls out "high interest incidence given its large working capital requirement and sizeable debt". CARE notes that "a negative cash flow from operations may imply a high amount of funds being employed in working capital requirements and exhibit the working capital intensity of operations". ICRA looks for "any significant deviation" in debtor and inventory days as "an indication of a possible dispute with a client".
5. **Off-balance-sheet exposure grows with the book.** ICRA: bank guarantees for bid security, performance security and retention release "form a sizeable part of the contractor's contingent liabilities", and "for construction entities with long execution cycle and defect liability period, the BG requirement keeps on adding over time". Non-fund limits, not just debt, gate how much work a company can bid for.
6. **Customer mix sets both the payment cycle and the counterparty risk.** ICRA: public-sector orders "provide more stability to revenues as they are relatively less prone to economic cycles" and carry lower counterparty credit risk, while private orders have "a shorter and less cumbersome bidding process"; a healthy mix of both is best. CRISIL warns that client concentration makes an engineering company "vulnerable to the performance and sourcing strategies, pricing decisions, and overall business plans of these customers".
7. **Technology tier is the durable moat.** CRISIL: "In high-technology areas, multinationals typically offer stiff competition to home-grown engineering firms. For low-technology products, there could be intense competition from unorganised players", and companies providing "total solutions encompassing product design, service and implementation" enjoy higher margins than pure manufacturers. Spares and after-sales carry higher margins and stabilise revenue (CRISIL).
8. **The demand cycle is presently policy-fed, which is a dependency as much as a tailwind.** Union Budget 2026-27 raises capital expenditure to Rs 12,21,821 crore from Rs 10,95,755 crore (RE 2025-26), +11.5%, with Road Transport and Highways at Rs 3,09,875 crore and Railways at Rs 2,81,377 crore, plus an Infrastructure Risk Guarantee Fund and new "Schemes ... for Enhancement of Construction and Infrastructure Equipments" (PRS, Feb 2026). ICRA (18 Jun 2026) sees "investment-led segments, including capital goods and infrastructure, ... benefit from a rising order book", with private capex standing out in "defence, electronics manufacturing, electric mobility and other production-linked incentive-supported segments, power equipment".
9. **Import competition is a live, policy-mediated risk.** In July 2026 four Chinese-owned electrical equipment makers were granted a two-year exemption under the Public Procurement Order to bid for select transmission equipment, with GIS, transformers, reactors, circuit breakers, insulators and bushings named as facing heightened competition (PL Capital, 6 Jul 2026 — a brokerage note, not a regulator's text). Protection here is administrative and can be withdrawn. **[reasoning]** That makes domestic-preference policy a monitorable, not a moat.

## Metrics — what we CAN compute
Bands are the live ones in `pipeline/reference/eqscore_sectors/capital-goods.json`; the scorer section below states them in full.

| Metric | How | What "good" looks like |
|---|---|---|
| Operating margin level | `opm_avg`, 5–6y mean | Full credit at ≥ 14%, no credit at ≤ 8%. Above 14% the scorer also labels the company "Strong pricing power" |
| Margin stability | `opm_sd` ≤ 4pp and no collapse (last year < avg − 8pp) | Steady margins through the customer's capex cycle; a collapse year is the fixed-price/cost-overrun tell |
| Return on capital | `roce_avg`, 5y | Full credit at ≥ 15%, none at ≤ 10% — this is the framework default, not a sector-chosen bar |
| Input-cost intensity | `rm_share` = raw material ÷ sales | Full credit at ≤ 68%, none at ≥ 80%. The band is deliberately loose: CRISIL puts sector raw material at 55-60% of operating income |
| Margin squeeze | consecutive years where RM share rose > 1pp **and** OPM fell > 0.5pp | Zero such years. This is the computable proxy for failed pass-through |
| Receivable days | `debtor_days` | Full credit at ≤ 75 days, none at ≥ 120 |
| Inventory days | `inv_days` | Full credit at ≤ 75 days, none at ≥ 120 — consistent with CRISIL's "over three months" raw-material holding |
| Cash conversion | `cfo_pat` = 5y CFO ÷ 5y PAT | ≥ 100% for full credit, nothing at ≤ 60%. Directly tests CARE's working-capital-intensity warning |
| Free cash flow | 5–6y `fcf` sum > 0 | Positive across the cycle; a project business that never converts profit to cash is funding somebody else's plant |
| Leverage & cover | `de`; `int_cov` | D/E ≤ 0.7 and cover ≥ 5 for full credit; D/E > 1.2 or cover < 2.5 earns nothing. Credit is the **weaker** of the two |
| Other-income reliance | `oi_pbt` | ≤ 20% of PBT for full credit, nothing above 30%. Arbitration and claim settlements land here — Elecon's H1FY26 included Rs 25 cr of one-time arbitration income |
| Revenue durability | no collapsed revenue spike | A won-then-lost order surge is not growth |
| Size | latest annual sales, log-scaled | Rs 1,000 cr full, Rs 250 cr floor. CARE: large size brings "economies of scale, higher bargaining power" and eligibility for larger tenders |

