eqdoc's guide to the Capital Goods sector: what drives its results and the figures to check in a filing.
A capital goods company sells the machine, not the output: transformers, switchgear, boilers, gears, cables, pumps, material-handling plant. Revenue is earned by converting an order into a delivered, commissioned asset, and a rupee of revenue arrives only when a contractual milestone is met — so the P&L is a lagged, smoothed picture of an order book won months or years earlier. CRISIL (Feb 2024) names the sector's defining features as "multi-year order books, long product cycles, replacement demand, and large working capital requirement", and says revenue "tends to be bunched up depending on the order book and delivery schedule". Two consequences follow. First, demand is derived: it is the capex budget of somebody else — power utilities, steel, cement, railways, refineries — so the cycle is the customer's investment cycle, partially cushioned by replacement and spares demand (CRISIL). Second, price is fixed before cost is known: the order is priced at tender, the steel and copper are bought over the following quarters, and whoever bears that gap earns or loses the margin. It is the largest industrial sector in India — 27% of all factories, 1.9% of GDP, capital goods production of Rs 5,69,900 crore in FY25 of which heavy electrical equipment is Rs 3,72,200 crore, and engineering exports of Rs 10,82,729 crore in FY26 (IBEF, Sep 2026).
Before reading a single number, decide how long the company's order takes to execute. The ratios do not merely differ between a catalogue-product maker and a project contractor — they invert.
| Axis | Short-cycle product | Long-cycle engineered-to-order / project |
|---|---|---|
| What is sold | Catalogue or lightly-configured equipment, shipped from stock or a short build slot | A designed, site-erected plant or system, executed over 1–3+ years |
| Order book vs revenue | Small; a book below one year's sales is normal, not weak. Elecon's open order was Rs 1,226 cr at 30 Sep 2025 against FY26 revenue guidance of Rs 2,650 cr — roughly 0.5x | Large by necessity; ICRA compares the order-book-to-operating-income (OB/OI) ratio against the weighted-average residual execution time of the book |
| Working capital | Inventory-led. CRISIL: average raw-material inventory holding is "over three months" | Receivable- and claim-led: retention money, milestone billing, mobilisation advances (ICRA: "generally 10% of the total project value"), bank guarantees |
| Input-price risk | Repriced each order or each list revision; short exposure window | Locked for years. ICRA: an entity on a fixed-price contract "has to absorb this increase in prices, which in turn would drive down its profit margins" |
| Reads as a red flag when | Order book swells far beyond capacity to build | OB/OI is very high — ICRA warns a large ratio "could be the result of aggressive bidding" and bring "enhanced execution risks" |
A high order book is therefore not a quality signal on its own; it is a quality signal only against execution capacity and bid discipline. [reasoning] Our financials carry no order book at all, so this axis must be set from disclosures before the computed ratios are interpreted.
1. Bid discipline, not bid volume. ICRA assesses the bid success ratio and, for large orders, "the difference between the top two bids (lowest bid or L1, and second lowest or L2)" to detect aggressive bidding, "in which case the profitability could be lower". Winning cheap converts an order book into a loss-making backlog that cannot be repriced.
2. Contractual pass-through of steel and copper — partial by construction. The Indian electrical industry's standard answer is the IEEMA Price Variation Clause, which settles "variation in the basic price of raw materials from the period of tendering till the date of delivery" and "give[s] variations on both sides, either upwards or downwards", with formulae published for transformers, cables, conductors, switchgear, motors and towers (IEEMA). Crucially, such clauses index only a slice of the price: ABB's own escalation instruction sets price as `P1 = P0 × {x% + [y%×(LME Cu ratio) + z%×(CRU HR-coil ratio)]}`, where `x` is "fixed proportion of the contract price (not subject to price escalation)" — and `x` is 81% for MV switchgear up to 24kV, 63% for LV switchgear, but only 20% for a copper-heavy busway. The residual is management's risk, and ABB's clause triggers only when the deviation exceeds "+/- 2%". So pass-through is real, product-specific, and incomplete.
3. Raw material is the dominant cost block and it is mostly metal. CRISIL: "Raw materials, mainly equipment components and steel sheets, account for 55-60% of operating income." CARE adds the pricing-power test that decides who absorbs a metal spike: where prices "are driven by market forces like the landed cost of imports, etc., ... even a large player may not be in a position to pass on the increase in the input costs", and it checks whether gross margin is sufficient "to absorb the other operating costs and fixed costs".
4. Working capital is the sector's real balance-sheet risk. CRISIL calls out "high interest incidence given its large working capital requirement and sizeable debt". CARE notes that "a negative cash flow from operations may imply a high amount of funds being employed in working capital requirements and exhibit the working capital intensity of operations". ICRA looks for "any significant deviation" in debtor and inventory days as "an indication of a possible dispute with a client".
5. Off-balance-sheet exposure grows with the book. ICRA: bank guarantees for bid security, performance security and retention release "form a sizeable part of the contractor's contingent liabilities", and "for construction entities with long execution cycle and defect liability period, the BG requirement keeps on adding over time". Non-fund limits, not just debt, gate how much work a company can bid for.
6. Customer mix sets both the payment cycle and the counterparty risk. ICRA: public-sector orders "provide more stability to revenues as they are relatively less prone to economic cycles" and carry lower counterparty credit risk, while private orders have "a shorter and less cumbersome bidding process"; a healthy mix of both is best. CRISIL warns that client concentration makes an engineering company "vulnerable to the performance and sourcing strategies, pricing decisions, and overall business plans of these customers".