## Metrics we CANNOT get from financials
- **The order book itself** — size, and therefore book-to-bill, OB/OI and CRISIL's "new orders and order backlog", "book-to-bill ratio", "bidding success rates". This is the sector's single most important number and it is absent from our P&L and balance sheet.
- **Order book quality** — ICRA's stage-of-execution mix, slow-moving or stuck orders (which it *excludes* from the book before judging visibility), and CRISIL's "quality of order book in terms of counterparties, funding, approval status, and price escalation clauses".
- **Order concentration** — ICRA's top-five-projects share of the book, "typically more than 65-70%" indicating high concentration risk.
- **Price-variation clause coverage** — whether contracts carry an IEEMA-style PVC at all, and what fraction of contract value is indexed versus ABB's fixed `x%`. Nothing in the financials distinguishes a fully-indexed book from a fixed-price one until the margin has already gone.
- **Retention money, mobilisation advances and bank guarantees** — ICRA's non-fund-based limits and contingent liabilities; the advance is a liability whose interest-bearing status must be read from the notes.
- **Claims and arbitration** — ICRA views recognising claims as revenue "without the final settlement" negatively. Whether reported profit contains unsettled claims needs the notes to accounts.
- **Fixed-price versus escalation split of the backlog**, liquidated-damages exposure, and penalty clauses (ICRA).
- **Technology tier, spares/after-market share, and import exposure** — the CRISIL moat and the PL Capital competition risk; segment disclosure at best, never a ratio.
- **Capacity, utilisation and execution track record** — ICRA's OI/GB ratio and its assessment of adherence to "quality and time parameters".

## Red flags
- Order book growing while margins fall — the L1/L2 signature of buying revenue below cost (ICRA).
- A margin-collapse year after a metal spike: input share up, OPM down, two or more years running — a fixed-price book meeting an unhedged input, which is exactly the ICRA fixed-price mechanism.
- Receivable or inventory days stepping up out of line with the company's own history — ICRA reads this as "a possible dispute with a client with regard to certification of work executed".
- Profit without cash: multi-year CFO well below PAT, or persistently negative FCF while the order book grows — the working capital is eating the business (CARE).
- Reported profit leaning on other income, arbitration awards or claim settlements rather than delivery.
- Contingent liabilities and bank guarantees rising faster than the order book, with thin unutilised non-fund limits — bid capacity is exhausted (ICRA).
- Top-five orders above roughly two-thirds of the book, or a single government counterparty funding most of it (ICRA).
- Debt-funded capacity added into a policy-fed upcycle: the demand is a budget line (PRS), and the domestic-preference protection is administrative and revocable (PL Capital).
- A single-technology, low-tech product line facing unorganised-sector or import price competition, with no spares or service annuity (CRISIL).

## One-line screen intent
A strong capital goods company is a **technology-differentiated equipment maker that converts a disciplined order book into cash** — margins at or above 14% and steady through the customer's capex cycle, ROCE clearing 15%, raw-material share contained and pass-through working (no multi-year squeeze), receivables and inventory each inside ~75 days, five-year CFO at least matching PAT with positive FCF, and low debt with real interest cover — whose order book size, quality, concentration, price-variation coverage and guarantee load are verified outside the financials before the ratios are believed.

## How the live EqScore scorer measures this sector (2026-09-16)

Read from `pipeline/reference/eqscore_sectors/capital-goods.json` and `pipeline/jobs/eqscore.py` at write time.

**Framework: `standard`.** The JSON declares no `framework` key, and `sector_pass` resolves `S.get("framework") or "standard"`, so companies are scored by `score_company` on industrial bands — margins, ROCE, debt, working capital, cash — rather than the `bank`, `lender` or `insurance` cards. A company whose own warehouse row carries a different framework is scored on **its** framework, not the guide's.

**Shared mechanics.** Each numeric check earns the fraction of its weight measured from the half band to the full band: full weight at the full band or better, zero at the half band or worse, linear in between, hard clamp above full (`grade`); `full == half` degenerates to the old hard step. Verdict labels (pass/half/fail) still come from the raw band comparison, so a check can read "half" while earning any fraction. Score = points earned ÷ points **attempted** × 100, rounded with Python's banker's rounding (half to even). An `na` check leaves **both** sides of that ratio — a company is not punished for a figure nobody published — except a label the company made unmeasurable through its own accounting, which keeps its weight and earns nothing. Below `MIN_COVERAGE = 0.70` of checklist weight, no score is published at all. No market value → no score (`r["mcap"]` falsy is an absence, not a threshold). Below `EXCELLENT_MCAP_FLOOR = 500` crore a score of 80+ is held at 79. Incomplete checklists are then blended one way toward the median of full-coverage peers in the same sector — it can lower a score, never raise one. The verified-events overlay (clamped to [−20, +100]) and the pledge ramp (no effect below 15%, −6 points at 50%, −12 at 100%) sit on top.

**Checks this guide arms** (120 points attempted at the sector level):

| Check label | Metric | Full credit | Zero credit at/beyond | Weight |
|---|---|---|---|---|
| Healthy profit margins | Avg operating margin (5–6y), % | ≥ 14 | 8 | 20 |
| Steady margins | OPM std-dev ≤ 4pp and no collapse (last year < avg − 8pp) | boolean | — | 10 |
| Good return on capital | Avg ROCE (5y), % | ≥ 15 | 10 | 15 |
| Generates real cash | 5–6y FCF sum > 0 | boolean | — | 10 |
| Low debt | Weaker of D/E and interest-cover fractions | D/E ≤ 0.7, cover ≥ 5 | D/E > 1.2, cover < 2.5 | 10 |
| Gets paid on time | Debtor days | ≤ 75 | 120 | 10 |
| Doesn't just resell inputs | Raw-material cost % of sales | ≤ 68 | 80 | 10 |
| Profits come from the business | Other income % of PBT | ≤ 20 | 30 | 5 |
| No boom-and-bust | No collapsed revenue spike | boolean | — | 5 |
| Real cash behind profits | 5y CFO as % of 5y PAT | ≥ 100 | 60 | 10 |
| No margin squeeze | Consecutive years of RM share +1pp with OPM −0.5pp | 0 years; half credit at exactly 1 | — | 5 |
| Inventory moves | Inventory days | ≤ 75 | 120 | 5 |
| Meaningful size | Latest annual sales, Rs cr (log scale) | ≥ 1,000 | 250 | 5 |

Four standard-framework checks stay **off** because the guide sets no bands for them: "Liabilities under control" (`tol_full` null), "Wages in step with sales" (`ecd_full` null), "Sales kept growing" (`g_full` null) and "Assets earn their keep" (`nfa_full` null). `fcf_relief` is off, so negative five-year FCF is a fail, not half credit. There is no `weights` override, so every weight above is the engine default. The segment label uses the same margin bars: ≥ 14% "Strong pricing power", ≥ 8% "Moderate pricing power", below that "Low pricing power".

**Subsection — `cables-electricals` (Cable & wire makers).** `match` is the vendor taxonomy rule `sector in ["Cables - Electricals"]`; taxonomy matches are tier B, so an explicit symbol pin would outrank it, and there are no pins here. It overrides exactly two bands, setting `rm_full` and `rm_half` to null, which **retires the "Doesn't just resell inputs" check** and drops attempted points from 120 to 110 for this cohort. Every other band is inherited. The guide's own stated reason, quoted from its `why`: a cable maker "passes copper and aluminium through to the customer: the cohort's entire raw-material range is 74-85% of sales — an 11-point spread the metal price dictates, not management", judged on the sector band "RR Kabel and Finolex Cables scored zero on a check that was measuring the copper price, and no band inside so tight a range ranks anything real", so "margins, returns, debt and the cash checks — where cable makers genuinely differ — carry the weight instead". That 74-85% range is the repo's own measurement of its cohort, not an external published figure; independently, Polycab describes a "disciplined back-to-back metal booking approach to neutralise raw material price volatility (specifically copper and aluminium)" (Integrated Annual Report 2025-26), which is consistent with the metal being a pass-through rather than a management cost decision.

**Why these bands — what the file does and does not say.** Unlike some sector configs, `capital-goods.json` carries **no `scoring_notes` field**: the only recorded rationale anywhere in it is the subsection `why` quoted above. So the bands below are stated, not explained, and this document will not invent reasons for them. What can be established by comparing the file with `STANDARD_DEFAULTS` in `eqscore.py`:

- **Inherited, not chosen for this sector:** ROCE 15/10 and size 1,000/250 are identical to the framework defaults, as is the "Steady margins" 4pp bar (`opm_sd_max` is not set here) and other income 20/30.
- **Loosened against the default:** raw material 68/80 versus a 45/55 default, and inventory days armed at 75/120. Both move with CRISIL's 55-60% raw-material share and "over three months" inventory holding, so the direction is consistent with the sector's published cost structure, though the file does not say this.
- **Tightened against the default:** margins 14/8 versus 22/12, debtor days 75/120 versus 120/180, and debt converted from the degenerate step (D/E 1/1, cover 4/4) to graded 0.7/1.2 with cover 5/2.5. The margin cut is directionally unsurprising for an order-driven sector, but **the 75-day debtor bar is the one band this document cannot account for**: it is stricter than the framework default in a sector every agency read describes as working-capital-heavy, with retention money and milestone billing. It fits a short-cycle product maker and sits awkwardly on a project contractor, and neither the JSON nor the scorer records why it was set there.
- **Armed optional checks:** "Real cash behind profits" (`cfopat` 100/60) and "No margin squeeze" (`sqz_check: true`). Both bear directly on sourced mechanisms — CARE's working-capital-intensity test and ICRA's fixed-price absorption — but again, the file states no reason.

`method_version` is `"m" + SCORER_REV + "." + sha256(payload)[:8]`, currently the `m2.` prefix, and the payload includes this guide's `scoring` block and its subsections' `scoring` blocks alongside the gates, penalty table and aliases — so editing any band above changes the published method version.

# EqScore checks

The checks eqdoc scores a company in this sector on (its [EqScore](https://eqdoc.com/guide/capital-goods)), in the order of the card.

| Factor | The question | Good | Red flag |
|---|---|---|---|
| Order book to revenue (revenue visibility) | Is the order book sized sensibly against revenue AND against the weighted-average residual execution time of the book? | book consistent with execution capacity; short-cycle product makers can sit below 1x, project businesses need multi-year cover | ICRA: a large OB/OI ratio 'could be the result of aggressive bidding' and brings enhanced execution risk; a very low ratio can signal lost bid capacity |
| Order book quality | Is the book made of funded, approved, mid-execution orders from creditworthy counterparties rather than stuck or nascent ones? | healthy public/private mix, funding and approvals in place, slow-moving orders excluded before judging visibility | stuck or unfunded orders padding the book; skew to nascent or nearly-complete projects distorts medium-term revenue |
| Order and client concentration | Is the order book spread across projects, clients, segments and geographies? | diversified book; no single counterparty funding the majority of it | ICRA: top five projects above ~65-70% of the book indicates high project concentration and counterparty risk |
| Price-variation clause coverage | Do contracts carry an IEEMA-style price variation or commodity escalation clause, and what share of contract value is actually indexed? | PVC-linked orders with a large indexed proportion; escalation tied to the actual metal index rather than a broad inflation measure | fixed-price backlog, or escalation capped to WPI-style inflation while steel/copper move far more — the contractor absorbs the gap |
| Input-cost intensity | Is raw material a contained share of sales for this cohort (steel sheets, copper, components)? | at or below 68% of sales; CRISIL puts sector raw material at 55-60% of operating income | raw material at or above 80% of sales = a metal reseller with no engineering value added (check retired for cable makers, where the metal is a pass-through) |
| Pass-through actually working | Has the company avoided consecutive years where raw-material share rose and operating margin fell together? | zero squeeze years — input costs recovered through price or clause | two or more consecutive squeeze years = fixed-price book meeting an unhedged input; the computable signature of failed pass-through |
| Operating margin level / pricing power | Does the average operating margin clear the sector bar, indicating engineering value rather than assembly? | 5-6y average at or above 14%; total-solution and high-technology players earn more than pure manufacturers | average at or below 8% = low-technology product facing unorganised or import price competition |
| Margin stability through the capex cycle | Do margins hold steady across the customer's investment cycle, with no collapse year? | std-dev within 4pp and no year falling more than 8pp below the average | a collapse year is the cost-overrun / fixed-price tell, and replacement demand should have cushioned the down-leg |
| Return on capital | Does ROCE clear the cost of capital across the cycle given the working capital the business ties up? | 5y average at or above 15% | at or below 10% while the order book grows = capital sunk into receivables and inventory, not returns |
| Receivable and inventory discipline | Are debtor days and inventory days contained and stable against the company's own history? | each within about 75 days and trending flat; CRISIL notes raw-material holding alone runs over three months | ICRA: a significant deviation in debtor or inventory days indicates 'a possible dispute with a client with regard to certification of work executed' |
| Cash conversion / earnings quality | Does multi-year operating cash flow match reported profit, and is through-cycle free cash flow positive? | 5y CFO at least 100% of 5y PAT and positive FCF sum | CARE: negative CFO 'may imply a high amount of funds being employed in working capital requirements' — profit that never becomes cash |
| Leverage and interest cover | Is debt low and interest cover strong enough to fund the working capital cycle without distress? | D/E at or below 0.7 with cover at or above 5x | CRISIL flags the sector's 'high interest incidence given its large working capital requirement and sizeable debt'; D/E above 1.2 or cover below 2.5 earns nothing |
| Guarantees, retention money and advances | Are bank guarantees and contingent liabilities proportionate to the book, with unutilised non-fund limits left to bid with? | ample unutilised non-fund lines; mobilisation advances (ICRA: generally 10% of project value) non-interest-bearing | ICRA: for long execution cycles and defect liability periods 'the BG requirement keeps on adding over time' — exhausted non-fund limits cap bid capacity |
| Claims and arbitration in reported earnings | Is reported profit free of unsettled claims, and are counter-claims adequately provided for? | claims recognised only on settlement; disputes disclosed in contingent liabilities | ICRA views recognising claims as revenue 'without the final settlement' negatively; one-time arbitration income flattering a weak delivery year |
| Technology tier and import competition | Is the product high-technology or total-solution, with a spares and after-market annuity, rather than commoditised? | differentiated technology, design-to-commissioning capability, meaningful spares/service revenue | low-technology line exposed to unorganised players and to import competition whose only shield is a revocable domestic-preference rule |